The Parks Crew opened the ice rinks on Friday, December 12tn, the earliest in history.
The hockey nets were brought out to the rinks and trash barrels to the warming houses.
They plowed the cul-de-sacs, pedways, parking lots and ice rinks.
Rick plowed the lift stations and cul-de-sacs. He did a sanitary sewer line repair
inspection on Alice Lane.
The Streets crew cleaned the bridge deck and sidewalks on Wagon Wheel Trail and
Mendota Heights Road. They mixed salt with sand.
Snow Events for the Week:
Date: Amount: Response:
12-14-08 Rain/Ice/snow Salt all mains and hills
12-15-08 2-1/2" snow Plow all streets and salt
(3:00 A.M. start)
12-16-08 started snowing Salt all mains and hills
(afternoon) (stayed through rush hour)
(came back at midnight)
12-17-08 2" snow Plow all streets and salt
0
Engineering
Staff has continued to work with representatives of Mendota Mall Associates on the
application for the redevelopment of the Mendota Plaza. Staff has been keeping a list of
issues and working with the applicant to address the concerns of the Planning Commission
and Council. A hearing before Council is scheduled for January 6tn
Staff is working on the completion of a Stormwater Management Ordinance that is a
requirement of our Municipal Separated Sanitary and Storm Sewer (MS4) permit. The
Ordinance is scheduled to be before Council in January.
Staff is working with Dakota County on the renewal of Joint Powers Agreements for
Wetland Health Assessment and pavement cracksealing/sealcoating. These agreements
are anticipated to be before Council for approval on January 6tn
Staff is ready to prepare Feasibility Reports for the upcoming 2009 street reconstruction
and rehabilitation projects. Resolutions authorizing the production of these reports will be
presented to Council on January 6tn
LETT,E R The Pipeline
Public Works -�
Engineering December 12, 2008
Code Enforcement
Public Works
The Parks Crew plowed the pedways, parking lots and cul-de-sacs. They are still flooding
ice rinks. The hockey nets were rewired and retied.
Rich plowed all the lift stations, middle area of the city on Saturday morning and Monday
morning. On Tuesday he plowed cul-de-sacs and assisted the Parks Crew with the ice
rinks. A new hydrant flag was replaced on Summit Lane.
The Streets Crew changed the wing cutting edges on plow truck #312. All plow trucks
were washed and the sanders and wings were greased. The wing front plow was put on
truck 308, was greased and the hydro fitting was changed because of a leak. The front
cutting edge was changed on plow truck 312.
Snow Events of the Week:
Date:
Amount:
Response:
Saturday, December 6
1.5" snow
Plow all street and salt
Monday, December 8
1.5" snow
Plow all mains and salt
Tuesday, December 9
4" snow
Plow all streets and salt
(12:00 A.M. start)
Engineering
Engineering is putting together feasibility reports for next years proposed road
reconstruction and rehabilitation projects. Surveying has been completed on Hunter Lane,
Orchard Circle and Culligan Lane. RFP's have been mailed for soil borings, and SPRWS is
assessing the water main for potential replacement. Feasibility reports will go to council
in January with public hearings likely in February.
Engineering staff is continuing to work out detail issues with Paster Enterprises on the
redevelopment of the Mendota Mall. Staff received revised plans this past Thursday, and
will be meeting with the applicant on Tuesday (12/16). Staff will provide an update to
Council at the 12/16 Council Meeting.
Engineering staff is working on the final details for a Citywide Stormwater Management
Ordinance. This ordinance is a requirement of our MPCA permit and is anticipated to be
before Council in January.
Code Enforcement
A building permit was issued this week to Gunderson Construction LLC for a $500,000
addition/remodel for Somerset Country Club pool house.
LETTIE R ,)The Pipelin
Public Works December 5, 2008
Engineering
Code Enforcement
Public Works
The Parks Crew went through the warming houses and checked the furnaces. They
started flooding the skating rinks. The lights were checked at the hockey rinks
and light bulbs were replaced as needed. Summer equipment was winterized and
stored in the water tower. The pedways and parking lots were plowed Monday
and Wednesday.
Rich repaired the water shut off valve box on Trail Road. He changed out the
broken panel heater at the Centre Pointe lift station. He plowed the lift stations on
Monday and Wednesday.
The Streets Crew cut down pine trees at 1327 Sylvandale Road that were low
hanging and had become a safety hazard. The homeowner kept the wood for
firewood. The sander was installed on truck 303 - John Ambrose made a new
bracket to hold the sander on the truck and new hoses and hydraulic plumbing
was installed. "No Dumping" signs were installed in the easement on Ridge Place
and Wachtler Avenue. Storm gates were cleaned on Woodridge and Cascade. The
sander and wing were installed on truck 308. New street name signs were made
up for Ashley Lane, Norma Lane, Ellen Street and Chippewa Avenue.
Snow Events
Date: Amount: Response:
Saturday, November 22 1
/2" salt all areas
Sunday, November 30 1.5" plow main lines and salt
Wednesday, December 3 i" 1" plow main lines and salt (4:00 A.M.
start)
Engineering
Staff met with representatives form Mendota Mall Associates to discuss the
redevelopment of the Mendota Plaza property at Dodd Road and Highway 110.
Many outstanding issues were ironed out and agreed upon, with further issues to
be worked on in December. Mendota Mall Associates plans on having their
application in front of City Council at the January 6th meeting.
Staff executed an administrative warrant to inspect the property located at 694
Wentworth Avenue. Staff found a number of issues which are currently being
worked through with the City Attorney. An update is planned for the December
2"d City Council meeting.
Staff met with representatives of MnDOT, Dakota County, Eagan, and Inver Grove
Heights to discuss the potential for an interchange at Delaware Avenue and
Interstate 494. Staff reiterated the City's position opposing the construction of the
interchange. Dakota County will be completing an area traffic study in 2009 that
will include the potential for the interchange. Staff asked to be part of that
process to ensure the City's desires are included.
Attachment
Please see attached email from Council Member Vitelli.
From: Jack Vitelli [mailto:j.vitelli@comcast.net]
Sent: Thursday, November 20, 2008 11:34 AM
To: pwsuper@infinetivity.com
Cc: John R. Mazzitello; Jim Danielson; 'John Huber'
Subject: Tree Removal
Tell your "tree removal team" that I am very impressed with their
professionalism in removing the tree from across the street from my
home.
George really knows how to operate that BobCat. He handles it in a
manner that it just becomes one of his own hands. They had to avoid
ruining an Xcel box and a Comcast box but George positioned the
BobCat grappler in exactly the right position and the tree toppled just
where it should have to avoid any damage to the boxes. Great work.
Further, they are finishing up the job right now and they have only
been here about 30 minutes. I am impressed.
Jack Vitelli
651-455-5625
651-357-7616 cell
320-233-6006 lake
N E w s The Pipeline
LETTER -
Public Works
Engineering c November 21, 2008
Code Enforcement
Public Works
The Parks Crew repaired a downed pedway sign on Rogers Lake pedway. A
downed tree on the pedway in Valley Park was removed. The aerator at
Rogers Lake was set up for winter. The decking was repaired in front of the
warming house at Wentworth Park. The dog waste sign was replaced at Ivy
Falls Park in the parking lot.
Rich checked First through Fourth Avenues with the contractor to make sure
the manholes were clean and working fine. He televised the sanitary sewer
lines on Callahan Place with the Engineering Department. On Wednesday,
he attended the annual pesticide applicators recertification seminar.
The Streets crew started installing the wing sanders on the plow trucks.
The curbs were marked in Town Center for snow plowing. Truck 303 was
brought to Kramer for a D.O.T. inspection. Salt was delivered to Public
Works. They blacktopped Hunter Lane, Culligan Lane, Glen Hill Road,
Veronica Lane, Mayfield Heights Lane and Road, Knollwood Lane and Court,
Butler Avenue and Spring Street.
Engineering
Sam and Ryan have been continuing to survey on Hunter Lane when
weather allows. The streets of Hunter Lane, Orchard Place and Culligan
Lane are scheduled to be reconstructed in 2009.
Callahan Place hit a setback. Due to the cold weather, sod contractors have
closed down for the season prior to completing the project. Areas that did
not receive sod will have mulch with soil binder applied to stabilize the area
and minimize erosion. The yards will then be sodded in the spring when
temperatures increase.
John is attending the MPWA conference. The conference covers innovative
methods of public works operation as well as networking opportunities with
neighboring city engineers.
Public Works
The Parks Crew repaired the fencing around the hockey rinks at Marie Park,
Wentworth Park, and Friendly Hills Parks. The sweeper and 580D was
cleaned up and stored in the water tower for the winter. They attended a
Safe Assure meeting. Fertilizer was ordered for next year.
Rich checked the lift stations daily. There was a power outage for three
hours at the Lilydale lift station. Rich mulched leaves at the Veronica lift
station.
The Streets Crew loaded five dumpsters with the bonfire ash and had it
hauled away. They hauled in Class 5 from Solberg and stockpiled it. Plow
truck 303 was picked up from Towmaster in Litchfield, MN which had a new
sander installed on it. Compost (3 loads) was cleaned up that was dumped
on city right-of-way on Wachtler Avenue and Ridge Place and disposed of at
Gertens in Eagan.
Engineering
Asphalt driveway aprons were installed in the Callahan Project this past
week. Sod installation behind the curb is anticipated for next week
RFPs for the Pedestrian Improvements project at Dodd Road & 110 have
been scored and ranked. Council will act on the award of the Feasibility
Study at Tuesday night's meeting.
The Lower Mississippi River Watershed Management Organization
(LMRWMO) needs a primary representative from Mendota Heights appointed
to their Board. By State Statute, City Staff cannot serve as the primary
representative. Anyone who knows of someone interested in serving on the
Board can contact John Mazzitello.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
November 7, 2008
The Parks Crew raised the sprinkler heads on the soccer fields at Kensington
Park. They trimmed shrubs around park signs throughout the parks.
Leaves were mulched in the parks. The tennis nets were taken down and
gates locked at the tennis courts for the winter.
Rich changed the oil in the pumps at the Northland lift station, Mendota
Heights Road lift station and on the Rogers Lake aerator. Grease was
cleaned off the floats at the Northland lift station.
The Streets Crew blacktopped the Highway 110 Frontage Road from South
Lane to Delaware Avenue. Manholes were ringed with blacktop. Potholes
were filled on Warrior Drive, Sibley Court and High Ridge Circle. The bonfire
fence was taken down. John Boland watered down the bonfire. Wood that
was not burned in the bonfire was picked up. A TV was picked up on
Bourne Lane and taken to Appliance Disposal in Inver Grove Heights. A new
fence panel was put up that was broken from roadside mowing on Kay
Avenue.
Engineering
Driveways were prepped and boulevards graded on Callahan Place.
However the weather did not cooperate to have the driveways paved and
sod laid. The contractor hopes to complete this work next week. Sam and
Ryan constructed a rain garden on the project which will help with water
quality.
Punch list items were taken care of in the "Avenues" neighborhood. The
project should be wrapped up for the winter and just the wear course and
repair work left to do in the Spring.
Engineering and Tom Olund assisted with setting up and tearing down
precincts for the election.
Proposals for the Pedestrian Improvements at 110 & Dodd Road were
received and reviewed by the selection committee. Scoring will be
tabulated and a selected consultant will be announced next week.
NEWS T e Pi elin
LETTER
Public Works mr
Engineering i'
Code Enforcement October 31, 2008
Public Works
The Parks Crew finished fertilizing the neighborhood parks. Leaves were mulched
in the parks. The inside of the hockey boards at Marie Park were painted where
the paint had chipped off. Tractor #510 was serviced and put away for winter
storage.
Rich changed the guardrails at the St. Thomas lift station - stainless steel
guardrails were installed. Stainless steel guardrails won't corrode as quickly. A
sanitary sewer pipe repair inspection was done in North Freeway Road. Roots had
cracked the homeowner's service pipe.
The Streets Crew did storm sewer repair on Emerson Avenue and Wachlter
Avenue. Big pieces of wood and 40 pallets were cleaned up from the bonfire site.
John Ambrose did repair work and welding on a big rip on the wing for truck 580D.
Storm sewers were prepared for blacktopping by filling with class 5 and
compacting on Celia Road at Victory Lane, Watersedge Terrace, and Bluebill Drive.
Enoineerin
A base course of asphalt was placed on Callahan Place on Thursday. Driveway
aprons and behind -the -curb backfill is scheduled for next week. General site
cleanup will continue over the next couple of weeks and the wear course will be
installed in the spring.
Engineering staff continues to work with the re -development team for the Mendota
Mall working out details for the revised site plan reviewed by Council last week.
Engineering staff is working with The Visitation School and Saint Thomas Academy
to arrive at a solution to alleviate traffic issues along Mendota Heights Road.
RFP packages for the Feasibility Study for pedestrian improvements at Highway
110 and Dodd Road are due in by the end of the day on October 315t. Review of
the RFP packages will take place next week.
Public Works
The Parks Crew fertilized all the ball fields, soccer fields, City Hall, Fire Hall and Public
Works. Repairs were made to 580D. The water was pumped out of the pipes at
Mendakota and Kensington Parks and the water meters were removed.
Rich replaced the alarm light cover and bulb at the Lilydale lift station because it had been
vandalized. The pump bearings were greased at the Lilydale lift station which is done
every spring and fall. Leaves were mowed and mulched at the Veronica lift station.
The catch basin was repaired at Celia and Victoria Roads. The frame was bricked and
filled in with concrete. A new frame was made for the catch basin at 889 Bluebill. The
inside of the catch basin at 614 Watersedge Terraced was mudded up. The bonfire pile
was pushed up. A street sign was reinstalled on Fieldstone. The sink hole at 1307
Mendota Heights Road was dug up. Water was bubbling up out of the hole so St. Paul
Regional Water Services was called and informed of the water leak.
Engineering
Curb was poured on Callahan Place on Tuesday. Due to the cold weather the contractor
will not be allowing the curb to be driven on until Monday. Next week, the class V base
will be graded and the street paved.
Two trees were replaced on Delaware Avenue. The existing trees deteriorated after the
street was rebuilt. This is a rare occurrence and a professional arborist could not
determine an alternate cause.
The rain gardens were dug and seeded on the Avenues project, trees will be planted today
or early next week. The yard at Dodd and 4th Avenue was graded and seeded and the
trail to Wentworth Park was graded. The trail was scheduled to be paved on Friday but
will be delayed due to the weather.
Staff has been meeting with consultants on the RFP for the Feasibility Report on
Pedestrian Improvements at Highway 110 & Dodd Road. Proposals are due into the City
by 4:OOpm on October 315`
Staff has been working with the development team for the Mendota Mall Expansion
project. A new Concept Site Plan was presented at City Council on Tuesday night, and
Staff will continue to work with the development team to incorporate the City's
requirements and requests into the project.
Public Works
The Parks Crew blew out the sprinkler systems at Kensington Park,
Mendakota Park, City Hall and the Fire Hall. Sprinkler heads were repaired
as needed. Sprinkler heads were raised at Kensington Park and filled in
with black dirt. The buildings at Kensington and Mendakota Parks were
winterized.
Rich inspected the rebuilt manholes on Pilot Knob Road. Two of the
manholes were dusty and he called the County about it. The floats at the
Veronica lift station were cleaned. Rich met with Friedges and inspected the
manholes on Kay Avenue and Walsh Lane. Friedges cleaned the dirty ones.
The Streets Crew blacktopped 810 Park Place where the storm sewer was
fixed. The fence was put up around the Halloween bonfire site. News signs
and posts were installed in the Kay Avenue and Walsh Lane project. Tree
stump holes were filled with black dirt and seed at 1037 Delaware Avenue,
566 Hiawatha Avenue, and 810 Park Place Drive. They made election signs
for the upcoming election.
Engineering
Engineering continued monitoring the progress of the Callahan
Reconstruction Project, addressing public concerns and contractor issues.
Pavement installation is tentatively scheduled for next week.
The Traffic Safety Committee met Tuesday night to discuss a crosswalk for
Brown College, stop signs and speed in the Avenues neighborhood, a
permanent stop sign at Maple and Linden, an update on the Decorah Lane
Speed Study, and potential Mendota Heights Road improvements at
Visitation Drive and Lake Drive. An update on the Committees will be
presented to Council on Tuesday night.
Staff received an updated concept Site Plan for the proposed Mendota Plaza
redevelopment project (Paster property), and is coordinating presentation to
the Council on Tuesday night.
NEWS The Pipeline 4t]
LETTER
Public Works,{
Enaineerina
Code Enforcement October 10, 2008
G
Public Works
The Parks Crew cleaned out the utility room at Mendakota Park and
prepared it for winter. New dead bolt locks were installed on the warming
house doors at Marie, Wentworth and Friendly Hills Parks. A light bulb was
replaced on the side of the Public Works Garage.
Rich checked the 11 rebuilt manholes in the Bachelor Avenue neighborhood
after construction was done and all looked clean. Rich fixed two manholes
in Kensington Park with John Boland's help. Rich did the fall inspections of
Lilydale's storm sewer system and all looked good.
The Streets Crew and Durable Concrete raised the storm pipe at 810 Park
Place. The void was filled under the curb sections and major brick work and
mudding was done in the storm drain. Stump grindings were cleaned up at
1037 Delaware Avenue and 566 Hiawatha Avenue. Light bulbs were
replaced on the street light at Dodd Road and Mendota Heights Road.
Attached is the thank you letter that was not included last week - thanking
the Streets Crew for trimming trees on Marie Avenue.
Engineering
Callahan Reconstruction Project is ongoing. Utility installations are
practically complete and street construction is scheduled to begin next
week.
Engineering is issuing an RFP for a Feasibility Report on pedestrian
improvements at Highway 110 & Dodd Road. Proposals are due to the City
by October 315c
Engineering has been working with Council Subcommittee and the realtor on
the potential sale of the old fire station lot. The next subcommittee meeting
is Oct 15rn
John attended the quarterly Municipal State Aid Pre -Screening Board
Meeting on October 7`n and is working on our annual assistance application.
Mr John Idazzitello Sept 27 2008
Public Works Director
City Of Mendota Heights
Dear John,
Jo Ann and I are wish to express our gratitude for arranging to
have the unsightly and `non -sightly' trees trimmed on Marie Ave
(rear of 1£20 and 1822 Valley Curve) on Friday, Sept 26.
What a vatst improvement it makes to the sight line and the general
appearance of the street and boulevard. Our work in keeping the
boulevard neatly trimmed throughout the warm weather will be
even morc pleasurable and easier.
George Ni')ack and his crew work arduously and conscientiously,
and are very neat and courteous. They are an asset to the city of
Mendota Heights.
Thank you .... and please commend and thank George and his workers.
ncerely
Joe and Jo Ann Stefani
1820 Valley Curve Rd
NEWS
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
October 3, 2008
The Parks Crew cut out the brush from under the pine trees at Marie Park. Mulch
was put down under the picnic tables at Marie Park. The bathroom sink in the
men's room at Public Works was repaired. The mulch kit was installed on the
xmark mower.
Rich turned on all condensate heaters at the lift stations. A new condensate
heater was installed at the Northland Drive lift station. These heaters keep the
inside of the panel water in the winter. He poured concrete around the manhole in
the Rogers Lake easement. The old concrete was cracked and breaking.
The Streets Crew cut down a large ash tree on Hiawatha Avenue and two maple
trees on Delaware Avenue. A pothole was patched at the intersection of South
Lane and South Freeway Rad. The speed limit sign was reinstalled that was
knocked down by the Valley Park tennis courts. A willow tree was trimmed back
on Marie Avenue (see attached thank you letter). They attended the Fall
Maintenance Expo in St. Cloud.
Engineerino
Assessment hearing packages were prepared for The Avenues and
Somerset/Evergreen Rehab projects to be held during the October 7th City Council
Meeting. There was one assessment deferment request that was included in the
information.
A Request for Proposals for the Feasibility Study of Pedestrian Improvements at
Highway 110 & Dodd Road was prepared. If Council authorizes issuing the RFP, it
will be sent out and proposals received by October 315t
Met with the Mendota Plaza development Engineer to discuss addressing City's
concerns and issues about the development proposal. Significant progress was
achieved, and the developer will be forwarding a revised site plan for the October
215t Council meeting.
Began an analysis of issues surrounding the sale of the old firehall lot on Dodd
Road per Council direction.
Continued to address issues and answer questions from the public pertaining to
Engineering and Public Works Issues. A public complaint log is accessible on the
engineering drive for tracking the issues and responses made by the City.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The pipeline
September 26, 2008
The Parks Crew attended the Minnesota Turf and Grounds Foundation Field Day
where they got an overview on turf grasses and turf grass disease control. The
new soccer goals were put in place at Mendakota Park for Mendota Heights soccer.
A tool box and running boards were installed on the new pick up truck. Sprinkler
heads were repaired at Kensington Park.
Rich put root x in the sanitary sewer lines at Williams Court, Wagon Wheel Trail,
Glen Hill Road, Downing Street, Lexington Avenue, Knob Road, Highway 13
(Fremont Avenue to Garden Lane). Root x kills any roots that are growing into the
sanitary sewer line. He assisted the Streets Crew with blacktop work.
The Streets Crew weed whipped the east side of Victoria north of Marie Avenue.
They put up temporary stop signs at Maple and Linden in Town Center. They put
blacktop down on Lilac Lane, Douglas Road, Overlook Road and James Road.
Engineering
Water main installation was completed on Callahan Place. The main was
disinfected and will be flushed and tested for bacteria on Friday. If tests pass, the
main will be put into service early next week and the temporary water system will
be removed. The contractor is now installing the storm sewer causing a slight
disturbance on Marie Avenue. The storm sewer should take about a week to
complete.
Remaining streets were paved on the Avenues project and the driveways are being
patched. The next step is to back fill the boulevards and get the area ready for
sod. Storm sewer will be installed on Tuesday in the park and rear yard on Dodd
Road. Kay and Walsh Avenues will be receiving the wear course this year.
Sod was installed on the Marie Creek project where a slope project needed to be
repaired.
Final touches were added to the Somerset Mill and Overlay project, this project
should now be complete.
Assessment hearings for the Avenues and Somerset Park projects will occur on
Oct. 7tn
N E W S The Pipelin
LETTER .j
Public Works
Enaineerina September 19, 2008
art.
Code Enforcement
Public Works
The Parks Crew completed general maintenance in the parks this week including
trash pick up, cutting grass, striping soccer fields, dragging fields, and cutting
grass adjacent to the pedways.
Rich cleaned the sanitary sewer lines on Riverside Lane, Aspen Way, and
Brookside Lane. He sprayed Kensington and Mendakota Parks for broadleaf
weeds. A sewer inspection was done on Cullen Lane. He fixed a manhole on Ivy
Hill Road. The concrete ring had a hole and then the blacktop caved in. A new
ring was installed and the Street Crew then blacktopped it.
The Streets Crew dug out a patch on Mendota Heights Road and blacktopped it.
They cleaned storm sewer grates. John Ambrose made a "Do Not Enter" sign for
the Police and installed it. Rip rap was installed at the Pilot Knob site where there
was a washout. Tree branches were cut that were overhanging the street on
Huber Drive. Pot holes were filled on Valley Curve by the alleyway. A broken
storm grate was replaced on Mendota Heights Road. The parking lot entrance at
the fire hall was overlaid.
Enaineerina
The last of the curb was installed on the Avenues project. The contractor is
finishing the gravel base and the project will be ready to pave on Tuesday.
Concrete driveways have also been poured and bituminous driveways will be
paved toward the end of the week. 1st Avenue has "bump outs" in the
intersections as a traffic calming measure, the full effect of the calming will not be
known until the street is paved and boulevard landscaped.
The Somerset Park/Evergreen Knoll project and Main Street were paved this
week. The contractor, Bituminous Roadways, did an exceptional job with the
quality of their work and relations with the public.
over half of the water main has been installed on Callahan Place. The contractor
is not working Thursday or Friday but will return next week to complete the
installation and begin installing the storm sewer.
A slope was repaired at 755 Willow Lane where the city recently did a stream bank
stabilization project.
i
NEWS
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
The Pipeline
September 12, 2008
The Parks Crew is still spraying weeds on the pedways. Downed
tree limbs were cut up and hauled away from Ivy Falls Park. The
limbs broke off the tree from high winds last week. The newly
planted trees at Rogers Lake Park were watered and mulch was
put down.
The Streets Crew blacktopped Mendota Heights Road from
Lexington Avenue to Dodd Road. The LP tanks were filled for the
hot box and maintenance was done. They attended the Safe
Assure meeting at Public Works. They attended the Equipment
Expo at Canterbury Park in Shakopee.
Engineering
John and the Engineering/Public Works staff continue to be
responsive to resident issues and inquiries.
Jim, Jake, and John have been discussing with MnDOT the
possibilities of enhancing the pedestrian crossing at Highway 110
and Dodd Road. A brief summary will be presented at the
September 16th City Council Meeting.
Jim, Jake, and John met with representatives of the Paster
Development project at Mendota Plaza. City Staff will review the
list of conditions as passed by the Planning Commission and
provide the developer with a boiled down list of items that need to
be addressed prior to City Council action.
N E W S The Pipeline
LETTER
Public Works
Engineering August 22, 2008
Code Enforcement N
Public Works
The Streets Crew cut down and cleaned up the vines on both sides of the fence on
the Wagon Wheel Trail bridge. The north end of Diago Lane, Winston Court,
Brompton Place and Chippewa Avenue was blacktopped. Patches were seeing cut
fir storm, cleaned out and filled with class 5 in Hidden Creek. The storm grate on
Winston Court was cut out, filled and blacktopped.
The Parks Crew did irrigation repairs and adjustments at Mendakota and
Kensington Parks. The soccer fields were laid out and striped for the fall soccer
season. Weeds are still being sprayed on the pedways. They helped the Street
Crews trim trees.
Engineering
John R. Mazzitello started as the new Public Works Director on Monday. He has
already met with several residents who have had ongoing problems or concerns
with regard to drainage, street conditions or restoration work.
The street light rehabilitation is complete. Four poles needed to be replaced and
the remaining 116 were sand blasted and repainted.
The mill and overlay is progressing rapidly. The curb and gutter replacement is
complete as well as the edge milling. The bituminous base will be patched today
and manholes and valves will be adjusted next week.
The water main is complete on the "Avenues" project and the contractor is placing
class 5 gravel on 1st and Clement to get the streets ready for curbing.
A preconstruction meeting was held for the Callahan Place reconstruction project.
The contractor plans to start the project on September 8tn. Xcel is in the process
of replacing the gas main and St. Paul Regional Water Services is setting up a
temporary water service for the residents.
Mn/DOT is replacing the guard rails on Marie Avenue and also on Mendota Heights
Road. The work should be complete by early next week.
Began review of submitted Preliminary Plans for the development at SE corner of
Pilot Knob and Northland Drive (Mendota Heights Lodging Investors, LLC).
cn
Scheduled for Planning Commission on August 26
N E W S The Pipeline
LETTER
Public Works
Engineering
Code Enforcement August 15, 2008
Public Works
The Parks Crew repaired the sprinkler heads at Mendakota Park. They
continued to spray weeds in the pedways. The parking lot in the back of the
shop was cleaned. They watered trees in the parks. The warming house
signs were put back after the warming houses were painted.
Rich did a sanitary sewer inspection at 1255 Mendota Heights Road. He
cleaned sanitary sewer lines at Park Circle, Park Place Drive, Park Circle
easement and Boardwalk Court.
The Streets Crew applied asphalt wearing course on the Victory turnaround
from Eagle Ridge. Streets were patched by Mendota Elementary School.
They cleaned inside the shop. The brush pile was chipped up and hauled to
Resurrection Cemetery (to dispose of at no cost). The bigger wood pieces
were hauled to Metro Wood in St. Paul.
no
Engineering
Public Works held their annual "Super Summer Picnic".
They put on a nice spread with shredded turkey,
shredded pork and all the fixings. It was a nice day for a
picnic and a lot of employees showed up along with the
Mayor and Councilwoman Krebsbach. Thank you Public
Works!!
Bituminous driveway work started on Third Avenue for the Avenues project.
Water main replacement is finished on First Avenue. Storm sewer work is in
progress. Topsoil placement has begun.
Dakota County paved Pilot Knob Road for their bituminous overlay project.
Street light pole painting is still in progress in the Industrial Park.
Gas main replacement starts Monday on the Callahan Street project.
" E `" s The Pipeline
LETTER
Public Works _
Engineering
Code Enforcement QP
Public Works
The Parks Crew finished aerating the soccer and ball fields. The soccer
fields at Kensington Park and Mendakota Park were fertilized as were the
ball fields at Mendakota Park and City Hall. Seed was put down at the
soccer goal mouths and areas that needed it at Kensington Park. The
hockey rinks and warming houses were painted. Weeds were sprayed along
and in the pedways between cracks.
Rich cleaned the sanitary sewer lines on Hingham Circle, Staples Avenue
and Emerson Avenue. The sump manholes on Swan Drive were cleaned out
and four yards of gravel and grass clippings were hauled out.
The Streets Crew put the sign head back up at Hidden Creek and Nature
Way. The red light at Dodd Road and Mendota Heights Road was out and
replaced with a bucket truck by Mid Northern Electric. The street sign was
replaced at Mendota Heights Road and Northland Drive. Four "no parking"
signs were replaced. Potholes were filled on Eagle Ridge Drive. The street
was sinking at Douglas Road and James Street and St. Paul Regional Water
Services filled the area with blacktop.
Engineering
Bituminous base was placed on Third Avenue, Fourth Avenue, Clement
Street and Vandall Street for the Avenues project. Water main replacement
continues on First Avenue.
The mill and overlay project at Evergreen Knolls and Somerset Park starts
next Tuesday. The project was awarded to Northdale Construction.
Dakota County milled Pilot Knob Road for their bituminous overlay project.
Street light pole painting is in progress in the Industrial Park.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
August 5, 2008
The Parks Crew picked up the new pick up for Parks and taken to Inver
Grove Ford for the box to be sprayed. They worked a tournament at
Mendakota Park. The women's restroom at Kensington Park was
repaired and the sink and toilet were repaired at Kensington South. A
hornet's nest was removed from Marie Park.
Rich sprayed for broadleaf weeds at Mendakota Park, City Hall and the
Civic Center ball field. He painted fire hydrants on Lemay Lake Road,
west end streets, Augusta shores, Mendota Heights Road, Highway 13,
and Delaware Avenue. He cleaned the sanitary sewer lines at 2400
Lexington Avenue.
The Streets Crew cut back trees and brush along the fence line on
Victory Road. Crosswalks were striped at Sibley High School, Village
of Mendota Heights, St. Thomas Academy, and Mendota School. The
sign post was replaced for the crosswalk/speed limit sign at Friendly
Hills School. A street name sign was installed for the alley on Valley
Curve. They blacktopped Marie Avenue, and Dodd Road to Delaware
Avenue. A downed tree on Valley Curve Road was cut up and hauled
away.
Engineering
John has been working with the developers of the proposed
Homewood Suites site at Pilot Knob and Northland Drive to work out
the technical details of their proposal. It is anticipated that these
issues will be addressed by September 16 Council Meeting.
Engineering staff continues to work with members of the public to
resolve a variety of issues. Engineering has started an issues log to
track issues/concerns, key dates, and their resolution actions.
NEWS
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
The Pipeline
August 1, 2008
The Parks Crew replaced the corner boards at the hockey rinks to prepare them for
painting. The sprinkler heads at Mendakota Park were repaired and adjusted as needed.
They started aerating the soccer and ballfields throughout the City. The ballfields were
prepared for last weekend's end of the year softball tournaments.
Rich cleaned the sanitary sewer lines on Pilot Knob Road and Delaware Avenue. Trees
and brush were cleared from the 12" easement line on Highway 110 Frontage Road. He
was called in on Sunday at 12:05 A.M. for a water flow alarm. The floats were wrapped in
rags and grease. George assisted Rich with cleaning the floats.
The Street Crew hauled in Class 5 to the end of Victory Lane and then graded it. Tree
branches were trimmed that were blocking the "stop ahead" sign on Victoria Road. They
helped the Parks Crew cut down a large tree and trim branches on other trees along the
pedway on Victoria and Stratford Roads. A new sign was made up and the post replaced
on Overlook and Summit. Signs posts were replaced on Lilac Lane, Mayfield Heights
Road, North Freeway Road, and South Lane.
Code Enforcement
A permit was issued for 1255 Northland Drive for a three story addition to the A.R.R.T.
building. Estimated cost for construction is $4,800,000.00. United Properties is the
general contractor. The addition will contain 34,800 square feet of office space and a link
connecting the existing and new building containing 4,500 square feet.
Enaineerina
Curbing and concrete driveways were installed on over half of the Avenues Project. The
sewer crew continues to install the remaining watermain. Streets that received new
curbing and being toleranced for class 5 (gravel) and paving is scheduled for next
Wednesday. Curb was removed from First Avenue and brought to Pilot Knob for the new
Snake Habitat.
A preconstruction meeting took place for the Somerset Park/Evergreen Knoll Mill and
Overlay project. Bituminous Roadways expects to start on August I1tn
Bids are to be received for the Callahan Place Reconstruction Project on Monday April 4tn
Public Works
The Parks Crew brought in rec rock to Mendakota Park fields, leveled it out and
then dragged the fields. The playground equipment at Hagstrom King Park was
repaired. Trees were trimmed in the parks, as needed. A tree was removed from
along the pedway on Victoria Avenue. Roundup was sprayed in the cracks where
weeds are coming through the cracks on the pedways.
Rich cleaned the sanitary sewer lines on Pilot Knob Road, Commerce Drive and
Highway 13 easement. He changed a check valve spring on pump one at the
Mendota Heights Road lift station.
The Streets Crew finished blacktopping on Wagon Wheel Trail, Curleys
neighborhood and Dakota Drive. A storm pipe on Mendota Heights Road was fixed
near Patterson Dental. Weeds and small trees were cleaned up in the culvert on
the east side of Lexington Avenue on the north side of City Hall. Guard rail areas
were weed whipped on Mendota Heights Road and the Marie Avenue underpass.
Aggregate was brought in from Solberg and stockpiled behind Public Works.
Engineering
Curb and gutter was placed in the Avenues neighborhood (not without issues, of
course) and all residents on the project are satisfied. Concrete driveways will be
placed next week and manholes and valves will be raised to grade in anticipation
of paving on August 4th. Curb panels removed on 15t Avenue were brought to Pilot
Knob site for the construction of a snake habitat.
Ryan is still working with Mn/DOT to coordinate drainage improvements on Dodd
Road.
The Somerset Park Mill and Overlay project will begin on August 11th. A
preconstruction meeting was held on Thursday and the contractor expects to
complete the project within four weeks.
Plans for the Callahan Place reconstruction are nearly complete for an August 4th
bid opening.
Attachments•
Thank you letter from Midwest Weed Harvesting
Dakota County Soil and Water Conservation District Fact Sheet for the Par 3
Raingarden
Project: A 200 square foot
raingarden which captures runoff
from the adjacent municipal golf
course parking lot. The raingarden
will provide water quality treatment
and volume reduction for the parking
lot runoff
COStS: The total cost for materials
and rented equipment was $594.74,
with City of Mendota Heights staff
providing the in -kind labor to complete
the project.
Funding: Dakota CountyswCD
provided design assistance through the
Blue Thumb Program, construction
oversight, and Community Conservatiol
Cost Share funding in the amount of
Dakota Countv Sail and 'Water Conservation District
4100 2201" tit. %V._ Suile 102. Farmington. Nn 55124 6514SIl--^,177 wu�r.dakoiaswnLnr
GOJt1T'>` SO/� FN
�U
TIGN O\5,
Revised OTOR103
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
July 11, 2008
The Parks Crew repaired sprinklers at Kensington Park, Mendakota Park and City
Hall. Newly planted trees and shrubs were watered. The hockey boards at the
hockey rinks were pressure washed in anticipation of painting.
Rich cleaned sanitary sewer lines.
The Street Crew was busy fixing potholes and high irons in the Friendly Hills area
and on Wagon Wheel Trail this week. There were a couple of trees down after
Thursday's storm on Creek Avenue and Dodd Road, which were cleaned up. Storm
sewer grates were checked.
Tom Olund became a grandpa for the third time when his son, Dave, and wife,
Casey, had a baby girl on June 28th at 2:32 A.M. Morgan Lynn Olund weighed 7
lbs.
Engineering
Sewer and water extension has been completed on the Koppeck property.
Guy has coordinated with the DNR and Midwest Weed Harvesting to do weed
removal in preparation of the upcoming fishing derby.
Bituminous Roadways was the low bidder on the Somerset Park/Evergreen Knoll
Mill and Overlay project.
Friedges Contracting has been grading subgrade and placing class 5 on the Avenues
project. Driveways are prepped and ready to be paved on Kay/Walsh. The
contractor hopes to place curb and gutter on 4th and 3`d Avenues on Tuesday of
next week.
Sam and Ryan attended a safety workshop at the water tower.
Sam replaced plants in the Somerset rain gardens that were stressed or did not
survive the winter.
Plans are being completed for the Callahan reconstruction project.
Ryan met with the residents on Field Stone Drive regarding a potential storm sewer
drainage improvement project.
N E W S The Pipelin
LETTER
Public Works June 27, 2008
Engineering
Code Enforcement
Public Works
The Parks Crew watered shrubs and newly planted trees in Kensington and Friendly
Hills Parks. They repaired the air hose in the shop. Round up was sprayed around
fences in the parks. The soccer fields and at Kensington South and Mendakota
Parks and the ball fields at Mendakota Park and the Civic Center was fertilized.
There were tournaments for Mendota Heights Athletic Association this week and the
fields were dragged, chalked and cleaned up.
Rich dug out and raised the manhole 8" on Lexington Avenue and then put blacktop
down. Four storm sewer covers were changed out by the Par 3. The old covers
said "sanitary sewer" and covers that read "storm sewer" were put on. The storm
beehive cover was dug out and raised behind the Concord Way townhomes.
Sanitary sewer lines were cleaned on Victory Avenue and Furlong Avenue. 1640
James Road had roots in their sanitary sewer service and the City's portion of the
line was ok.
The Street Crew made up new signs and installed them. Trees were trimmed to
improve sight distances on Huber Drive and Delaware Avenue, and Huber Drive and
Cheyenne Lane. A catch basin was made for Pilot Knob Road and Class 5 was put
down. The ditches on Highway 13 and Bachelor Avenue and Callahan Place were
cleaned out. Street sweepings were hauled to Solbergs.
Enaineerin
Watermain has been completed on 3rd Avenue and Clement Street. Watermain
replacement is underway on 2"d Avenue. Subcutting has started on Vandall and 4th
Avenue, additional subcutting and granular borrow is required due to poor soils.
Curb and gutter has been poured on Kay and Walsh and gravel is close to finish
grade. We anticipate streets being paved next week.
The final wear course has been placed in the Ivy Falls area. Only minor punch list
items remain to be completed.
Gartzke has been installing a sewer and water extension to service homes adjacent
to the Hidden Creek development.
GL Contracting has begun replacement of curb and bituminous on Wagon Wheel
Court.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
' June 13, 2008
Parks crew cut grass, striped fields and collected trash in the parks. Performed set
up and take down of equipment for park celebration. Weed whipped pedways and
post through out city, painted inside of warming houses and cut up and removed
down tree at friendly hills pond. Extra dirt was removed from Rogers lake park
after installation of new playground equipment.
Street crews cleaned up brush in back lot and collected downed trees on Emerson
Ave, Overlook Rd, Summit Lane, Willow Ln, Spring Creek Ct and Fox PI. Repaired
two catch basins on Havenview Dr. Installed trash guard to culvert on Swan Or and
cleaned up dirt at 1101 Chippewa. Cleaned up stump grindings at 2131 Aztec
Lane.
Sewer crew checked lift stations daily. Cut roots and jetted sewer on South Ln,
Ocala Ln, Pagel Rd, Callahan St, Warrior Dr, Fox PI and Creek Ave. Weeds were
sprayed at Par 3 near Maint. Building per Gerry Murphy request. Storm and
Sanitary manholes were assessed for repair in the Somerset Park/Evergreen Knoll
area.
Engineering
Installation of new playground components at this park were completed on Friday.
Last month Public Works removed the old CCA treated border timbers, and the
westerly old playground equipment. The tall four -swing unit will remain surrounded
by non -toxic border timbers with one foot deep wood fiber resilient surfacing. At the
easterly "ship -theme" playground area non -toxic border timbers will be added as
well as a cable climbing structure and wood fiber resilient surfacing. Public Works
will restore disturbed turf areas.
The final lift of Bituminous will be installed in the Ivy Falls area on Monday June
16tn
St Paul Water will be repairing the intersection of Douglas Or and Victoria Rd on
Monday June 16tn. The street will be closed to traffic during this repair.
Curb will be installed on Kay Ave and Walsh lane on Monday also. Watermain will
continue to be installed on 3`" Avenue next week.
NEWS
LETTER w� The Pipelineis
Public Works
Engineering
Code Enforcement June 6, 2008
Public Works
The Parks Crew cleaned up Mendakota Park for this Saturday's Park
Celebration. Stump grindings were removed from Rogers Lake Park and the
hole was filled with dirt and grass seed and leveled off. Dirt was filled in
around newly planted shrubs at Kensington Park South.
Rich ran the generator on Saturday at the Lilydale lift station from 4:30 A.M.
to 7:00 A.M. Xcel Energy was changing out the power lines. The alarm
went off at the Lilydale lift station on Saturday evening. Rich cleaned off
dental floss and grease. He cut tree roots in the sanitary sewer lines on
Valley Curve, Ridgewood Drive, Sunset Lane, North and South Freeway
Roads, Knob Road, Staples Avenue and Hingham Circle. Rich did a sewer
inspection at 1200 Sylvandale.
The Street Crew cleaned catch basins. The storm sewer at Overlook Road
and Overlook Lane was repaired. Pot holes were filled in and high iron
patching was done in the seal coat areas. The speed limit sign by the Par 3
was moved. No parking signs were put up on Northland Drive. Stump
grindings were cleaned up on Aztec Lane, Rogers Lake Park, and Friendly
Hills Park.
Engineering
St. Paul Regional Water Services plans to repair the intersection of Victoria
and Douglas on Monday, June 9th. Traffic will be detoured to Lexington.
Underground work is complete at Kay and Walsh. Street work has started.
Watermain replacement is complete on Vandall and continues on Fourth
Avenue.
The homeowner at 1200 Sylvandale had to install a new sanitary service as
the old one was not working properly. The repairs are complete and the
street is patched.
Punch list work items are underway in the Ivy Falls neighborhood.
NEWS
L E T T E
Public Works
Engineering
Code Enforceme
Public Works
The Pipeline
May 30, 2008
The Parks Crew installed wood shakes on the roofs of the new "You are
Here" park signs at Hagstrom King, Friendly Hills, Rogers Lake, Victoria
Highlands, Valley and Wentworth Parks. The newly planted trees at Friendly
Hills and Ivy Falls Parks were watered. A broken irrigation line was repaired
at the Fire Hall. Dead shrubs were removed from Kensington Park South.
Rich vacuumed out the storm sewer manholes then applied mosquito control
briquettes. Rich was trained on how to apply the briquettes. He cut tree
roots in the Kay/Walsh area then flushed out the sanitary sewer lines in
anticipation of the street construction project. He also cut tree roots in the
Winston Court easement, Chippewa Avenue and Annapolis Street easement
and at Highway 13 and Fremont Avenue.
The Street Crew cut down two boulevard trees on Marie Avenue. Logs were
cleaned up on Spring Street and overhanging trees were removed. The hot
box tray mount on truck #308 was fixed. Demolition debris was hauled out
to SKB from the Public Works back lot.
Engineering
On Tuesday, Friedges Excavating began removing pavement on Kay Ave,
Walsh Lane, Vandall Street and 3rd and 4th Avenues. Temporary water has
been installed to homes on 3rd and 4th and storm sewer was installed on Kay
Avenue. The contractor will begin installing water main on 4th Avenue next
week.
Sam and Brian replaced dead plants in the Somerset rain garden.
Approximately 20 plants did not survive the winter and had to be replaced.
Sue returned from Arizona and found a beautiful new home.
L
Cc
Public Works
The Parks crew cleaned out the playground equipment at Rogers Lake and
piled up the pea gravel. They removed tree stumps at Rogers Lake and
Friendly Hills Parks, hauled in black dirt and grass seed. Flowers were
planted at Mendakota Park. The hill by the maintenance building was
leveled off at Par 3 and debris hauled out.
Rich's summer helper, Andy Quinlan, started on Monday. Rich pulled credit
cards and ID cards out of a catch basin on Kirchner Avenue for the Police.
He sprayed for weeds at the Par 3, Public Works, and the tot lots at Curly
and Friendly Hills Parks. The man holes in the Bachelor Avenue area were
checked and some need new concrete rings. All fire hydrants in the
Bachelor Avenue and Callahan Place were painted. Lloyds BBQ called and
said their grease trap (separator) was broken. They put four days worth of
grease (1,000 gallons) down in our sewer system. The grease was cleaned
up and vacuumed out. Lloyds will be billed for this work.
The Street Crew put up no parking signs in the seal coat areas. A tree was
cut down at 17 Dorset Road. No parking signs for Mendakota School were
picked up. A pedestrian crossing sign and post was picked up and installed
on Mendota Heights Road. Black dirt and grass seed was put down on
Hilltop Road and Dodd Road. A new stop sign was installed on Mendakota
Drive. The hot box was installed on truck 308. Sod damage was repaired in
Augusta Shores and Medallion Drive.
Engineering
MnDOT's contractor installed a new catch basin on Mendota Heights Road
and piping down to 35E.
Xcel's subcontractor installed the last four street lights on Main Street next
to the ABC building.
The preconstruction meeting for Pilot Knob Road was held on Tuesday. The
schedule calls for mill and overlay work the week of June 23rd. The
contractor is Niles-Wilse Construction Company out of Medford, Minnesota.
N E S The Pipeline
LETT ER\
Public Works
Enaineering
Code Enforcement May 16, 2008
Public Works
One of the part-timers for the summer started working with the Parks
Crew this week. They repaired the sprinkler valves at City Hall and
Kensington South Park. Three pin oak trees were plated at Friendly Hills
Park. The trees were donated by the Friends of the Parks.
Rich got called in on Saturday at 2:00 P.M. because pump 2 at the
Mendota Heights Road lift station overheated. The spring on the check
valve was broken and replaced. He sprayed for weeds at Mendakota
Park, Friendly Hills Park, Rogers Lake Park, Curly Tot Lot, Fire
Department, Valley Park, Wentworth Park, City monument sign on Dodd
Road and North Kensington Park. He assisted the Street Crew with
blacktopping around the 2 manholes he raised last week on Highway 13
and Hunter Lane.
The Street Crew did boulevard repairs by putting down black dirt and
grass seed from damage caused by the snow plows. A street sign was
installed on Wagon Wheel Trail and Wagon Wheel Court. The last
mailbox was repaired that was damaged by snow plows.
Engineering
Sam and Nancy (with little help from Jake) planted the rain garden at the
Par 3.
Sue had her annual meeting with Terry Schwalbe, the Lower Minnesota
River Watershed District Administrator. The District has been working on
a gully inventory project.
The bases and wiring for the last four street lights in Town Center were
installed this week.
NEWS y� f The Pipeline
LETTERS
Public Works May 9, 2008 Wother
Enaineerina
Code Enforcement �� `s ' '
Public Works
The Parks Crew cut grass and striped the ballfields in the parks. Rec rock was hauled to
the Civic Center ballfields for mound and infield repair. Crab grass preventative was put
down at Mendakota, Kensington, Highland Parks Public Works, Fire Hall, and City Hall.
Donated trees from "Friends of the Parks" were picked up to be planted at Friendly Hills
Park.
The homeowner at 2218 Lexington Avenue called with sanitary sewer trouble. Rich went
and checked into. The trouble was found in the homeowner's line. Rich raised a
manhole 10" on Hunter Lane. It was buried in the homeowner's driveway. He sprayed
for broadleaf weeds at City Hall, Marie and Victoria Highland's Parks. John Ambrose
welded a hatch cover to repair the storm lift well.
The Street Crew installed four more parking signs at Patterson Dental. Two no parking
signs were installed Friday at Patterson Dental. A speed limit sign was put up on
Decorah Lane. A tree was cleaned up that fell on Valley Curve Road.
Enaineerina
Sam, Ryan and Brian
creating the new rain
garden at the Par 3
Golf Course
Attachment: Invitation to an open house for the Robert Street Corridor Transit
Feasibility Study on Thursday, May 29th 3:00 - 7:00 P.m. with formal presentations at
3:30 and 5:30 at the Dakota County Northern Service Center in West St. Paul.
News Release
FOR I VIWDIATE RELEASE
Contact: Sam O'Connell, Transit Specialist, Dakota County Transportation, 952.891.7105
May 7, 2008
Brandt Richardson
County Administrator
www.dakotacounty.us
Gaff Plewacki
Communications Director
Sharon M Madsen
Communications
651438-4235
Hear the results of the Robert Street Corridor Transit Feasibility Study
It's time to hear the results of a 14-month study of transit possibilities in the Robert Street Corridor.
This feasibility study in the Robert Street Corridor is part of Dakota County's development of a long-term
transit vision for the Robert Street Corridor.
The public open house will be held on Thursday, May 29, 3 to 7 p.m., with formal presentations at
3:30 and 5:30 p.m., at the Dakota County Northern Service Center, 1 Mendota Road, West St. Paul.
The purpose of the study was to create a long-term corridor vision that identified transit and
transportation issues, opportunities, costs, benefits, and impacts of potential transit alternatives that could
offer remedies for future mobility issues. During the process, Dakota County has sought public comment on
the alternative transit modes and routes to ensure that everyone was involved in the early stages of the
decision -making.
For more information on the results of the study contact Sam O'Connell at 952-891-7105 or visit:
www.dakotacounty.us and enter "Robert Street" in the search feature.
Dakota County's Office of Transit coordinates public transit planning services for Dakota County residents. The
office's mission is to improve existing and future mobility needs within Dakota County through comprehensive transit
planning and innovative and progressive project development.
' NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
May 2, 2008
The Parks Crew marked locations for the "You Are Here" park signs. They set up and
striped soccer fields and lacrosse fields at Kensington Park. Rec rock was hauled in to
fields 1-4 and all warning tracks, and then leveled off at the Civic Center fields. Two
donated Pin Oak trees were planted at Ivy Falls Park. Holes were prepared and filled
where trees were removed last year from Victoria Highlands Park.
Rich put stainless steel lifting chains on the pumps at the Culligan Lift station. The old
chains were rusty and rotting. Lilydale's storm sewer outfalls were checked and looked
good. The sprayer for weed spraying was prepared for the upcoming season.
The Street Crew finished up fixing mail boxes that were damaged by snow plows.
Potholes were filled on Chippewa Avenue, Diego Lane, First, Second, Third and Fourth
Avenues and in the Mendota Heights Road and Lake Drive area. Trash was picked up
along Delaware and Huber up to Sibley High School where there were broken trash
bags. The trash guard was cleaned in a Pond View backyard. The blacktop was cleaned
up on the Furlong curb that was broken up. Barricades and cones were brought to the
Spring Clean Up site and "No Parking" signs were put up. The street light bulb at Dodd
and Mendota Heights Road was replaced.
Engineering
Sue met with a resident on Walsh Lane who opposed the proposed bump outs.
The Traffic Safety Committee held their first meeting. A group of University of
Minnesota seniors presented their findings on the Decorah Lane traffic calming study.
The committee decided to install 30 mph signs on Decorah, increase enforcement and
send a letter to the neighborhood to inform them of the decision and remind them to
watch their speed.
Sue met with St. Paul UMC board of trustees to discuss a drainage issue along their
common property line with the Village. Grading corrections will take place when the trail
along Dodd Road is constructed.
Attachment:
Please see the attached letter and map from MnDOT regarding the release and
conveyance of Victoria Curve from MnDOT to the City of Mendota Heights.
Minnesota Department of Transportation
Metro District
Office of State Aid
1500 W. County Road B2 Office Tel: 651-234-7761
Roseville, MN 55113 Fax: 651-234-7765
April 22, 2008
Ms. Sue McDermott, Public Works Director
City of Mendota Heights
1101 Victoria Curve
Mendota Heights, Minnesota 55118
Dear Ms. McDermott:
This letter is notice of the pending release and conveyance of the following roadway to
the jurisdiction of the City of Mendota Heights.
CS 1918 T.H. 110 Frontage Road (Victoria Curve) from the West City Limits to
Lexington Avenue
The planned effective date for release is on or about October 1, 2008. An exhibit
displaying the roadway is attached.
In accordance with 8820.0800 subpart 1, this roadway may be eligible upon request, for
consideration as part of the state aid system. In accordance with 8820.0800 subpart 2
this roadway is not eligible for turn back funds.
The Office of Land Management will subsequently prepare and submit to you
documents affecting the conveyance of our interest in the roadway to the City of
Mendota Heights. If you have any questions concerning the release, please feel free to
contact me at (651) 234-7761.
Sin erely,
Gre V. o ghlin
Metro District State Aid Engineer
cc: Julie Skallman, Division State Aid Engineer
Khani Sahebjam, Metro District Engineer
Mike Kowski, State Aid Pre -Award Engineer
Lynn Clarkowski, Area Manager
OLO HIGHWAY NjGAY
< 13
CD
O D Z N W W N
C7
N O z C) Z
3-i0 D
3 m� A o
Op R0. o
113 n
m
w o r
o41
o
� c ACgC a s� s�
r m m o I9i DR. '
D zo o o a3; ap a y5
z D
"< m m
m 15
m0
�� >
z—
m
m -� m GLENHIL n R0.
�00
O r C: C
.. - C m --i Z n D r Z
D Zi CENTR E'O�o o Dr'i m
o BLVO. cn v m HUNTER LA.
m
m f�T1�DZm n zo
zORCH
C��m £
m
� � z o� D
LEXINGTON AVE. 105 W m D< o
W G D W
7 D
THERESgr pS rRICI ST. < o D T D � z
z � o -i m <o TWINCI(LE PRF
TIMMY ST.' x . D -i � nC)
' 3 omo p' 0 LA LA
93 CT. CA LA
. SUMMIT y
C) p LA
WALSH , o
z � O
Y
O
mm
DTP VICTOR
0 0
LETTER
Public Works
Public Works
The Pipeline
April 25, 2008
The Parks Crew dragged the ball fields and put out the bases. The old globes and lamps
were replaced at Mendakota Park around the pavilion and playground equipment. They
swept turf areas at City Hall, Public Works, Fire Hall, Mendakota and Kensington Parks.
The foul lines were striped at Mendakota Park and the soccer fields and lacrosse fields
were striped at Kensington Park.
The Street Crew cleaned sod off the boulevard from plow damage. The streets are being
swept and they worked with the sweepers hauling away the street sweepings.
Enaineerina
Sam and Ryan finished collecting data for the topography survey on Callahan Place. The
project is expected to get started in late July.
Bids were received for the sanitary sewer cleaning and televising project. The low
bidder was Pipe Services Corp. with a bid of 77,303.40.
SEH consulting came to city hall on Tuesday to offer training on the new NPDES permit
track software. The software will help simplify the annual reporting process required by
the Minnesota Pollution Control Agency.
Pilot Knob
Members of the Pilot Knob Preservation Association plan to hold a small bonfire
celebration at the site on April 26th. Association members, while visiting the site to sow
native grasses and wildflower seeds have been collecting twigs and branches to fuel
their bonfire. Gail Lewellan requested a burning permit that was approved by the Fire
Marshal and the group plans to bring along rakes and shovels to extinguish remaining
embers. If winds are gusty or April showers appear the event will be postponed.
Also, next Monday, April 28th an Environmental Studies class from the Apple Valley
School District will be visiting Historic Fort Snelling to gather information on immigrants
and early settlers and asked that the chain closing the roadway be removed for several
hours so that they can visit Pilot Knob and experience the view of Fort Snelling from this
side of the river. Guy or Public Works will open the roadway for easy access to the cul-
de-sac.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
April 18, 2008
The Parks Crew put the trash barrels out in the parks. The tennis nets were
installed on the tennis courts in the parks. The pedways were swept. The
ballfields were dragged. A downed tree was removed on First Avenue and
chipped up.
Rich did a service check on the storm lift station and the pumps looked
good. The guide rails are rusty. He did sewer inspections at 665, 685, and
691 Hidden Creek. The benches for the Par 3 were power washed, primed
and painted. He dropped off fluorescent lights from Public Works, Fire
Department and City Hall for recycling.
The Street Crew and Tom went to the Minnesota Spring Maintenance
Training Expo in St. Cloud, Minnesota. The plows and sanders were taken
off the plow trucks in anticipation of starting street sweeping.
Code Enforcement
Paul issued a building permit to Kraus Anderson for 1031 Mendota Heights
Road. The valuation of the permit is $3,040,000.00. The work is for
alterations and the interior of the new and existing Patterson Dental facility.
Engineering
Ryan and Sam are surveying in the Callahan neighborhood.
Tom has been inspecting storm sewer outfalls for NPDES permit compliance.
The Avenues and Kay/Walsh Street Reconstruction project was awarded to
Friedges Contracting Co. LLC in the amount of $1,563,254.50.
Sue received the nice letter about the sweeping of Marie Avenue boulevard
(see attached letter).
Pearson Bros. moved in their equipment in anticipation of sweeping the City
streets next week.
April 18 2008
Dear Sue,
e are grateful to You inn your departaawm for arranOng
to have the Mqrie Ave boulevard (behind our place) cleaned
with the motorized sweeper on Thursday afternoon, April 17,
By chance, we happened to be there when it was being swept
The gentleman who disc it was quite friendly (we should have
asked him for his name).
You really helped us.
Thank you so much.
Joe & Jo Arm Stef ni
1820 Valleys Curve Rd
454-5372
N E W S The Pipet/me,
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
N 5 a
April 11, 2008
The Parks Crew hauled supplies out to Mendakota and Kensington Parks for
spring and summer use. The water meters were hooked up to the
outbuildings and bathrooms cleaned out at Mendakota and Kensington
Parks. Burned out light bulbs around buildings and in the parking lots were
replaced at Mendakota, Kensington and Rogers Lake Parks.
A snow plot hit and broke a manhole lid and casting on Highway 13
(MnDOT). The sanitary sewer line was jetted clean by Rich and the casting
lid was replaced with George's help. A curb stop water shut off (cover and
box) was replaced at 1320 Medora Court that a snow plot hit. There was a
possible sewer blockage at 1288 Dodd Road. The City's line was checked by
Rich and found to be ok. Blockage is in the homeowner's service line. Rich
did service checks on the lift stations at Veronica and St. Thomas. Both
looked good.
The Street Crew filled pot holes and fixed mailboxes that were damaged
from snow plows.
Enaineerina
Guy and Sue met with Dakota County Park Planners to discuss the County's
proposed greenway corridor map.
The Engineering Department met with Paster Enterprises and RLK
Engineering to review the latest Mendota Plaza submittal.
Park Construction completed mandrel testing for the storm sewer installed
with last year's Ivy Falls street reconstruction project.
Ryan, Sue, and Sam held a neighborhood meeting for this year's street
rehabilitation project on Wednesday, April 9tn
N E W S The Pipeline
LETTER
Public Works
Engineering April 3, 2008�
Code Enforcement !
Public Works
The Parks Crew cleaned up the Groundsmaster snow blower and broom. The
tandem trailer was prepared for summer. Portable satellites were ordered for the
parks for the upcoming season.
Rich did service checks on the Northland lift station, Centre Pointe lift station and
the Culligan lift station. The pumps at the Northland lift station will need seals and
bearings. He plowed the middle area streets on Monday and Tuesday. The pump
at the Rogers Lake aerator was pulled - there was a muskrat in the impellor. John
Ambrose made a guard to keep them out. Rich and John Boland put the pump
back in.
The Street Crew filled pot holes. The front cutting edge was replaced on plow
truck #303. The wing was taken off truck #308 and John Ambrose welded the
wing slide.
Date:
Tuesday, April 1st
Snow Events of the Week:
Event:
7.5" heavy, wet snow
Response:
Plow all streets (2:00 A.M.
sta rt)
Engineering
Dakota County is promoting water conservation by selling
rain barrels. The barrels cost $54.00 and will be available for
pick up on April 24th and 25th at the Dakota County
Fairgrounds. Reserve your barrel by April 20th by calling 952-
891-7000 or water@co.dakota.mn.us or contact Sam in the
Engineering Department.
The bid open for the 2008 street reconstruction project (Avenues, Kay/Walsh) is
Wednesday, April 9th at 10:00.
N E W S The Pipeline
LETTER
Public Works March 28, 2008
Enaineerina
Code Enforcement
Public Works
The Parks Crew plowed the snow from last Friday and Saturday off the cul-de-
sacs, pedways and parking lots. The groundmaster 580D was serviced and
repaired for summer.
Rich plowed the middle area streets on Friday and Saturday. The roots in the
sanitary sewer lines were chemically treaded on Keokuk, Pontiac Place, Apache
Street, Marie Avenue, Ridgewood Drive, and the Dodd Road easement. The storm
sewer was unplugged on Whitfield Drive. Pipe Services cleaned the sanitary sewer
lines from Lloyd's BBQ on Mendota Heights Road to the lift station. They also
vacuumed the lift station for grease. (Lloyd's BBQ pays for this). Pipe Services
also cleaned the sanitary sewer lines at Mendakota County Club do to Wagon
Wheel Trail (Mendakota Country Club pays for this). The Northland lift station, St.
Thomas and Lilydale lift station were cleaned.
The Street Crew replaced light bulbs at the southbound Dodd Road light.
Date:
Friday, March 21, 2008
Saturday, March 22, 2008
Sunday, March 23, 2008
Enoineering
Snow Events•
Event:
4"
2"
1"
Response:
Plowed all streets
Plowed all streets
Plowed all streets
Letters were mailed out to residents in the Somerset Park/Evergreen Knoll
neighborhood about an upcoming informational meeting regarding street
improvements.
St. Paul Regional Water Service installed the final hydrant on Kay Avenue this
week in preparation of the street reconstruction.
The street reconstruction project (Avenues/Kay, Walsh) has been getting a lot of
attention with 28 sets of plans already sold.
Sue is on vacation in Arizona.
N E W S The Pipeline
LETTER
Public Works
Enaineerina March 21, 2008
Code Enforcement
Public Works
The Parks Crew plowed the cul-de-sacs, pedways and parking lots on Tuesday.
The new tool box was picked up for the new truck. They worked on the summer
equipment getting it ready for spring and summer.
Rich was called in on Wednesday at 7:00 P.M. for a phase fail alarm at the Lilydale
lift station. There was a power outage at the Mendota Heights Road lift station at
12:45 A.M. on Saturday. The power was restored at 6:30 A.M. Rich unplugged
the storm sewers on Wesley and Dodd, Winston Court, Orchard and Lexington,
and Twin Circle. He plowed the middle areas of the city on Tuesday.
The Street Crew picked up carpeting on Acacia Blvd. and a large TV on Valencour
Court. They opened up storm pipes with the help of Rich and the jetter on Pond
View going to the pond and the Orchard and Lexington culvert.
Snow Events of the Week:
Date: Amount: Response:
Tuesday, March 18tn 3.5" Plow all streets
Enaineerin
Pearson Brothers was awarded the street sweeping project at Tuesday night's City
Council meeting. They anticipate beginning the work on Monday, April 14tn
Tom Knuth worked with a home builder in Hidden Creek to install a gravity drain
tile system that was connected to the City's storm sewer system using directional
boring methods.
Street settlements occurred at Douglas/Lexington and Mohican Lane where a
water main break repair had taken place. St. Paul Regional Water Services placed
flashers around the area and will repair the damage in the spring.
Public Works
The Parks Crew attended a Sherwin Williams Pro Show at the Minneapolis
Convention Center. New products and updated paint sprayers were
featured. They cleaned out the warming houses and took inventory of the
shovels. They attended a NPDES meeting at City Hall on Wednesday
morning. The pedways were plowed where needed. The parks "You Are
Here" signs are being finished.
Rich cut roots in the sanitary sewer lines on Apache Street, Fox Place, and
the Lexington easement. Trees and brush around fire hydrants were
trimmed throughout the City. There was a sewer blockage at 740 Main
Street. The manhole was frozen inside. The oil was changed for the pump
on 404. Grease was cleaned off the floats at the Veronica lift station. Rich
used the jet to unplug a culvert on Pondview Drive with the street crew.
The Street Crew, along with Tom and Rich, attended a seminar at Mystic
Lake Casino. The seminar was put on by Highway Technology, called Safety
in the Work Zone. There was information about working on roads, highway
laws, etc.
Engineering
Engineering finished the 2008 street rehabilitation feasibility report, started
the surveying for Callahan Place, and investigated a sewer and water main
extension to the north of Hidden Creek.
Public Works and Engineering staff attended a training class on NPDES
requirements.
Public Works
The Parks Crew replaced the circuit breaker on the aerator at Rogers Lake. They
continue to work on the "You Are Here" park signs. The ice skating rinks were
officially closed on March 1st. They were open this year from December 15
through March 1, the longest they have ever been opened. The pedways were
plowed. Truck 501 was taken to Crysteel to have the lift gate installed.
Rich helped plow the main streets on Friday and Wednesday. He attended a traffic
safety school on Tuesday. Rich plugged the pick holes in 10 manhole covers for
the upcoming spring melt. The plugs will stop the inflow from the spring runoff.
The Street Crew did pothole filling on Mendota Heights Road from Lake Drive to
Dodd Road and Dodd Road to Delaware Avenue. A few potholes were filled on
Highway 110. They plowed all the main streets and salted other city streets.
They plow trucks were washed and the sanders cleaned out. They attended the
traffic safety school on Tuesday.
Snow Events of the Week:
Date: Event: Response:
2-28-08
1"
Plow main
lines and salt all streets
3-5-08
1.2"
Plow main
lines and salt all streets
Enaineerina
Staff met with utility companies to discuss the upcoming street reconstruction
projects in the "Avenues" and Kay/Walsh areas.
Sue attended a workshop on creating green development initiatives in local
governments.
St. Paul Regional Water Services hit a gas main while replacing a hydrant on
Walsh Lane.
N E W S
LETTER Pi-pel ile
Public Works
Engineering February 29, 2008
Code Enforcement
Public Works
The Parks crews collected trash from the parks. Rinks were broomed and blown
daily to remove snow and flooded to provide fresh ice. New "you are here" signs
for the parks were worked on and the shop was cleaned and organized. The
aerator at Rogers lake was checked daily.
The Streets crew washed plow trucks and performed routine maintenance on plow
wings. Sanders made up signs for back shop per safe assure. Installed new
cabinet for gas cans, etc... Extra snow was plowed from the boulevard on Medallion
drive and Mendota Heights Road to gain access to the street light handholes for
pending repairs.
Rich checked sanitary sewer lift stations daily. Bolts were replaced in the force
main drain valve so when the new valve arrives replacement will be quick and
easy, cliff assisted. Changed out 18 broken hydrant flags around the city.
Engineering
The engineering department is still working with Bonestroo on finalizing plans for
the 2008 reconstruction project, assembling a feasibility report for the 2008 Mill
and overlay, and working with Rich on this years sewer lining project.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
February 22, 2008
The Parks crews collected trash from the parks. Rinks were broomed and blown
daily to remove snow. Pedways and trails were plowed on Tuesday. Equipment
and vehicles were cleaned and maintained; new shovel at Marie Park warming
house, wash trucks, repair broom on unit 505.
The Streets crew plowed city streets, cleared snow banks from mailboxes on Pond
View and Timmy Street and cleared snow from the pedway at Mendakota Park.
Plow truck 303 needed a new hydraulic pump, the front plow was removed and
brought to Macqueen Equipment to be replaced.
Rich checked sanitary sewer lift stations daily and annual service check up was
done at Mendota Heights Road lift station, Braun pump inspected the pump motors
and electrical system and they checked out ok. A generator was needed at the
Northland Drive lift station as Xcel energy was changing over to new transformers.
Engineering
Dakota County is holding open houses on Tuesday and Wednesday for residents to
view and comment on the proposed park plan (see attached article). Sue
attended the open house that was held in Apple Valley last week.
We have received our annual Municipal State Aid Apportionment: $290,185 for
construction and $96,728 for maintenance.
Vacationing staff: Nancy is in Cancun, Mexico; Tom K. Is in Florida; and Paul Berg
is in Maui, Hawaii. Russ Wahl will be filling in for Paul while he is on vacation.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline 2-15-08
Fft''i&n't's Days
The Parks Crew groomed the ice rinks and checked the warming houses daily. The
aerator at Rogers Lake was repaired. The broom for the ice rinks was repaired.
They met with Guy about the Pilot Knob site barricades. They plowed the cul-de-
sacs, pedways, ice rinks and parking lots.
Rich checked the lift stations and plowed their parking lots. He took the gas
detector to Continental Safety for calibration. Wagon Wheel Trail between Rogers
Lakes was televised. No leaking pipes or joints were found but some manholes
are leaking. Rich will be getting quotes to seal them. He salted the middle area
city streets on Saturday and plowed them on Thursday.
The Street Crew plowed the main streets and salted them on Saturday. All streets
were plowed on Thursday with at 3:00 A.M. start. Streets that drifted over from
blowing snow were plowed throughout the week.
Snow Events for the Week:
Date: Amount:
February 9, 2008 1"
February 14, 2008 2"
Enaineering
Response:
Salt all streets and plow main streets
Plow all streets
Sue, Ryan and Jim went to St. Paul Regional Water Services to hear their annual
report. St. Paul Regional Water Services reported on:
➢ current projects
➢ upcoming projects
➢ water rates
➢ new billing technology
N E W S he Pipeline
LETTER p
Public Works
Enaineerina
Code Enforcement February 8, 2008
Public Works
w w �
The Parks Crew continues to check the ice rinks, warming houses and groom the
rinks daily. They plowed the cul-de-sacs, pedways and parking lots on Monday
evening. The brush along the road at the Pilot Knob site was chipped up. The
new pickup truck was ordered that was approved at the City Council meeting.
Rich plowed the lift station parking lots. Rich put new batteries in the trailer
generator and main lift station generator. He plowed the middle area of the City
on Monday night.
The Street Crew plowed and sanded streets on Monday evening. They helped the
Parks Crew chip up the brush that was at the Pilot Knob Site. A few mailboxes
that were hit by the plows were repaired.
Snow Events for the Week:
Date: Amount: Response:
2-4-08 1-1/2" Plow and sand all streets
Engineering
The Engineering Department hosted a "Blue Thumb" rain garden design class on
Wednesday and Thursday evenings. There were 26 attendees that designed 11
rain gardens. Sam completed a design for a garden adjacent to the Par 3 parking
lot. Sue designed a garden for her front yard. Matching grants and construction
assistance will be provided by Dakota County Soil and Water Conservation District.
A public hearing was held on Tuesday night at the City Council meeting for the
Callahan Place project. City Council authorized staff to prepare the plans and
specifications for the project. There were about 9 residents at the hearing and
they are in favor of the project.
NEWS
LETTER
Public Works
Enaineerino
Code Enforcement
Public Works
T e Pipeline
February 2, 2008
The Parks Crew picked up trash in the parks, checked the rinks and
warming houses, broomed and blew snow from the skating rinks daily.
They ordered materials for the "You Are Here" park signs. The Rogers
Lake aerator was checked daily.
Rich and Tom attended the Collection System Seminar for the MPCA.
Some of the classes were on manhole rehabilitation, infiltration,
electrical safety and traffic control. Rich did a visual inspection on the
Victoria Road easement. He helped John Boland install the eye wash
station at the Public Works Garage.
The Street Crew worked on plow truck #303 with Force American
Mechanical to install a new computer board for the sander. The new
Mack truck was brought to Roseville Mack for recalls on the parking
brake and other warranty work. Maintenance was done on the brush
chipper to get it ready for chipping up the trees from the Pilot Knob II
site.
Engineerincl
Sue attended the annual city engineers conference. The conference is
a three day event covering the latest issues in maintaining and
improving the infrastructure of the city.
The engineering department is researching the rental of a large format
scanner to scan all as -built drawings into a digital format. Currently
the drawings are hanging on a rack and take quite a bit of abuse. The
drawings, once scanned, can either be viewed/edited on the network
or sent to the plotter to be printed.
LETws
o..�.. T E R
The
P�no�:�
.... %.f ew br
warming
the Yhouses The plow e rinks Was epa the
ous after aY s snow 503 as repaired�th eking the
Rich Are Here" park signs' Lumber was ordered and Plowed the
and Torn attended nil unloaded for
They need Wiled their
Operator's license
this school annual sanitary Sew
nse current, every year in order to keeer p
school.
There was a water to keep their
Ma -
the ice off the main break
on CO/shire
Find tractor Lane.The Street
hydrant had to the leak. The and helped Crew
because of be replaced b Y then de St' Paul Regional
cut
Road a leak. The Street St. Paul Reg sanded
the street. q fire
area, et Crew salted water
d Highway Services
Y 13 and London
Die_
January 21
Snow Events for the
Ev_— Week;
1"
Res onset
Plowed main streets and salted
Pilot Knob -Phase 2 Restoration Begins
"ews Permission from Acacia Cemetery,
Eder began re meter
growth fr removal of exotic and y' Great River
om the 15 non-native Greening work
be acquired by the cityacre Pilot Knob Phase species of trees and
erall site restoration ' Wiley
y Buck from site this wee
(under contract R°G is many k� SO°n
the Cit ging the
Y) and will be
R
's
N E W S The Pipeline
LETTER
Public Works
Enaineerina January 18, 2008
Code Enforcement Me
Public Works
The Parks Crew checked the rinks, warming houses and trash daily. They continue
to broom, blow snow and flood rinks. They attended the Minnesota Green Expo
seminars and trade show. They started the aerator in Rogers Lake and posted
"Thin Ice" signs.
Rich cut tree roots in the sanitary sewer main on Marie Avenue, Ridgewood Drive,
Warrior Pond easement and Callahan Place. He jetted the shop floor drain. Cliff
rewired the trailer generator lights. Rich also replaced the battery for the back up
alarm at the St. Thomas lift station.
The Street Crew was called in on Saturday to salt and sand after the snowfall the
City received on Friday night. The salt bin was refilled. They washed the trucks
and did maintenance on them. They are cleaning the back shop.
Enaineerinco
Engineering held an informational street reconstruction meeting with the residents
of Callahan Place. Thirty property owners representing 20 properties attended the
meeting. A couple of people expressed opposition to the curb and gutter as well
as the unit method of assessment. Overall residents appeared to be in favor of
the project.
Engineering is hosting another neighborhood meeting for the residents of the
Avenues and Kay/Walsh neighborhoods on January 23rd at City Hall starting at
6:00 P.M.
Dakota County SWCD held a meeting at City Hall for residents interested in
installing rain gardens and stabilizing shorelines on their property. There were 23
residents that attended - Mendota Heights (13), Inver Grove Heights (3), St. Paul
(1), Eagan (5), and Apple Valley (1) that attended the meeting along with Sue
McDermott, Sam Kuchinka, and Ryan Ruzek. The meeting was very informational
and educational. Residents learned the basics of gardening and native plants to
help protect our waters.
NEWS
LETTER The Pipeline
Public Works
Engineering ° a
Code Enforcement January 11, 2008 `•.••
Public Works
The Parks Crew attended the Minnesota Green Expo and attended a variety of
classes.
Rich checked the sanitary sewer line at the Mendakota Golf Course to the trunk
line on Wagon Wheel Trail. He found a little grease build up. Mendakota Golf
Course is in the process of installing a grease trap. He cut roots with the jet truck
on Ocala Lane, Decorah Lane, Simard Avenue, Miriam Street, Apache Street,
Pontiac Place and Keokuk Lane. He attended the Safe Assure training regarding
meth lab awareness and traffic safety.
The Street Crew refilled the salt bin. They continued to clean snow from fire
hydrants in the business park, street corners and site problem areas. Steve from
Force America came out to the shop to fix the sander on plow truck 303. They also
attended the Safe Assure training regarding meth lab awareness and traffic safety.
PILOT KNOB PHASE 2 — SITE CLEAN UP
Demolition and site clean up continues. Abandonment of the well at the northerly -
most house will be completed Thursday, asbestos removal has been completed at
the second house with demolition of the house and outbuildings to be completed
next week. Work has been slowed by difficult well closures. Improperly abandoned
wells are a significant threat to groundwater quality and can channel contaminated
surface or soil water into nearby drinking water wells or bedrock formations
(aquifers). Dakota County Environmental Department is requiring that both wells
(one with a 2" casing, the other with a 3"casing) be "over -drilled". This requires
the well contractor to drill a 6" bore hole thus enlarging the hole and breaking up
the existing smaller metal casing pipe before filling the hole, under pressure, with
grout / cement.
Bob McGillivay TPL, informed City staff that he will close on the property with
Acacia Property on January 25th, and the City will then purchase the property from
TPL and immediately submit payment requests to the County and DNR for the four
funding grants, that have been pre -approved, to assist with the City's purchase of
this 15 acre property.