2007NEWS
LETTER
Public Works
Ennineerin4
Code Enforcement
Public Works
The Pipeline
January 4, 2007
The Parks Crew checked the rinks and warming houses daily. Snow
was removed from the rinks and flooding continues. The door and lock
at the Marie Park warming house was repaired. The pedways were
cleaned up where needed.
Rich cut roots from the sanitary sewer lines on Kay Avenue, Walsh
Lane and Glen Hill Road.
The Street Crew is clearing snow from around the fire hydrants. The
snow banks are being winged back in the industrial park.
Enaineerina
Sue and Ryan met with three residents who live on Kay Avenue and
Walsh Lane to discuss their concerns regarding the upcoming street
reconstruction project. All concerns were addressed.
Pilot Knob Update
The City recently received Grant Funds from the DNR Environmental
Partnership Grant Fund ($14,800.00) and the Lower Minnesota River
Watershed District ($6,700.00) for restoration work and volunteer
events on the 8.5 acre Pilot Knob Phase 1 site accomplished during
2007. The applications were prepared and applied for under the
contract the City has with Great River Greening for management and
oversight of the restoration efforts to return this site to an oak
savannah similar to what the site looked like when European settlers
arrived in the 1850's.
NEWS
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
he Pipeline
December 28, 2007
The Parks Crew checked the parks and warming houses daily. They continue to
flood rinks. They swept the skating rinks and plowed the cul-de-sacs, pedways
and parking lots.
Rich plowed the snow in the middle area streets and lift station parking lots. He
used the jet to cut roots in the sanitary sewer lines on Wagon Wheel Trail, Valley
Curve and Dodd Road. Grease from the middle school was removed in the
Mendota Heights Road sanitary sewer lines.
The Street Crew plowed and salted the roads on December 22, 23 and 26th. They
started to clean off the bridge decks on Mendota Heights Road and Wagon Wheel
Trail. Broken mailboxes were fixed.
Date:
Saturday, December 22
Monday, December 24
Wednesday, December 26
Enoineerin4
Snow Events of the Week:
Event/Amount: Response:
Rain and 3" of snow
3.4"
3"
Sand and plow all areas
Plow all areas
Plow all areas (4:00 A.M.
snow emergency declared)
The Marie Creek stabilization project has been substantially completed. Attached
is a project fact sheet with photos.
Engineering staff is preparing for a January 9th neighborhood meeting for the
Callahan Street Reconstruction project.
" E `" 5 The Pi elin
LETTER
Public Works cont. Page 2
Enaineerino December 28, 2007
Code Enforcement
Tom Knuth is off for the next month enjoying time on the
beach and golf courses in Florida.
PILOT KNOB
Purchase of 15 acres of land east of Pilot Knob Road from Acacia Cemetery has
been delayed until mid -January. Thursday morning demolition crews had removed
the two out -buildings of the house located at the end of the gravel cul-de-sac.
Workers were removing / salvaging the windows and casements (installed several
years ago by MAC for sound attenuation) before demolishing the house. Crews will
separate wood, metal, and masonry items to be recycled or disposed in a landfill.
Removal of asbestos from the 1-1/2 story stucco house is underway and removal
of underground fuel tanks and several sites where excavation and removal of
contaminated soil and materials have been identified. The demolition crews are
working with another firm which performs soil testing and oversight of removal
and clean up efforts to assure that all work conforms to Minnesota PCA and Dakota
County requirements.
Attachment:
Please see the attached Marie Creek Streambank Stabilization Project Fact Sheet
0,30V SO/t Gq
tiO
S�RVATION 0�5�
Cost: The total project cost was
$45,240.
Project: A 200 foot streambank
stabilization project that incorporated
hard armor and bioengineering
techniques. A series of pools and riffl
created to dissipate energy and slow
stream velocities, was used with soil
wraps, live staking, seeding, and
planting of native woodland shrubs
Financial Assistance:
Dakota County SWCD provided
Incentive Payment Practice funding in
the amount of $17,998.50.
L
on:Heights, Oa ° ' °
0.
Dakota County Soil and Water Conservation District
4100 22011 St. W., Suite 102, Farmington, MR 55124 651-480-7777 www.dakotaswed.org
Dakota County Soil and Water Conservation District Revised 12/OS/07
4100 220"' St. W., Suite 102, Farmington, MN 55124 651-480-7777 www.dakotaswcd.org
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipelin
December 21, 2007
The Parks Crew are flooding the skating rinks. A broken board was replaced
on the hockey rink at Wentworth Park. The hockey nets were put out on
the rinks for their opening (rinks were opened on December 14th). The new
furnaces were installed in all the warming houses. The lights were repaired
on plow truck #503.
Rich assisted Cliff with repairing the crane on truck #409. The homeowner
at 1068 Overlook Road called and said they cleaned their service so Rich
jetted it. Jetti cleaned Sunset Lane after St. Paul Regional Water Services
broke the sanitary sewer line at 1255 Dodd Road. There were a lot of rocks
and parts of the clay pipe in the line. After the line was cleaned it was
lamped and televised. Rich cut roots in the sanitary sewer lines at
Chippewa Avenue and Annapolis, Winston Court, Downing Street and
Somerset Road. He also cleaned the grease of the floats at the Veronica lift
station.
The Street Crew cleaned snow off the bridge decks and sidewalks on
Mendota Heights Road and Wagon Wheel Trail. The cutting edges were
changed on the plow trucks. John Ambrose welded a new lifting bracket for
the chipper box. The streets were salted because of the water main break.
A dead deer was picked up on Marie Avenue.
Engineering
St. Paul Regional Water Services replaced a fire hydrant on Mohican Court
this past week.
There was a water main break on Dodd Road and Mears Avenue.
Engineering and Public Works had radio training on the new 800 MHz radios.
The traffic signals are out at Mendota Heights Road and Pilot Knob Road.
Temporary stop signs have been put out at the intersection.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
The Parks Crew hauled hoses and fittings out to the warming houses
for flooding ice rinks, which has already started. The warming house
furnaces were started up. The cul-de-sacs, pedways, skating rinks,
and parking lots where plowed by the Parks Crew on Saturday and Wednesday.
Rich plowed the middle area of the City and the plow lift station parking lots on
Saturday and Wednesday. St. Paul Regional Water Services broke a sewer line
service on 1255 Dodd Road, which they repaired. Rich did a sewer inspection at
750 Main Street.
The Street Crew plowed and sanded over the weekend and on Wednesday. They
repaired mailboxes. John Ambrose did welding on the plows for the Parks Crew.
Crosswalk signs were put up on the pedway on Decorah and Huber Drive.
Snow Events•
Date: a Amount: Resoonse:
o o
�< e
Saturday, December 1 4" Plow and sand all areas
Tuesday, December 5 6" Plow and sand all areas
The first winter event of 2006 was December 21st, when there was snow/ice
and the streets were sanded.
Engineering
Sue received only a handful of plowing complaints: 3 were mailbox complaints, 2
- too much snow at end of driveway and one resident who wants the use of salt
discontinued because it hurts his dog's paws.
There were two water main breaks this week: Sunset Lane and Aztec Lane.
e
a o
• y
NEWS The Pipeline =�
LETTER
Public Works R
Enoineering November 30, 2007
Code Enforcement
Public Works
The Parks Crew finished mulching leaves in the parks, where needed. The shrubs
around the park signs were trimmed up and leaves removed. The Xmark mulching
kit and decks on mowers were rewelded. Small engines were serviced and
prepared for winter storage. They finished cutting and trimming up trees along
the pedways.
Rich put in a new phase monitor in the St. Thomas lift station after the old one
went out on Sunday at 2:00 A.M., November 18th. He put root killer in the
sanitary sewer line on Lexington Avenue from Cullen to Wagon Wheel Trail.
Micheals Pipe Services finished the sanitary sewer lining project, most of the areas
had a lot of tree roots and groundwater infiltration. The areas relined were: 360
feet on Highway 13, Spring Street, Ivy Hill and easement, Dodd Road easements,
Clement Street easement, Wentworth Avenue and Callahan Place. McNamara
Contracting cleaned dirty manholes in Copperfield (manholes were dirty from the
street project). Rich cut roots in the sanitary sewer lines on Keokuk Lane and
Pontiac Place.
The Street Crew finished up adding blacktop "blisters" around high manholes and
filling potholes. A spill on Highway 13 and London Road was cleaned up. The hot
box was taken out of the plow truck and the sander was put back on. Tree stumps
were cleaned up that were dumped in the area of Trail Road and Bachelor Avenue.
Stump grinding from trees that were taken down was cleaned up and black dirt
put down. Various street name signs were made that were missing.
Enaineerina
There was a watermain break this past weekend on Mohican Lane. St. Paul
Regional Water Services fixed it over the weekend.
Stocker Excavating, Inc. substantially finished the Marie Creek project this week.
Assessments payments are being made on this past year's projects. Eight out of
58 homeowners have paid their assessments in the Ivy Falls project and 55 of the
198 homeowners have paid in the Copperfield project.
NEWS
The Pipeline
LETTER
Public Works
Engineering
Code Enforcement
Public Works
November 16, 2007
The Parks Crew brought their "You Are Here" sign to City Hall for the Parks
and Recreation Commission to look at. All of the Parks and Recreation
Commissioners really liked the design of the sign. A tree limb was removed
from the pedway on Mendota Heights Road. There were downed tree limbs
at Rogers Lake, Friendly Hills and Ivy Falls parks to pick up also.
Rich did a sanitary sewer inspection at 659 South Freeway Road. He
mowed the grass and mulched leaves at the Veronica lift station.
The Street crew finished mounting all plow blades on the dump trucks along
with the sanders and wing blades. With Dave Sorby off, George Noack
directed pot hole repairs and adding blacktop "blisters" around high
manhole castings in streets maintained by City plows. They should be
finished by the first of next week.
Engineering
Sod work is being done on the Ivy Falls project.
Scherff, Inc. excavated the ditch along Victoria Road north of Marie Avenue.
The ditch was filled with silt and sand. Stone rip -rap was added to prevent
future erosion problems. Work was completed this week.
Contractor mobilized equipment for the Marie creek stream bank
stabilization project. Trees have been cleared and the contractor is
anticipating to complete most of the project during the short holiday week.
Sue is attending the MPWA seminar at the Earle Brown Center in Brooklyn
Park. The seminar covers innovative techniques in Public Works
Management.
N E W S
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Polpelmine
watemm
The Parks Crew worked on the "You Are Here" signs for the Park's Commission
meeting next Tuesday. The donated bench has been installed in Valley Park.
Black dirt was hauled in, leveled out and seed put down around the bench area.
They attended the Safe Assure meeting on Wednesday morning.
PARK "YOU ARE HERE" SIGNS
The Parks and Recreation Commission desires to place new signs, sort of a "You
Are Here" sign in City Parks or along significant trail segments throughout the City.
The sign will include a color map of the City's parks and trail system along with
other information such as Dog Leash, Motor Vehicle or Motorized Boat Restrictions,
etc. John Boland and Park Leadsperson, Terry Blum have assembled a `prototype
sign design" for review by the Parks Commission next Tuesday that will be on
display outside the front entrance at City Hall. If the Commission approves of this
prototype and City Council authorizes funding for materials, Public Works staff will
assemble the signs during "slow or down time" this winter for installation next
summer.
Micheals pipe liner is half way done relining the sanitary sewer lines on the north
end of the City. Rich worked on the Mendota Heights Road lift station heating
system for winter by putting in a new filter, a new fan belt and greasing the unit.
The Street Crew relamped the red arrow that was out north bound on Dodd Road
and Mendota Heights Road. The catch basin at 105 Douglas Road was cleaned of
leaves. Snow removal equipment was mounted on the dump trucks. A dead
goose was picked up on Mendota Heights Road. The new 304 truck was brought
to Kramer Spring to be DOT inspected and certified.
Enaineerina
A preconstruction meeting was held on Thursday for the Marie creek bank
restoration project. Construction starts on Monday.
Sod work continues on the Ivy Falls street reconstruction project. Park
Construction is raising manholes.
Public Works
The Parks Crew stored the soccer goals, soccer nets and picnic tables
for the winter season. The parks throughout the City were fertilized.
A cement pad was installed for a donated bench in Valley Park off the
pedway. Tennis nets were taken down and the gates locked at the
tennis courts.
Rich checked the manholes in the Copperfield neighborhood because of
the street construction project. There was some dirty sanitary sewer
lines found that will need to be cleaned. A broken manhole cover was
changed on First Avenue and Brookside Lane. A water box was fixed
on South Plaza Drive.
The Street Crew reinstalled street name signs on Emerson Avenue and
Hingham Circle. Three downed trees were removed by the creek on
Spring Creek Circle. Pot holes were patched on Stanwich Lane,
Douglas Road, Victoria Curve and Lilac Lane. Preparation work and
black top was put down at the entrance to the Civic Center ball field
and pedway, Mendota Height_ ,.,ad and Huber Drive, and in front of
the Qwest building. The new dump truck was picked up that is
replacing #304. The Halloween bonfire was extinguished and hauled
out. This year there were not a lot of large limbs in the bonfire pile.
Engineering
There was a water main break on TH 13 last weekend near Happy
Hallow causing a road closure.
Boulevard restoration started on the Ivy Falls Street Project.
Staff learned how to operate the new projector in the Council
Chambers.
IV E iN SThe Pipeline
LETTER
Public Works
Engineering October 26, 2007
code Enforcement
Public Works
The Parks crews cut grass and collected trash. Irrigation systems were repaired at
Mendakota, Kennsington and City Hall. They also repaired a light on the fire
marshals truck and installed new tires on one of the squad cars.
The Streets crew restored boulevard areas in several locations were curbing was
replaced. They are administering the cleanup for the Halloween bonfire and piling
brush. Locates were called for stump removal on city property and catch basins
were cleared of leaves. Streets signs were reinstalled on Huber drive at Decorah
and Mendota Heights Rd. Met with contractor about proposed ditch improvements
on Victoria Rd north of Marie Ave.
Rich checked sanitary sewer lift stations daily and cleaned grease off of floats @
Veronica lift. Completed fall inspection of Lilydale storm sewer and exercised
pumps at Marie Park. Winterized tank sprayer used for spraying weeds.
Engineering
Streets were paved in the Copperfield mill and overlay project and sod is being
placed.
Ryan attended the Minnesota water resource conference which covers innovative
storm water management techniques.
The remaining storm sewer was installed in the ivy falls neighborhood and sod is
planned to be placed early next week.
Crews from Prairie Restorations began over -spraying for new / young Buckthorn
plants in City parks where mature plants have been removed. During the past four
years removal and eradication efforts have been ongoing in all City parks except
Valley Park. Once mature plants are removed from an area, over -spraying to
prevent re-emergence of new plants must continue for three or more years. In
addition to chemical treatments at other parks, work on removing mature plants in
Valley Park will begin in November / December once snow is on the ground.
Removal efforts will focus on areas 50 to 100 out from existing trails. Valley Park
is over ninety acres in size and will require several years to remove all mature
plants with over -spraying of cut areas in following years.
IU C \A/ C � ■ � M ■ N
Public Works
The Parks Crew finished blowing out th
out of the pipes in Mendakota Park and
were removed. A downed tree was ren
Wentworth Park and Fourth Avenue. It
ANN
Op�
Rich cut tree r e ana uaiiahan
Place. He Jett h" the Street Crew. A
new pump leverlex Pipe. Rich did a
sewer inspection on Wagon Wheel Court.
The Street Crew cleaned catch basins. The fence was put up for the Halloween
bonfire site. Street name signs were put up because they were missing' at
Brookside &Laura and Ocala & Decorah. Prep work and patches were put in by
the new curbs for catch basin repair,at Garden &`'Hiawatha and Park Place &
Boardwalk. Potholes were filled on Mendota Heights Road east' of the 35E bridge
and at Wesley Lane and Wesley Court.
Code Enforcement
Patterson corporate headquarters at 1031 Mendota Heights Road applied for a
building permit for two additions to heir building. The scope of the project
includes anaddition shell on the south and`east side of the existing structure and
an interior demolition of the first and second floor. The estimated cost of the
project is $4,000,1000.00.
cots, sanitary sewer
on
,Flex
ThE
&o
the
ed� the storm sewer line o
and cable was installed
sprinkler systems. The water was drained
Kensington Park after the water meters
oved from the pedwau between ,v
was cut up and chipF
r lines on Keokuk Lan
Hill Road wit
on the jet truck by,
aerinq
in has limited the amount of progress on the ongoing reconstruction and mill
lay projects. Let's hope for some nice weather before the snow flies to get
)jects completed.
iment
Attached is a letter from a happy resident thanking Sam
new rain garden.
for their
LETTER The Pipeline
Public Works
Enaineerinc>
October 12, 2007
Code Enforcemeni
�,114
Public Works
The Parks Crew striped the soccer fields, cut grass and mulched leaves. Sprinkler
systems were winterized at Mendakota Park, Kensington Park, City Hall and the Fire
Hall. They attended Turf Works Fields Days and got information on new products and
new equipment.
Rich cut roots in the Victoria Road easement. He was called in at 4:30 A.M., Tuesday
because of a power outage at the Northland Drive lift station. Power was restored at
1:00 P.M. He inspected the manholes on First Avenue, Second Avenue, Third Avenue,
Fourth Avenue, Vandall Street, Clement Street. Sam from Engineering helped Rich
measure barrel sections and count rings on those streets for Engineering.
The Street Crew cleaned storm grates. A beehive was cleaned in the runoff pond
behind Cherry Hill Road. It was draining slow because the pipe was plugged and Rich
will jet it. Missing street name signs were put up on Victoria Road and Summit Lane.
Street name signs were made up for Ocala Lane, Decorah Lane, First Avenue,
Brookside Lane, Laura Street, and Apache Street. They attended a safety meeting
with Safe Assure the topics were "Personal Protective Equipment" and "{Cold Weather
Awareness". The traffic signal on Mendota Heights Road and Highway 149 "don't
walk" light is out. The Street Crew relamped it and it was still out. Upon further
investigation, they found mice were chewing on the wiring harness and MnDOT
Electrical Services was notified.
ENGINEERING
Restoration has continued on the Ivy Falls Reconstruction project. Driveways have all
been patched and boulevards have been graded with new topsoil.
The NURT trail construction has begun near town center with the contractor
excavating to place the base for the new trail.
Weather limited the amount of work the contractor could complete in the Copperfield
Neighborhood. Paving is expected to be completed late next week.
Ryan met with Mn/DOT regarding three separate drainage issues on Dodd Rd (TH
149). Mn/DOT is working on funding and design for the three locations which should
be constructed sometime in 2010. Two of the areas are where drainage leaves the
Somerset Country Club. The new system should greatly reduce the amount of erosion
currently experienced by several homes.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
* + October 5, 2007
Columbus Day ,
The Parks crew marked all tree stumps in the parks for grinding.
Broken hockey boards were replaced at Wentworth and Friendly Hills
hockey rinks. All mowers were serviced. The mulching kit was put on
the xmark.
Rich was called in Wednesday night for a high water alarm. Grease
was caught on the floats causing them not to work. He cut roots in
the sanitary sewer lines on Highway 13 from Garden Lane to Fremont
Avenue, Annapolis Street east of Chippewa Avenue, Hingham Circle
and Downing Street.
The Street Crew attended the annual Fall Maintenance Expo in St.
Cloud. Sessions included snow and ice control on roadways, dealing
with the public, and street sweeping dos and don'ts. Catch basins
were cleaned of leaves. Tim cleaned up an excessive amount of leaves
off Marie Avenue by Valley Park. Temporary street name signs were
put up at Wagon Wheel Trail and Wagon Wheel Court. Garbage was
picked up on Mendota Heights Road and Lake Drive.
Engineering
Streets in the Ivy Falls neighborhood were paved this week. Work
continues on both the Ivy Falls project and the Copperfield mill and
overlay.
The Engineering Department held a public informational meeting for
the proposed street reconstruction meetings for the Avenues
neighborhood and Kay Avenue/Walsh Lane. The meeting was well
attended with 39 properties represented and at least 50 people
present.
Public Works
The Parks Crew trimmed trees along the pedways on Lexington Avenue, Marie
Avenue and Victoria Curve. Downed tree limbs were picked up in the parks and
chipped up.
Rich was called in on Thursday at 6:00 P.M. because of a power outage at the
Lilydale lift station. The power was out until 11:30 P.M. He inspected manholes
on Kay Avenue, Walsh Lane, Summit Lane, Victoria Court, Vandall Street, and
First, Second, Third and Fourth Avenues. He helped the Parks Crew pick up
downed trees and chip them up.
The Street Crew patched potholes on Knollwood Court. Stop signs and street
name signs were reinstalled on Mendota Heights Road and LeMay Lake Road.
Street name signs were reinstalled at Stanwich and Dodd Road, Ivy Falls Avenue
and Sylvandale Road. Trees were cut up that were down from Monday night's
storms. Trees were down on Kirchner, Hampshire and the end of Victory Lane.
Dead elms were removed from Marie Avenue east of Dodd Road.
Engineering
Pine Bend Paving removed damaged trail areas, patched and overlaid
approximately 1100 feet of trail south of Marie Avenue beginning at the Marie
Avenue pedestrian underpass tunnel opening. Several sections of trail had been
damaged during the Xcel Energy power line and pole replacement project
completed in early summer. Xcel Energy crews repaired disturbed turf areas and
have been asked to reimburse the City for this trail repair/overlay.
Refreshing of paint striping on City streets was completed on Wednesday of this
week. Each year the City refreshes/repaints approximately one-third of the total
striping and paint markings on City streets with an epoxy based paint that, on
average, provides from three to five years of visible coverage. This year over
39,000 lineal feet (7.4 miles) of four inch wide yellow and white striping was
applied to Lake Drive, Centre Pointe Drive, Mendakota Drive, Dakota Drive,
Victoria Road, and portions of Centre Pointe Curve, Hunter/Orchard and Pilot Knob
Road north of Hwy 13.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipelml NZN :3
September 21, 2007,
The Parks Crew trimmed trees along the pedways. Pilot Knob trash barrels were
picked up. They serviced the mowers. The roots from the trees were sprayed
along the pedway on Huber Drive.
Rich cleaned the sanitary sewer lines on John Street, Ivy Hill, and Highway 13. All
of these are being relined by Micheals Pipe. Micheals Pipe also started the sanitary
sewer line rehabilitation work. The rootsaw broke down and was taken to ABM
Equipment for repair.
The Street Crew repaired a broken catch basin and curb at High Ridge and Warrior
Drive. A gate box extension was put in, the depression was filled in, and blacktop
put down at Pilot Knob Road and Mendota Heights Road. A street patch was put in
at Park Place and Farmdale Road.
Engineering
The contractor on the Copperfield mill and overlay project replaced the concrete
and curb panels this week. Milling of the streets will begin on Monday, September
24tn and last through Wednesday, September 26tn
Storm sewers were installed on Woodridge Drive for the Ivy Falls reconstruction
project. Phase I of the project has new blacktop. Gravel was put down on 3/4 of
the streets of Phase II. The contractor has been slowed down this week with the
heavy rain. Sam and Ryan have been busy all week surveying the project.
Repairs to the trail in Valley Park, south of Marie Avenue, began on Thursday of
this week and will resume next week. City Council on Tuesday night authorized
Pine Bend Paving to do the repairs and overlay 11,000 feet of the trail in this park.
Street striping and markings at 10 locations throughout the City may begin today
and work will be completed next week.
Engineering hosted a fabulous cookout for City employees on Thursday. The
weather was chilly at lunch time, but the food was excellent!!
Please see the attached thank you letter from a resident on Emerson Avenue
regarding their new rain garden.
9
o rf
O
P
P R
�
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
f
September 14, 2007
The Park Crew sprayed the pedway on Huber Drive for weeks that
were growing in the cracks. John Boland helped install in the rain
gardens in the Somerset neighborhood. The irrigation system was
added on to at City Hall in the newly planted shrub areas.
Rich was called in Saturday morning for a phase failure at the Lilydale
lift station. He reset the phase monitor. He helped with the rain
gardens also. He helped plant plants and watered them. Rich raised a
manhole up 1' on the Apache Court easement. He attended Safe
Assure's confined space training.
The Street Crew removed trees from the storm. School zone signs
were installed. Crosswalks were painted.
Engineering
The majority of the rain gardens were planted this week. Sam put in
many hours with assistance from Rich, John Boland, Nancy, Sue, Guy,
Ryan and residents. The remaining gardens will be planted by the
homeowners.
McNamara Contracting worked on the Delaware Avenue/Huber Drive
turn lane, sidewalk, curb and gutter, and removal and replacement in
the Copperfield neighborhood.
Park Construction installed curb and gutter on the first phase of the
Ivy Falls street reconstruction project. Paving is scheduled for
Monday.
Please see the attached Dakota County newsletter regarding the North
Urban Regional Trail, Phase II.
North Urban Regional
Trail, Phase II
September 4, 2007
Bids were received on July 3, 2007 for the second
phase of the North Urban Regional Trail (NURT)
project. The County Board awarded the project to
Max Steininger, Inc. Work on this project will begin
on September 10, 2007.
C�A
What's Being Done?
The North Urban Regional Trail (NURT) is a paved
bicycle and pedestrian trail that connects the cities
of Lilydale, Mendota Heights, West St. Paul, and
South St. Paul. Phase II of the project continues the
trail along TH 110 from Dodd Road to Charlton
Street in Mendota Heights and West St. Paul. This
trail will connect to two existing trails, one along
the east side of Dodd Road, and the other along the
north side of T H 110 east of Charlton Street.
What Should I Expect?
On Monday, September 10, survey crews will begin
construction staking for the project. Clearing of
trees and brush within the construction limits will
begin. Some trees and plants will be relocated. This
project includes some storm sewer work in various
locations, installation of curb and gutter, and several
retaining walls will be constructed. Paving and
landscaping will take place toward the end of the
project. Private utility work may begin prior to
September 10 and continue throughout the project.
For the safety of both the construction workers and
I►1
When Will The Work Be Completed?
It is anticipated all work will be complete by the
end of October.
More Information
This construction update is being delivered to
residents and businesses near the vicinity of the
construction. The following names and phone
numbers are for your use if you have questions or
concerns about the project. For notification by email
of any updates to the website, email your request to
the Project Inspector. If you have any special needs,
don't hesitate to call or visit:
htt :/h"n x,,dakotacounLy.us/EnvironiiientRoads/RoadConstruction/Current
PROJECT INSPECTORS
Erin Borchert
952.891.7908
Erin.Borchert@co.dakota.mn.us
Mark Jelinek
952.891.7916
Mark.Jelinek@co.dakota.mn.us
EMPIRE TRANSPORTATION OFFICE
952.891.7900
Monday through Friday
7 a.m. to 3:30 p.m.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
August 31, 2007
After Tuesday morning's storms there were a lot of trees down throughout the
City. The Parks Crew chipped up trees from Rogers Lake Park and Friendly Hills
Park which were the worst hit parks. Graffiti was cleaned up at Valley Park. The
Par 3 mower was repaired as was the big Toro, 580d and the Xmark. The soccer
fields were laid out and striped. The water tower storage area was cleaned.
There was damage to the backstop at Mendakota Park.
Rich checked Lilydale's bad sewer line every day. There were power outages
Tuesday morning from the storms at all lift stations. Rich was called back Tuesday
evening at 5:30 p.m. because the power was out at the Veronica lift station until
7:30 P.M. He cleaned sanitary sewer lines on Wentworth and Winston Court at the
easement. Both had roots in them. Rich helped the Parks Crew clean up the
water tower storage area.
The Street Crew cleaned up after numerous reports of trees blocking the streets.
The hardest hit neighborhoods were Curley and Friendly Hills.
The four summer helpers last day at Public Works was August 30`h. All the
summer employees are going back to school.
Engineering
Wagon Wheel Trail is still closed as curb and gutter is being put in the Kipp
Addition.
Street reconstruction continues in the Ivy Falls neighborhood with installation of
storm sewer and grading.
The Copperfield neighborhood mill and overlay project starts next week with
construction of the right turn lane at Delaware Avenue and Huber Drive.
Code Enforcement
Paul Berg was in a motorcycle accident yesterday. He is in the hospital with
broken bones in his right hand, a bruised liver, and a couple of broken ribs.
Luckily he was wearing his helmet or it could have been a lot worse.
LETTER
Public Works
Enciineering
Code k August 00
Public Works
The Parks Crew made playground repairs in Ivy Falls Park. They performed
routine maintenance on the mowers.
Rich checks the Lilydale sewer line daily because it is partially broken and
needs to be dug up and repaired. He cleaned sewers on William Court
(found roots), Victoria Court easement and Glen Hill Road. He put
landscaping and wood chips around the Marie Park storm lift station. The
root saw broke down and Lenny rebuilt it with new bearings and seals.
The Street Crew cleaned catch basins and repaired one at Medora and
Emerson. Low hanging limbs were cut on Mendota Heights Road and
Executive Drive. Crime watch signs were replaced on Upper Colonial and
Knollwood Lane north of Emerson. Stop signs were replaced at Huber and
Decorah.
Engineering
On Wednesday, a water main broke on the west end of Ivy Falls Avenue.
The preconstruction meeting for the Copperfield neighborhood project was
held at City Hall on Thursday. McNamara Contracting plans to start
construction right after Labor Day beginning with the right turn lane at
Delaware Avenue and Huber Drive.
Dakota County held a preconstruction meeting for the NURT (Northern
Urban Regional Trail). The contractor has 30 working days to finish
construction. Construction is planned to begin September loth
Ryan and Sam are continuing to survey the Ivy Falls neighborhood. Sam
"the awesome bee whisperer" was stung five times in one day while
surveying this week.
NE`"s - LETTER `�f The Pipeline o
Public Works ' 0 0 p °
Engineering 0 °a p0 �A
Code Enforcement August 17, 2007 0
Public Works
The Parks Crew removed rec rocks from the infield at Mendakota Park on field #3,
put down new rec rock, and leveled it out. Old turf was removed from in front of
the soccer goal on the west field at Kensington Park and new sod put in. Other
areas were resodded as needed. Downed tree limbs were picked up from parks
and along pedways from the storms that came through. Lines were painted on
basketball courts in the neighborhood parks. Fields were dragged for a church
league tournament. The soccer fields were fertilized at South Kensington Park.
A pump was plugged with a hand towel at the Lilydale lift station. The towel was
removed by Braun Pump. Rich cleaned sewers on Mary Adele, Patricia Street,
Theresa Street, and Timmy Street. There were roots found on Timmy Street and
Theresa Street. Rich did a sewer inspection at the Mendota Heights Par 3 Golf
Course. There were power outages on Saturday, August 11, at the Lilydale lift
station - Mike Maczko responded, Center Pointe on Saturday morning - Terry
Blum responded and Centre Pointe on Saturday evening - George Noack
responded.
The Street Crew met with a John Deere factory warranty representative because
the backhoe is settling and the representative authorized to have it repaired.
Brush was trimmed back to clear sight distance on Douglas and Victoria. Catch
basins were cleaned. Trees were cleaned up after Monday night's storms. Trees
blocked streets on South Lane, Summit Lane, end of Spring Street, and Delaware
Avenue. A permanent pedway sign was installed on Wachtler and Highway 13.
Engineering
Tom Knuth, Ryan and Sam staked curb in the Kipp Addition. Storm sewer is being
installed this week in the Kipp Addition.
Ryan and Sam are surveying the Ivy Falls neighborhood. Water main is being
replaced this week in the neighborhood.
Thursday was Mandy's last day as she is returning to school in Ames, Iowa.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
August 10, 2007
The Parks Crew aerated the soccer and ball fields throughout the City. The
hockey boards were painted at Wentworth Park to cover up graffiti. The
fields at the Civic Center and Mendakota Park were top dressed.
Rich's summer helper, Andy, filled in for Rich while he was on vacation.
Andy trimmed trees in the sewer easement in Friendly Hills. He painted fire
hydrants on Lexington Avenue, Centre Point Curve and Centre Point Blvd.
Public Works treated the City Hall and Police employees to a summer picnic.
The food was excellent and the day beautiful. Thanks to Public Works
employees!! A great time was had by all who attended.
Engineering
There was a water main break on Monday at the east end of Lakeview
Avenue.
On Wednesday, Sue, Guy, Sam, and Mandy toured the Shakopee
Mdwankanton Sioux Community's Wastewater Reclamation Facility. The
$20 million facility is the cleanest, most advanced wastewater plant in
Minnesota. Effluent from the facility is used to irrigate the community's golf
course and other areas. It also features a 31,000 sf green roof that
contains more than 45,000 seedlings along with seeds from native prairie
grasses and flowers.
Sue will be on vacation in sunny California the week of August 13`h
Sam is out of the office until Tuesday, he is hiking the Rockies in Laramie,
Wyoming.
NEWS
LETTER
Public Works
Engineering
Public Works
The Pipelin
August 3, 2007
The Parks Crew cleaned up the back shop. Trees were trimmed along
the pedways and in the parks. A swing was repaired at Rogers Lake
Pa rk.
Rich painted the storm sewer lift station panels and fire hydrants. He
jetted the sanitary sewer lines on Wagon Wheel Trail and in the
Curley's easement. The veronica lift station floats were cleaned. He
did a sanitary sewer inspection at 2130 Timmy Street. He inspected
the raised manholes on Lexington Avenue after the overlay project
was completed.
The Street Crew helped the Parks Crew clean up the back shop. The
debris was cleaned out of the ditch on the south end of Celia Road and
Victoria. Signs were made for the Police and installed. Pot holes were
patched on Evergreen Knoll.
Engineering
Bids were opened on Wednesday for the Copperfield Addition
Rehabilitation project. The low bidder is McNamara Contracting in the
amount of $541,761.30.
Water services are being constructed at the Kipp Addition.
Dakota County came to City Hall on Thursday to show staff the new
web -based GIS program.
NEWS
LETTER i he tolpeiine
Public Works
Engineerinci July 27, 2007
Code Enforcement
Public Works
The Parks crew worked the state baseball tournament for the Mendota Heights
Baseball Association. They trimmed trees and ground stumps along pedways and
in parks were needed. Trash was collected from parks, mowing, etc...
The Streets crew replaced stop sign on Mendota Rd and at the entrance to
Mendakota Country club. Installed a new yield sign, cleaned storm grates, cleared
a downed tree on Delaware and Huber Dr (notified Dakota County), and removed
a topsoil edge on Hunter Ln (temporary fix until curb and gutter can be installed).
Dave and Sue also inspected the ditch on Victoria Rd between Marie Ave and
Douglas Rd, Rip rap should be installed.
Rich checked sanitary sewer lift stations daily. Rich cleaned he sewer main using
the jet truck on Overlook Rd, Overlook Ln, Vicki Ln, Douglas Ct, and Douglas Rd.
On Wednesday Gartzke Construction replaced the 42" storm sewer pipe at
Wachtler and TH 13 and placed rip rap In the TH 13 ditch. The portion of the trail
that was disturbed by the construction will be repaired by Opus.
Bituminous Roadways completed the mill and overlay of the trail on Wachtler
south of Cherry Hill Road.
Dakota County's mill and overlay project on Lexington between Vail and TH 13
was completed this week.
Installation of the Sports Tile surfacing material at Valley Park tennis court was
completed on Thursday. The new court surfacing will be available for use Friday
afternoon. Earlier in the week Public Works removed a number of dead elms trees
along the easterly stream side of the courts which has "opened up" the area. The
mile long trail from Marie Ave. northerly to Hwy 13 is the most heavily used trail
segment (bikers, walkers and canine companions) in the City. Signs will be placed
in the all of the City's tennis courts next week asking residents to try the new
surfacing at Valley Park and to provide feedback to City staff.
NEWS
LETTER
Public Works
Enaineerinq
Code Enforcement
Public Works
The Pipeline
July 20, 2007
The Parks Crew trimmed trees in the parks and along pedways
throughout the City. Graffiti at Rogers Lake Park was cleaned up. A
broken chalker was repaired from Mendakota Park. A torn home plate
on field 4 was replaced at Mendakota Park. Weeds were trimmed
along pedways and around sign posts and hydrants.
Rich cleaned the sanitary sewer lines on Stratford Road, Coventry
Court, Walsh Lane, Avanti Drive, Faro Lane, Summit Lane and Marie
Avenue. Two manholes were raised in the easement at Ivy Hills
Townhomes.
The Street Crew patched potholes on Mendota Heights Road between
Dodd Road, and Delaware Avenue and on Evergreen Knolls. A catch
basin was repaired at Wachtler Avenue and Emerson Avenue.
Enaineerinq
Sue attended meetings on both the Eagan -Inver Grove Heights
North/South Corridor Study and the Robert Street Transit Corridor
Study.
Sewer and water were installed at the Wagon Wheel Trail intersection.
Class 5 should be installed on Monday. One lane is open, but the road
is still closed.
Lexington Avenue mill and overlay will start tomorrow (Saturday).
Ryan has taken some time off and is on vacation in Colorado.
11
NEWS The Pipeline
F `'
LETTER ... I
Public Works AftJ
Enaineerina July 13, 2007 S
Code Enforcement '
Public Works
The Parks Crew trimmed trees along the pedway on Wentworth Avenue. The sprinkler system
at City Hall and Mendakota Park was worked on. Broken boards were repaired on the park
bench at Mendakota Park along the pedway.
Enaineerina
The retaining wall along Wentworth Avenue west of Dodd Road, which had deteriorated due to
road salt, was replaced on Monday by Blaeser Landscape and Construction. This trail section
and retaining wall were originally installed adjacent to Wentworth in 1990 near the Somerset
19 Condominiums. Approximately one hundred and fifty feet of old concrete modular block
wall was removed and replaced with a natural stone product and drain pipe, that will not be
affected by winter road salt. The foreman of the five man crew reported that many of the
residents at Somerset 19 favorably commented on the new wall construction.
Six contractors submitted bids last week to Dakota County for construction of the NURT trail
along the north Highway 110 frontage road from Dodd Road easterly to Delaware Avenue. This
federally funded project, administered by Dakota County, had a construction estimate of
$750,000. The low bidder, Max Steininger, Inc. (Eagan, MN) submitted the successful low bid
of $682,213.69. Work is scheduled to begin later in July with completion expected in
September. City staff plans to attend the contractor's pre -construction meeting and will
periodically monitor the project and provide assistance, if requested. The trail segment along
Town Center will be illuminated by light bollards identical to ones in the Village at Mendota
Heights / Town Center development located on the northeast corner of Highway 110 and Dodd
Road / Highway 149.
On Tuesday a representative from EMI gave a presentation on a new product for street
overlaying. The process is similar to the slurry seal which has been utilized in the past with
poor results. It is a cheaper application than a full mill and overlay but until performance over
time is tested and positive feedback received the city has no plans to install it on any streets.
There were two bid openings on Wednesday. The first was for the Ivy Falls reconstruction
project, seven bids were submitted for the project. The low bidder was Park Construction at
$819,000, well below the estimate of $940,000. The project should get started before the end
of the month. The other opening was for the sewer lining project. Last year a portion of the
cities sewer system was cleaned and televised and problem areas were noted for repair
(problems in the sewer are generally infiltration of groundwater, cracked pipes, missing
pieces, etc...). A liner will be installed in the deficient areas to extend the life of the system
and reduce the quantity of water sent to the treatment plant. The low bidder for this project
was Michel's Corporation with a bid of $89,000 with the estimate being $107,000. It appears
to be a good year to have projects going and contractors being competitive for the work.
An application was submitted to Dakota County SWCD for a stream bank restoration project
along Marie Creek. A number of properties have been experiencing major erosion after storm
events and the project would install innovative armoring and greening techniques to stabilize
the banks and minimize further damage.
The Kipp addition project is getting underway. Clearing trees started on Thursday and the
contractor expects to get the utilities started early next week.
NEWS
L E T T E
Public Works
Engineering
Public Works
e Pi pel'i
June 30, 2007
The Parks Crew pulled weeds around the park signs throughout the parks. A bad sprinkler head was replaced at
Mendakota and Kensington Parks. Basketball courts were washed down and prepared for line painting.
Rich cleaned sanitary sewer lines at Mendakota Park, Warrior Drive easement, Dodd Road easement, Park Drive,
Hampshire Drive and Hampshire Court. The sanitary sewer line was visually inspected from the Mendakota Golf
Course down to Wagon Wheel Trail. There was a lot of grease built up. The grease build up will be reported to
Mendakota Golf Course. Rich did a sewer inspection on Centre Pointe Drive. Rich attempted to plug a five gallon
a minute leak of ground water into the manhole on Hampshire Drive. The attempt didn't work. Visu-Sewer is
coming out to look at the leak and provide a bid.
The Street Crew patched Ellen, Chippewa, John, and Junction Lane. The pedway and bridge were blacktopped
behind Somerset School. A dead tree was removed on city property at Pagel Road and Havenview Court.
Engineering
The final lift of bituminous pavement was installed on Delaware Avenue on Wednesday.
Crack filling and court surface repairs were completed this week at the tennis courts in Ivy Hill, Marie, Wentworth
and Friendly Hills Parks. Valley Park courts will be resurfaced using a sports -tile system installed on/over the
existing court surface in mid -July.
Great River Green conducted a "controlled burn' of the Pilot Knob site on Thursday morning. Originally scheduled
for Wednesday, the burn was delayed until Thursday when wind conditions would be better. On Wednesday, the
GRG crews watered and soaked areas adjacent to the site, especially the large stockpile of trees and debris Acacia
Cemetery has accumulated west of Pilot Knob Road. The first light -up began at 9:30 and was basically completed
around 11:30. Wetting down and control of smoldering wood embers to prevent a possible re -start of a fire, once
the crew had left the site, continued until around 1:30 pm. Gail Lewellan and Deborah Karasov, GRG Director, were
on site and Guy captured a number of photos of the burn operation.
The next step of the restoration plan will be to prepare the site for physical improvements (walking trail, overlook,
parking, etc) followed by restoration of native plants and grasses. Another clean up of the site by staff to remove
debris left from prior uses (old bottles, metals, wood, etc), that is now visible thanks to the burn will be done early
next week.
On Friday night, June 29th, the Skate Shop (located on Ford Parkway in St. Paul) is holding a FREE barbeque (hot
dogs, brats, etc) at the Skate Park in Roger's Lake Park beginning at 5:00 pm until sundown. The event is named
"Familia" (Family in Spanish) and the sponsors hold a similar event each week at various skate parks throughout
the area during the summer. Tomorrow night is Mendota Heights turn. Last years event was well attended with the
upper parking lot completely filled with cars.
Please see attached thank you letter from a happy resident in Mendota Heights.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
Jhe Pipelin
June 21, 2007
The Parks Crew worked a tournament for Mendota Heights Baseball Association by
dragging fields and chalking the foul lines. Newly planted and young trees were
watered. Rec rock was hauled in and put down in the infields at Mendakota Park
and all fields were graded. All irrigated parks were fertilized (Mendakota,
Kensington, Fire Hall and City Hall). The signs and fire hydrants along the
pedways were weed whipped.
Rich jet cleaned the sanitary sewer lines on Abbey Way, Haverton Road, Haverton
Court, Canton Court, Winthrop Court, Morson Court, Pond Circle West, Pond Circle
East, Stockbridge Road and Whitfield Drive. Two fire hydrant flags on Abbey Way
and one on Whitfield Drive were changed.
The Street Crew trimmed trees, on Emerson Avenue and Delaware Avenue that
were causing sight distance problems; and on Chippewa and Simard that were
blocking street name signs. Old sign posts were pulled out on Knob Road,
Highway 110, Northland Drive and Mendota Heights Road. They hauled in the rec
rock and black dirt for the Parks Crew. Pearson Bros. returned to sweep up the
chip seal rock.
NEWS
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
The Pipeline
June 15, 2007
The Parks Crew cleaned Mendakota Park around the building and cleaned up
rec rock off the cement area. They worked the USSSA tournament. The
irrigation systems at Mendakota Park and Kensington Park were tested. The
door handle on the concession stand at Mendakota Park was repaired after
vandalism. A downed oak tree was cut up and cleaned up at Friendly Hills
Park. Mulch was put down around newly planted trees.
Rich sprayed round up (total weed killer) in the right-of-ways for the Street
Crew and around fence lines for the Parks Crew. He cleaned sanitary sewer
lines on Copperfield Drive, Fieldstone Drive, Stone Road, High Pointe Road,
Watersedge Terrace, Pond View Drive, Pond View Court and Fieldstone Court.
The Street Crew patched potholes on Wagon Wheel Trail, Eagle Ridge Drive,
Downing Street, Brompton Court and Highway 13, Kay Avenue and Walsh
Lane. McPhillips was called in to sweep up debris after a vehicle fire on Laura
Court. Gartzke Construction did major catch basin repair on Boardwalk and
Park Place, Hiawatha and Garden Lane, and Victoria Road south of Highway 13.
George helped the Parks Crew with the bobcat and grapple bucket to pick up a
downed tree.
Enaineerina
Sue met with Lynn Clarkowski, the new MnDOT area manager for the south
metro area. We discussed local highway issues. Lynn also provided contact
information for MnDOT's landscape partnership program. Sue will look into a
potential landscaping project along TH 110.
A preconstruction meeting was held for the Somerset Rain Garden Project.
The concrete and paving work is finished at the Mendota Heights Road/Pilot
Knob Road traffic signal project.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Parks Crew worked the Parks Celebration on Saturday - setting up and
cleaning up. Tree limbs were removed at Wentworth Park around the foul
line pole. A damaged foul line pole was removed from Valley Park.
Rich jetted the sanitary sewer lines on Mendota Heights Road (Dodd to
Huber Drive), Arbor Court, Arbor Court easement, Mendota Heights Circle,
Westview Terrace, Pond Haven Lane, Bridgeview Court, Brookfield Lane,
Heritage Drive, Concord Way, Bedford Court, Lockwood Drive, Kensington
Park easement and Wilshire Court.
The Street Crew cleaned up downed limbs from Sunday's winds. Catch
basins were cleaned. The street lights were out on Northland Drive after
the contractor, who is installing the traffic signals, broke the conduit and
wires. Patching of potholes was done on Wagon Wheel Trail. John Ambrose
and John Boland helped install countertops in the Police Department.
Engineering
Sue met with Bruce McManus to discuss a potential creek bank stabilization
project on Marie Creek. Sue and Ryan also met with Dakota County SWCO
for funding these types of projects through their community conservation
cost share program.
Sue had a chance to visit both Somerset and Mendakota Country Clubs to
discuss potential projects they have planned.
The contractor working on the Pilot Knob Road/Mendota Heights Road traffic
signal hit underground power lines and telephone lines.
The seal coating in Curley's Addition and Bridgeview Addition was completed
on Tuesday.
Memorial Day
NEWS
LETTER
Public Works
Engineerinq
Code Enforcement
Public Works
he Pipelin
May 25, 2007
The Parks Crew prepared the fields at Kensington Park South for a Lacrosse
tournament. Sprinkler heads were repaired at Mendakota Park on fields one and
three. Trees were planted in the parks to replace ones that had died. The broken
swings at Friendly Hills Park and Rogers Lake Park were repaired. Downed tree
limbs were picked up in the parks after Wednesday afternoon storms.
Rich cut roots at Sunset Lane, South and North Freeway Road, Knob Road,
Winston Court easement, Miriam Street, Simard Avenue, Downing Street, Walsh
Lane and Kay Avenue, Glen Hill Road and Highway 13 at Brompton Place to
Sylvandale. He watered trees in the parks and helped the Parks Crew plant trees.
The Street Crew did street patching in the Avenues, Vandall Street, and Laura
Street. Two holes were patched on the pedway between Overlook and Marie
Avenue. The pothole at Dodd Road and Roundhill Road was filled. A bituminous
berm at 745 Hilltop Road was built to prevent erosion in the yard. Catch basins
were cleaned.
Engineerinq
Sue McDermott, Mike Maczko and Guy Kullander met Tuesday morning at Valley
Park with Excel Energy and their contractor to coordinate restoration efforts along
the recently upgraded power lines in Mendakota Park and Valley Park north to
Highway 13. Turf restoration, grading rutted disturbed areas began Tuesday
afternoon and weather permitting should be completed by mid -June. City staff will
coordinate replacement of severely damaged trail segments (billable to Excel)
through the bituminous contractor hired by the City to repair city trails. Minor trail
edge damage caused by Excel's contractors will also be evaluated by staff and a
'cost -per -foot" value determined, invoiced to Excel and the funds earmarked to
offset costs of a future trail overlay.
Sue and Tom Knuth met with Ross Fefercorn and Dakota County CDA staff to
discuss grading issues at Town Center.
Sue met with Brian Birch to discuss a creek bank stabilization project in his yard.
Sue and Ryan have been working with Dakota County and SWCD on a grant
application to fund the work.
NEp
Sp
�/+�
■M■ /ram ■y■
TT
LEE
■
Public Works
Engineering
May
17, 2007
Code Enforcement
Public Works
The Parks Crew removed downed tree limbs on pedways in Rogers Lake Park and
Hagstrom King Park. Permanent home plates were installed in all the neighborhood
parks. Fields at Mendakota Park were prepared for the Visitation Softball tournament.
Rich finished spraying the dandelions at the Friendly Hills Tot Lot and Curley's Tot Lot. He
trimmed tress at the Culligan lift station in put down wood mulch. He repaired the lawn
on Swan drive in the storm sewer easement by putting in black dirt and grass seed.
The streets crew hauled out sweeping and other debris from city property(approx. 190
cubic yards). Planted trees along Delaware Avenue. Patched blacktop on Medora Ct.,
Clement St. & 1st Avenue. Mailbox repairs were completed with the installation of a
$200.00 mailbox.
John Boland's a Father Again
John and his wife, Lori, had a baby boy on Monday evening. He was 9 Ibs 7 oz. This is
the first boy in the family - they have three girls!! Congratulations!!
City Council authorized installation of high impact polypropylene sports surfacing tiles over
the existing tennis courts at Valley Park. This product allows drainage through and under
the surfacing tiles making the courts usable soon after a rain fall event. The base asphalt
surface may still exhibit cracking but this will not affect the sports tile surfacing that in
effect "floats" on the old court's asphalt surface. Last week fence repairs and addition of a
large access gate to the court were completed.
SKATE PARK IN ROGER'S LAKE PARK
Three new ramps will be added to the skate park suitable for the beginner or novice skate
boarders. Existing Tier One rated skateboard equipment (maximum height is three feet)
does not require "full time supervision" will remain and the new components 7" 12" and
14" high are to be located on the north side of the Skate Park, within the fenced area.
WACHTLER AVE. & IVY HILL PARK TRAIL WORK
Trail repairs, patching and addition of a two inch bituminous overlay will occur on the
Wachtler Ave. trail from Wentworth Ave. to Cherry Hill Rd. and similar work, including an
access trail segment to the recently completed playground reconstruction, will be done in
Ivy Hill Park from Maple Park Dr. to Butler Ave. Other minor trail repairs will also be done
at three locations.
NEWS
LETTER
Public Works
Enoineerina
Code Enforcement
Public Works
The Pipeline
May 11, 2007
Nappy Birthday
Minnesota
149Years
The Parks Crew cleaned up downed limbs in the parks and pedways from the
heavy winds on Sunday. Netting was hung in the batting cage at the Civic Center
ball field. Home plate and matting was also installed at the Civic Center ball field.
Sprinkler heads were repaired at Mendakota Park, City Hall and Kensington Park.
The irrigation timers were replaced at Mendakota Park.
Rich sprayed weeds in Marie Park, Valley Park, Victoria Highlands Park, Wentworth
Park and Hagstrom-King Park. A manhole was sealed in the Ridgewood easement.
There was a large leak in the mahole, 7 g.p.m., which Visu Sewer grouted. Rich
did manhole inspections on Lexington Avenue between Highway 13 and Highway
110 and found six need to be repaired.
The Street Crew cleaned up and cut up downed trees and limbs from Sunday's
winds. More street sweepings were hauled to Solberg's. Two new speed limit
signs were installed north and south of Decorah Lane on Huber Drive. The
concrete bases from the street lights were pulled out on Mendota Heights Road
and Pilot Knob Road to make room for the new traffic lights. Pothole patching was
done on Sylvandale Road to Maple Park Drive. Brush was cut that was obscuring
signs on Victoria Road. Trees were planted in the boulevard on Delaware Avenue.
Enaineerin4
Graduate students from the University of Texas were in town on Friday doing laser
video testing on our plastic storm sewer pipe at Town Center. They are doing a
study on the performance of plastic (HDPE) pipe throughout the country. The
study is sponsored by the American Concrete Pipe Association.
The Engineering Department opened bids for the Kipp Addition improvements and
the Lilydale Water Main Extension. G.L. Contracting, Inc. was the low bidder on
both projects.
Attachments:
Pilot Knob & Mendota Heights Construction Update from Dakota County
NURT Trail Project Schedule and Planner
0
O
N
09
W
Z
Z
Q
J
CL
W
J
W
N
WS W
El
N P
m
^
N N
M
N
P
;
N
m
�2
N
o
m
O
N
yl
N
O.
N
ro
N
m
O
n
N M
N M
W
h
N P
N N
N N
To
>
W
n
N
N
N
N
W
N
O
n
4
m
N
O
m O
N
P
N m
J
N N
o
m
O H
N
11
�
W
N
N M
a0
n
M
ry
q
q
w
LyJ
Q
r
o
O
O
t7
O
O
M
O
O
l�l
O
O
O
O
O
O
O
O
O
ry
O
o 0
N
O O
N
y
IL
Q
�7
L
N
°
°
0
y
3
Q
LU
c0
�
O
Z
Q
ina
O
C
:E<
U
N
Q
E
Q
N
O.
O
U
o
U
a
<
`
Et
E
U
N
a`
0)
0
?
C
a
O
°
_
M
C
V
m
20
Q
-°
'm
0)o
° m
iL
W
h
N
N
IV
LL
n
O
W
N
N
Z
m
O
n
N
m
N m
m
O
n
N
N
N
Q Q
W
N
N
9 O
n
V
N m
W
h
N P
N N
n n
0 0
n
0
n n
o
n
O
p0p
N M
O
O Cl!
n h
O O
m
O
m P
O• O
O
n n n n l
0 0 0 0
N M t7 O
0 0 0 0
6
'o
a
a
°
v
m
a
u
�
O
�
E >Q
O
U a
a
°
C
G
v
0
0
o U
2
U
8
-2
$
0
N`
n I
0
O
n
0
N
O
Bids were received on November
21, 2006, for road and signal
work on Pilot Knob Road
(CSAH 31) and Mendota
Heights Road. The County
Board awarded the project to
Polyphase Electric Company.
What's Being Done?
Construction will take place at
the intersection of Pilot Knob
Road and Mendota Heights
Road.
The project includes installing a
new traffic signal system,
lengthening an existing turn lane,
and minor roadway
improvements. The purpose of
the project is to alleviate
congestion and provide optimum
safety.
Pilot Knob Road
(CSAH 31)
Mendota
Heights Road
Construction
Update
May 3, 2007
What Should I Expect?
Some of the private utility work
has already begun. The concrete
signal bases at all four corners of
the intersection have already
been placed.
The contractor is currently
working on installing the
electrical wiring in preparation
for the signal poles.
On May 14 the contractor will
begin working in the median on
Pilot Knob Road north of the
intersection. The left turn lane
will be lengthened. Traffic
delays will occur for about a
week while this work is
occurring.
Signal loops will be installed in
the pavement and some curb
work will be completed at each
corner of the intersection. We
anticipate a few week period
when no work will be completed
as we await delivery of the signal
mast arms. Traffic delays will
not occur during this time. As
always, the construction
schedule may vary due to
weather.
Traffic
Both Pilot Knob Road and
Mendota Heights Road will
remain open during construction.
There will be times when traffic
lanes are constricted. While the
contractor is performing some of
the work, you may encounter a
short delay. For the safety of
both the construction workers
and motorists, we ask for your
patience.
When will Work be
Complete?
The contractor is required to
have all work completed by
August 17.
More Information
This construction update is being
delivered to residents/businesses
in the vicinity of the
construction. If you have
questions or would like
additional information, please
call. For additional project
updates, visit the following
website:
htto://w.dakotacounty.us/EnvironmentRoads/
RoadConstruction/Current
PROJECT INSPECTOR
David Thao
952-891-7917
DAKOTA COUNTY EMPIRE
TRANSPORTATION
OFFICE
952-891-7900
M-F 7:00 — 3:30
Public Works
The Parks Crew finished working at the Civic Center ball field by leveling out
the rec rock. The irrigation system was started up at Kensington and
Mendakota Parks and repairs were made as needed. The Lacrosse field was set
up at Kensington Park. The field at Mendakota Park was striped for the youth
lacrosse team. The volleyball net was installed at Rogers Lake Park.
Rich sprayed for broadleaf weeds at City Hall, Mendakota Park, Rogers Lake
Park, the Fire Hall, Friendly Hills Park and Kensington Parks North and South.
He did a sanitary sewer and storm sewer inspection on Centre Pointe Blvd. He
cleaned out the sump pit at the Public Works Garage.
The Street Crew continues to make mail box repairs. Street sweepings were
hauled to Soulbergs Aggregate in Rosemount. Graffiti was removed from stop
signs on Victoria and Marie, and Victoria and Caren. The new truck was
brought to ]-Craft to be outfitted for the dump body, hydraulics and other
equipment.
Enciineering
The driveway at 2400 Pilot Knob Road (slope remediation project) was paved
on Tuesday. Landscaping will be completed by the end of May.
Ryan and Sam completed the second round of water quality monitoring on
LeMay Lake.
Sue met with WSB & Associates regarding the status of the Mendota Heights
Road traffic study. The report will be complete in a few weeks.
The first two signal bases at Pilot Knob Road and Mendota Heights Road were
poured today. The conduit has been installed on the base locations.
The crack sealing in the Kingsley neighborhood was completed on Monday.
NEWS
LETTER
Public Works
Enciineerina
Code Enforcement
Public Works
The Pipelin
April 27, 2007
The Parks Crew dragged, striped and chalked ball fields. They worked the softball
tournament for Sibley girl's fast pitch. The batting cage was repaired at Mendakota
Park. Crab grass prevention was put down in the parks. The irrigation system was
worked on at the Civic Center. Downed trees and brush from Pilot Knob Road was
chipped up.
Rich did sewer inspections on Waters Drive. Sump manholes (which collects debris)
were vacuumed on Haverton Road, Caren Road, Mayfield Heights Road, Emerson
Avenue and Lake Drive. Pipe Services vacuumed catch basins on Stockbridge Road,
Whitfield Drive, and Mendakota Court. They were blocked with leaves, sticks and
trash.
Sweeping of the streets was done in record time this year - three days. That's
because sand was not used this winter. Sue, Tom, and Dave attended the APWA
North American snow conference. Everything from staff, plowing, de-icing, and safety
was discussed. One interesting thing was learned - Fort Collins, Colorado does not
plow residential streets until there is eight inches of snow or more. The reason being
is the median temperature during the winter is 420 in the winter and in the summer
it's 850. The Street Crew assisted the Parks Crew with cleaning up debris in the parks.
Street lights that were out in the industrial park were worked on.
En4ineerina
There was work done at the JES slope remediation project this week. Curb and gutter
was poured for the driveway replacement and the grading was finished for the slope.
On Thursday, Sam and Ryan braved the treacherous water of LeMay Lake (in Sue's
canoe) to obtain a water quality sample for the Metropolitan Council's lake monitoring
program. Samples will be collected through October to measure levels of phosphorus,
nitrogen and chlorophyll -a (which is an indicator of algae). So for the water is clear
and no pirates were encountered!
Grandpas
Guy Kullander became a grandpa for the first time on Tuesday, April 24th at 6:00 A.M.
His oldest daughter Christine and husband Kyle had a baby boy, 20" long and 8 Ibs 10
oz, whom they named Kaden Alexander David.
Tom Olund became a grandpa for the second time this week. His son Jeff and wife
Sheila had a baby boy named Jaylen. He was born at 9:05 A.M. on Thursday, April
26th. He weighed 8 Ibs, 1 oz and was 20 inches long.
The Pipelinevv 1�
LETTER oPy
Public Works /
Enaineering
Code Enforcement April 20, 2006
Public Works
The Parks Crew set up Mendakota Park for summer use. The bases were installed,
foul lines were striped, fields were dragged and new netting was hung over the
batting cage. The cement was cleaned at Mendakota Park around the concession
building. The fence was removed from the Civic Center ball field and hauled away.
Safety netting was hung over the hub area where spectators watch the games at
Mendakota Park. Overhead backstop safety netting was hung at the Civic Center
ball field to prevent foul balls from landing on Victoria Curve.
Rich put rip rap along a manhole next to Valley Creek. The creek was eroding the
soil along the manhole. He scraped grease off the wall at the Mendota Heights
Road lift station. Rich also helped the Parks Crew remove the fence at the Civic
Center ball field. He cleaned the shop floor drains.
Street sweeping began on Wednesday at 6:00 A.M. The contractor brought in six
machines. The Street Crew did some mail box repairs. George helped the Parks
Crew with the bobcat to take down the fence at the Civic Center ball field. Wings
and sanders were removed from #303 and #312. (Hopefully they won't be
needed anymore). A stop sign was reinstalled at east Northland Drive and
Mendota Heights Road that was hit this winter.
Enaineering
Ryan attended the first meeting of the MN Cities Storm Water Coalition in
Monticello. The group was formed to assist cities with NPDES requirements.
Veit has resumed work on the slope remediation project at 2400 Pilot Knob Road.
Curb and gutter will be installed on Monday.
Civic Center Field
Public Works (Terry Blum, Parks Leadsperson, Rich Burrows, Utility Leadsperson,
and George Noack, Streets) on Monday and part of Tuesday removed the old ball
field fence and posts. Excavation began on Tuesday afternoon and completed
Wednesday morning followed by installation of the fifteen foot wide rec-rock
warning track that was completed on Friday morning. The fence contractor plans
to be begin work early next week. Weather permitting, batting cages will be
completed, including interior safety netting prior to May 1st. The first game of the
season was played late Tuesday afternoon even as excavation / turf removal was
ongoing in the (deep) outfield.
N E W S -�� The Pipelin
LETTER
Public Works
Enaineering April 6, 2007
Code Enforcement
Public Works
The Parks Crew picked up a downed tree at Marie Park and chipped it up. Burned
out light bulbs were replaced on the buildings at Mendakota and Kensington Parks.
Water meters were installed in the buildings at Mendakota and Kensington Parks.
Steel track barrels were picked up for the parks. Unit #506's broom was changed
out for next season and put in the water tower for summer storage.
Rich cut roots in the sanitary sewer line on Caren Road, the Caren Road easement
down to Highway 13. Grease was cleaned off the floats at the Veronica lift station.
The Street Crew cleaned catch basins. Handicap parking signs were replaced in
Town Center as they did not meet state requirements. A stop sign and street
name sign was removed after being hit be a vehicle at Sutton Lane and Marie
Avenue. A bad spinner motor on sander #303 was repaired.
Snow Events of the Week:
Date: Amount: Response:
April 3, 2007 Dusting Sand main lines with a 2:30 A.M. start
Enaineerina
St. Paul Water Regional Services has begun replacing hydrants in Ivy Falls for the
street reconstruction project.
Tom met with Tim Hanson and a representative from Xcel Energy regarding the
power lines for the Dodd Road trail.
Dakota County has included Lexington Avenue from TH 110 to TH 13 to their
overlay projects to be completed this summer.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
March 30 2007 ` o'
The Parks Crew took more trash barrels to the parks where needed. They
finished sweeping the pedways. Tennis court nets were put up in the
neighborhood parks and leaves were cleaned out from inside the courts. A
new dog leash sign was installed at Mendakota Park. A broken bench and
picnic table was repaired at Mendakota Court. A part for #504 mower was
installed and John Ambrose welded it on the arm to the mower deck.
Equipment was worked on preparing it for summer.
Rich applied root killer on Vandall Street and Dodd Road between Third and
Fourth Avenues. Roots were cut on William Court. A homeowner's service
was cut off that was 2' in our manhole and the service was redirected with a
4" pvc pipe in the Dodd Road easement.
The Street Crew cleaned storm grates. Marker posts were pulled out for
problem catch basins due to the rapid melting. A broken barricade was
pulled out at the end of Veronica Lane. A broken curb box for a catch basin
on Medora and Emerson Avenue was worked on.
Engineering
St. Paul Regional Water Services repaired a broken water main on Maple
Park Drive.
Tom, Sue and Guy met with Tim Hanson of WSB & Associates. Tim is
finishing up the design for the trail connections on Dodd Road and Sibley
Memorial Highway.
Informational letters were sent to residents on Woodridge Drive, Arcadia
Drive, Maple Park Court, Falls View Court, Cascade Lane, Maple Park Drive
and Sylvandale Road. This meeting is for the proposed street
improvements and is Wednesday, April 11 at 6:00 P.M. in the City Council
Chambers.
N E W S The Pipeline
LETTER
Public Works
Enaineerinq March 23, 2007
code Enforcement
Public Works
The Parks crew attended the Sherwin Williams seminar at the Minneapolis
convention center. Summer equipment was brought down from storage at the
water tower and winter equipment was stored for the summer. Trash was
collected from parks and sweeping has started on the pedways.
The Streets crew continued patching potholes. Debris was removed from Ivy Falls
Creek between Dodd Rd and Laura Ct. Made brackets and put up temporary cross
walk signs on Mendota Heights Rd near St. Thomas academy. Removed tree on
Pilot Knob Rd and Mendota Heights Rd.
Rich checked sanitary sewer lift stations daily. Rich and George cut roots in the
sewer main using the jet truck on Callahan PI, Hingham Cir, Chippewa Ave,
Annapolis St and Highway 13 (Fremont Ave to Garden St and Brompton PI to
Sylvandale Rd).
Enaineerinq
Guy and Sue met with Curt Chatfield from Dakota County regarding the 30-year
county park vision. Draft maps of the areas discussed will be sent to the city in
the near future.
Bids for the city wide street sweeping were received and prices increased by one
dollar an hour. Sweeping should commence within the next couple of weeks.
Tom has been able to begin a more detailed inspection of the Copperfield project
area now that most of the snow and ice has melted.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
HapPaitrldts
Y March 16, 2007
St. Dav
The Parks Crew repaired the mirrors on truck 502. Picnic tables were repaired and
stained. Trucks were serviced, washed and cleaned up. They went to Gerlack
Services in Hastings for seminars on new mower products and additions to the
older equipment.
Rich unplugged storm sewers on Kressin Avenue, Stockbridge Road, Mendakota
Drive, Fourth Avenue, and Copperfield. Most of the storm sewers were blocked by
leaves and Rich used the jet to clear them. The power went out on Wednesday at
10:45 P.M. at the Lilydale lift station, the power was out until 12:15 A.M. He cut
roots in the sanitary sewer line on Pontiac Place and Valley Curve. He checked the
sanitary sewer line down stream of the Mendakota Golf Course — there was some
grease but mostly looked good.
The Street Crew put up flashers on Lake Drive and Dodd Road. St. Paul Regional
Water Services was called because behind the water main break the street is
settling. Potholes were filled with cold mix. A plugged storm grate was opened
that caused water to pond on the street on Stockbridge Road.
Enaineerina
Sue attended a meeting for the Robert Street Corridor Technical Advisory
Committee.
The north ditch of State Highway 110 flooded and was nearing the traffic lanes.
MN/DOT called in emergency locates to re -grade the ditch. It was determined that
work by MN/DOT last summer covered the outlet which in turn caused the
drainage problem.
The city's seal coat project has been scaled back due to the high bids received. It
was determined that the prices submitted are the best available this season.
Plans are being finalized for the Copperfield mill and overlay project and design
has started for the Ivy Falls neighborhood reconstruction.
Plans have also begun on redesigning the storm water outlet at State Highway 13
and Wachtler Road.
There is a public hearing for the Kipp Addition at Tuesday's City Council meeting.
L E T T'E R The Pipeline
Public Works
Engineering
C >.T March 9, 2007
Public Works
The Street Crew plowed the cul-de-sacs, parking lots and pedways. The
cutting edge on truck 501 was replaced. A broken hose was repaired on the
ground master with the broom. The flooding hoses and fittings were picked
up from the warming houses and brought back to the shop. They attended
the Tessman Turf Academy at Edinburgh golf course in Brooklyn Park. The
academy was an intro to new turf products and new chemicals for 2007.
The alarm went off at the Lilydale lift station due to a power outage on
Sunday, March 4th. A MnDOT plow hit a power pole on Highway 13. Rich
checked the manholes in the Copperfield area to look for deteriorating
manholes. He cut tree roots in the sanitary sewer line on Vandall and
Brookside Lanes.
The Street Crew cleaned up after last week's storm. Mailbox repairs were
done, and snow was removed from troubled catch basins. Snow was
pushed from the street lights that will come down next week to make room
for the new traffic signals at Mendota Heights Road and Pilot Knob Road.
Engineering
Sue met with both St. Thomas Academy and Visitation regarding traffic
concerns on Mendota Heights Road.
Sue attended a )PA meeting regarding bids for the 2007 seal coating. The
bids for this project were 30% above estimated costs and bids may possibly
be rejected.
Workers complained of a sewer gas smell at a new home on Wesley Lane.
Workers have been using water and the bathrooms however, no records can
be found of the house being connected to the city sanitary sewer nor is
there a visible patch over the sewer main. The problem was referred back
to the contractor and workers were advised not to use the home's facilities.
NEWS LETTER he Pipelin
Public Works
Engineering
Code Enforcement March 2, 2007
Public Works
Public Works had a busy week this week with all the snow. They came in on Saturday,
February 24, at 10:00 A.M. and stayed until 1:00 P.M. Sunday, February 25. With this
week's second storm they came in at 7:00 A.M. Thursday, March 1, and stayed through
the night trying to keep up with falling snow. A resident dropped off a couple of pies and
ice cream on Thursday evening for the guys.
One of the axels on truck 303 shifted and had to be brought to Kremer Springs. A
serpentine belt and wing broke on truck 304. See the email from a happy resident about
the snow plowing.
Snow Events of the Week:
Day: Amount: Response:
Saturday/Sunday 101, Plow all streets
Thursday/Friday 9" Plow all streets
Engineering
The ice rinks were closed on February 28, 2007.
Tom Knuth attended a seminar on reclaiming bituminous pavement.
SEH demonstrated their web based MS4 tracking program for Ryan and Sue which will
help with our NPDES permit.
From: Dave Vierling[mailto:DVierling@bixproduce.com]
Sent: Friday, March 02, 2007 9:50 AM
To: Sue McDermott
Subject: snow removal
Dear Sue,
My name is Dave Vierling and I live at 2550 Whitfield Drive. I am writing to express my appreciation for the
wonderful job your folks are doing plowing our street.
The semi cul-de-sac I live on has very few places for the plowed snow to go. It would be very easy for the
Snowplow Driver to dump a huge amount of snow on our entrance and force us to spend hours digging out. The
Snowplow Guys do a great job of putting this snow in a place where nobody gets socked. I know this takes extra
time, but I certainly appreciate it.
Thanks again.
dv
L E T T/E R The Pipeline
Public Works*
Engineering February 23, 2007 0*0
Code Enforcement *a
Public Works
The Parks Crew continues to flood the ice rinks. The rinks are swept and
broomed daily. They also are working on repairing picnic tables. The
hockey goals at the Marie rink were repaired.
Rich checked the sanitary sewer line on Kressin Avenue downstream on
Bluebill to Lake and it looked good. A homeowner on Kressin called and
said their service was blocked. The homeowner also said Rooter Rooter had
pushed a small slipper into the City's line. There were no sign of the
slipper. Pipe Services cleaned and vacuumed the storm sewer and catch
basins on Victoria. They were packed with ice and leaves. Rich assisted
Len with replacing the radiator hoses, thermostat, and motor belts on the
portable generator for the lift stations.
The Street Crew picked up a dead deer on Delaware Avenue, and Marie
Avenue by 35E. Pot holes were filled with cold mix. Ice was scraped off
Victoria Avenue and hauled away. Callahan Place was sanded for runoff
water that froze. They are getting the trucks ready for this weekend's
storm.
Enaineerina
The Copperfield mill and overlay project was unanimously approved to
proceed with construction plans. The biggest concern of residents from the
public hearing was the speed and amount of crosswalks on Huber Drive.
The Council also approved the go ahead to advertise a public hearing for the
Kipp Addition.
Lots of robins have been spotted around City Hall eating last year's crap
apples.
NEWS he
LETTER
Public Works �►u „
Engineering
Code Enforcement;_r�';
Public Works
Pipeline
1
February 16, 2007 J `'
The Parks Crew checked the ice rinks and warming houses daily. Snow was
broomed and blown from the rinks. They were flooded, as needed. Parts
on plow 503 were replaced, as needed.
Rich changed the condensation heater at the Centre Pointe lift station. He
finished his record keeping for sanitary sewer cleaning in 2006, this included
filling out utility maintenance cards for each street or easement line
cleaned.
The Street Crew put down salt on Mendakota Drive where there was a water
main break. The Mendakota Park parking lot was salted because it was
used as a detour. Trash was picked up in the Bunker Hills neighborhood
where someone had dumped it. Salt was put down on Victoria Road where
ice had formed across from the County Day School. Cold mix was put in the
hole from the water main break on Dodd Road and Lake Drive.
Engineering
There was a water main break on Sunday at Mendakota Drive. Traffic had
to be detoured through the parking lot at Mendakota Park. St. Paul
Regional Water was working on fixing the damages.
A neighborhood meeting was held on Thursday to discuss the Copperfield
street rehabilitation project. 12 residents were in attendance.
Time Warner Telecommunication is completing a directional bore for high
speed internet on Pilot Knob Road between Pilot Knob Road and Executive
Drive.
NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Parks Crew continues to flood the rinks. The rinks are also broomed and kept
clear of snow. They plowed the pedways Tuesday after the snowfall.
Rich scrapped grease off the walls at the Mendota Heights Road lift station.
Grease was scrapped off the floats at the Veronica lift station. He ran the standby
generator at Mendota Heights Road #1 lift.
The Street Crew made temporary mailbox stands. Stop signs, yield signs and
speed limit signs were refaced.
Snow Events for the Week:
Date: Event: Response:
2-6-07 1.5" fluffy snow salt/plow
Engineering
Thursday night there was a water main break at Overlook Road and Lexington
Avenue.
WSB & Associates started surveying for the trail projects on Dodd Road and Sibley
Memorial Highway.
Jim, Jake, Sandra and Sue attended the Transportation Forum at Southview
Country Club on Thursday. Chairs of both the state senate and house
transportation committees (Senator Murphy and Representative Lieder) spoke
about upcoming legislation regarding a 10� gas tax and 0.5% sales tax increase.
Funding is needed for high priority state highway construction projects.
Approximately 30 city and county officials and staff were in attendance.
Engineering is holding an informational meeting on Thursday, February 15th at
6:30 P.M. regarding the Copperfield rehabilitation work.
NEWS
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
The Pipeline
February 2, 2007 4W
The Parks Crew continued to flood skating and hockey rinks. The rinks were also
broomed and snow was blown off as needed. A repair was made on an electrical
breaker in the warming house at Friendly Hills.
Rich jetted the storm sewer on Lake Drive after the water main break on Tuesday.
Our jet got stuck (pipe was full of rocks, gravel and mud). South St. Paul came
with their vac and jet and helped get our truck out. He checked out the sanitary
sewer line on Delaware Avenue where 1153 had service troubles in the main line.
i ne street crew
continue to make Snow Events of the Week:
mail box repairs.
The Street Crew Day. Event: Response:
was called in for
the water main 1-29-07 Dusting Sand streets
break to barricade the road and clean up. Temporary street name signs were put
up (they were run over) at Lakeview and LeMay Lake Road.
Enaineerina
There was a water main break on Tuesday, January 30th at Dodd Road and
Lakeview Avenue. Kare 11 News did a short blurb on the water main break on
their 5:00 news.
Sue and Ryan are attending the Annual Meeting of the City Engineers Association
of Minnesota. The conference is put on by the University of Minnesota.
Attendance at the conference will give them continuing education credits.
Pictures of the
water main break
NEWS
LETTER
Public Works
Enaineerinci
Code Enforcement
Public Works
The Pipeli-9-e
January 25, 2007
The Parks Crew checked the ice rinks and warming houses daily. The hockey and
general rinks were flooded, broomed and cleaned of snow. The pedways and
parking lots were plowed. Snow was removed from around the retaining walls in
the industrial park area where the pedways are located between the street and the
retaining wall.
Rich cut tree roots on Highway 13 (Brompton to Sylvandale) and on Dodd Road
(Mager Court to Marie Avenue). He looked at the video tapes of 14 miles of
televised sanitary sewer pipe from Northland Drive. Rich looked for bad spots and
many spots need repair. Pipe Services televised the line last fall.
The Street Crew did mailbox repairs. Truck #303 was brought to Kramer Spring
for broken rear springs on both sides of the truck. A breaker for the Bobcat was
rented and the old footings from the LP tank were broken up. A street sign was
made for Main Street and replaced (fourth time the sign had to be replaced).
Snow Events of the Week
Date: Event: Response:
1-21-07 Dusting Scrape main line and sand rest of streets - 12:30 PM. start
Engineering
Our 2007 MSA construction allotment is $290,503.00. Portions of this allotment
will be used to fund the Huber Drive overlay and the Pilot Knob Road/Mendota
Heights Road traffic signal.
A survey was sent to the Woodridge Drive residents regarding the type of curb and
gutter residents preferred. Out of 20 possible respondents, 18 residents sent back
the survey. The results are: 12 for surmountable curb and gutter, 4 for B618
curb & gutter, 3 residents want no curb and gutter and one resident didn't care
what type of curb and gutter was used.
See attached article regarding Mendota Heights' first snow emergency.
Snow, but no emergency
Page 1 of 2
Posted on Tue, Jan. 16, 2007
Snow, but no emergency
Public works officials in St. Paul and Minneapolis sized up Sunday night's storm and opted not to declare
snow emergencies. But even on a holiday, the plows rolled.
BY NANCY YANG and EMILY GURNON
Pioneer Press
Neither St. Paul nor Minneapolis declared a snow emergency Monday, but that didn't mean plow drivers stayed home on
the Rev. Dr. Martin Luther King Jr. holiday.
Crews were out plowing, sanding and salting the roads to combat the 3 to 5 inches of snow that fell Sunday night and
Monday morning.
Public works officials also battled the misconception that if there's no snow emergency, there's no plowing.
"Nothing could be further from the truth," said Mike Kennedy, director of winter operations for the Minneapolis Public
Works Department.
Crews are on the road, doing back-to-back 12-hour shifts, plowing and sanding, he said. St. Paul crews got started at
midnight Sunday.
"We had about 28 equipment pieces out and then followed that up with an additional 14 at 8:30 a.m.," said St. Paul
public works supervisor Jeff Sanchez.
He said plows finished clearing and sanding 90 percent of primary streets by 4:30 p.m. About 25 plows continued the
work Monday night.
Some cities, such as Mendota Heights and West St. Paul, declared snow emergencies. So why didn't St. Paul or
Minneapolis?
The big cities try to coordinate with one another to minimize confusion, Kennedy said. So it's likely that if one sounds the
alarm, the other will, too.
One big factor is the amount of snow. Generally, Minneapolis declares an emergency if the accumulation is 4 inches or
more. If it's 5 inches, "it's a no-brainer," Kennedy said.
But in the 3- to 5-inch range, public works officials also look at other weather conditions, such as current and predicted
temperatures.
Officials also look at the time, intensity and duration of snowstorms, as well as how consistent conditions are around the
cities. Kennedy said Monday being a holiday did not play into the decision about whether to declare an emergency.
While 4.2 inches of snow was officially recorded at the Twin Cities airport, storm totals increased to the south and
decreased to the north. Farmington reported 6 inches, Lakeville got 6.7 and Burnsville saw 8. St. lames, in southwestern
Minnesota, also recorded 8 inches. But the north metro communities of Andover, Forest Lake and Maple Grove saw less
than 2 inches.
The snow made for a messy morning commute in the Twin Cities, with dozens of spinouts and minor crashes reported by
7 a.m.
Nancy Yang can be reached at nyang@pioneerpress.com or 651-228-5480. Emily Gurnon can be reached at
egurnon@pioneer press.com or 612-338-6516.
htip://www.twincities.com/mld/twincities/news/local/I 6468808.htm?temp1ate=comcntMo... 1 / 19/2007
NEWS
LETTER
Public Works
Enaineerina
Code Enforcement
Public Works
e Pipeline
January 18, 2007 To
The Parks Crew checked all the warming house rinks and opened them for the
skating season. Flooding of all rinks is now being done. Monday they plowed cul-
de-sacs, parking lots, hockey rinks, general rinks and all pedways. Equipment
maintenance work was done on the new 510 tractor. Wire and an add switch for
the water sprayer attachment for dust control was installed for use when dragging
all fields.
Rich and Tom Olund attended their annual sanitary sewer operator's school held at
the Thunderbird in Bloomington. They need to attend this school every year in
order to keep their operator's license current.
The Street Crew did mailbox repairs. The cutting edge on plow #312 was
changed. The bridge decks were cleared of snow.
Snow Events of the Week:
Date: Amount: Response:
1-15-07 6" A snow emergency was declared by Public Works.
Plowing of all streets started at 2:00 A.M.
Personnel News
Tom Olund became a grandpa for the first time on Wednesday, January loth He
is the proud grandpa of a baby girl!! She was born at 9:20 A.M., weighed 7 Ibs 10
ounces and was 21 inches long. Her name is Alyssa May and was born to his
youngest son Jim and his wife Joanna.
Ice Rinks
Friendly Hills Park skating rinks opened on Saturday, all other rinks re -opened on
Monday. Terry reported that the rinks were heavily used on Monday even with
some rough ice conditions. Now that the cold weather is here, the Parks Crew
plan to flood the rinks everyday and part-time rink attendants are flooding at night
to help build an additional base. Warming house hours are: Weekdays 4:00 to
8:30 PM, Saturday 9:00 AM to 8:30 PM and Sunday noon to 8:30 P.M. The ice
rink/warming house hotline is 651-255-1174 and the ice skating lesson
information line is 651-255-1173.