2003NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks. They
also completed the following
other tasks this week:
• They picked up trash from
the warming houses and
checked them
• They flooded the rinks
• They repaired the shovels
at the Friendly Hills ice rink
by installing new handles
• They plowed the pedways
• They cleared snow from
the ice rinks with the snow
blower
• They placed cell phones in
the warming houses for the
rink attendants
• They plowed out the shop
parking lot and shoveled
the sidewalk to the shop
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He placed fill in and
around manholes on Lakeview
Avenue and Furlong Avenue
with class 5 gravel that were
hit by the plow. This will be
permanently fixed in the
spring.
Rich also plowed the lift station
driveways and put a new vent
on the lift station at Northland
Drive. The old one was hit by
a car sliding off the road.
The Pipeline
December 19, 2003
Street Report
The Street Department accom-
plished the following tasks this
week:
• Mixed salt and sand
• Filled salt storage bin
• Did some mailbox repairs
from the plows hitting the
mailboxes
• Made up and installed street
name signs at Douglas
Road, James Road, Mendota
Heights Road and Lexington
Avenue
• Removed plow and dumped
sand out of truck #304 to
take to Kramer spring to fix
a broken right rear spring
TV cables from their overhead
power lines on the east side of
Oak Street at Market Street to
connections within the newly
installed buried cable lines at
that location.
Somerset Area Street Re-
construction
Warmer weather towards the
end of the week afforded the
Engineering Department a
chance to gather some more
survey data in the Somerset
neighborhood. The Engineering
Department has completed
roughly 80% of the field survey
work in spite of being ham-
pered by the cold and snowy
weather that we have been get-
ting recently.
Snow Events of the Week
Date: Event: Response:
12-16-03 1" Scrape streets —all areas
12-18-03 1" Scrape streets —all areas
Town Center Proiect
Xcel Energy and Comcast con-
tinues to make progress on the
task of installing the new buried
power lines in the Town Center
development. Construction
crews of Xcel Energy and Com-
cast concentrated on routing
the respective existing over-
head electric power and cable
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks.
They also completed the fol-
lowing tasks this week:
• Checked out the warming
house furnaces
• Checked on the shovels at
the warming houses
• Replaced the cutting edge
on plow #503
• Washed and waxed the
trucks
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He also did a sanitary
sewer repair inspection on
Apache where the tree roots
had broken the line at the
joint.
The lift station at Lilydale
was cleaned by pipe services.
Electro Watchman repaired
alarm systems at the main
lift.
Street Department
The Street Crew accom-
plished the following tasks
this week:
• Replaced burnt out bulbs
in traffic signal heads at
Mendota Heights Road
and 55 on the northwest
corner and center me-
dian.
The Pipeline
• They had to call MnDOT
electrical Services for the
"Do Not Walk" center me-
dian which will not light
• Pushed and cleaned up the
dump site
• Mixed up salt and sand
• Cleaned bridge decks and
sidewalks
• Replaced some old Crime
Watch signs
• Got saws and equipment
ready for trimming trees
Wagon Wheel Trail Culvert
Crossing
Park Construction Company
cut an opening in the floating
silt curtain in the open water
area of Rogers Lake on each
side of the culvert. This per-
mits the fish a passage way to
travel between
the north and
south portions of
the lake.
NPDES Phase II
Permit
The Engineering
Department
placed a notifica-
tion in the Decem-
ber 7, 2003 edi-
tion of the South-
West Review to
notify the public
of the January
6th, 2004 presen-
tation at the City
Council meeting
to comply with the
provisions of
December 4, 2003
the Minnesota Pollution Con-
trol Agency Permit for Storm
Water Discharges under the
Federal Clean Water Act. This
presentation will provide an
overview of the six minimum
required control measures
and a status report on the
measurable goals identified in
the Mendota Heights Storm
Water Pollution Prevention
Program (SWPPP).
Town Center
The manufactured temporary
bank building was delivered to
the Town Center project. The
utility companies continue
with the installation of power
and other utility services to
the site.
Temporary Gateway Bank building at Town Center
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks.
They completed the follow-
ing other tasks this week:
• Set up the aerator at
Rogers Lake for the win-
ter
Finished fertilizing
throughout parks
Prepped and leveled the
general ice skating rink
for flooding at Friendly
Hills Park
Plowed the cul-de-sacs,
pedways and parking
lots
Street Report
The Street Crew fabricated
warning signs for the back
of the dump truck warning
"Stay back 75 feet".
The Crews started plowing
at 2:00 A.M. on Monday
and had one breakdown on
truck #308 where the
- D -
November 26, 2003
Snow Events of Week:
Date:
Amount: Response:
11-23-03
slush/snow sanded and scraped all main lines
sanded rest of streets
11-24-03
4" plowed snow in all areas
11-25-03
scrape streets and sand as needed
mounting bolt was sheared
off the front plow. The re-
pair was made and truck
#308 went back out.
Utility Report
Rich checked the City's
seven sanitary sewer lift sta-
tions daily. He plowed and
sanded the north end streets
(his normal route). Then he
plowed all his lift station
driveways and parking lots
when he was done.
There was a power outage at
the Mendota Heights Road
liftstation #1 Thursday eve-
ning. John Boland re-
sponded to the power out-
age call. The emergency
generator did not start. An
electrician from Total Con-
struction was able to get the
system up and running after
checking out the wiring and
transfer switch.
Rich jointly inspected the
sanitary sewers with Impe-
rial Developers throughout
the Hidden Creek develop-
ment.
Wagon Wheel Trail Cul-
vert Crossing
Park Construction Company
is approaching substantial
completion on the Wagon
Wheel Trail Culvert Crossing
Project. Park Construction
has installed the 45" x 73"
concrete arch culvert (60"
equivalent round pipe).
They were in the process of
backfilling and compacting
the roadway section with
Class 5 aggregate on
Wednesday. It won't be
long and the roadway will be
open for through traffic on a
temporary cold mix asphalt
driving surface.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks. They
also completed the following
other tasks this week:
• Checked over the warming
houses and got them ready
for winter
• Painted the warming
houses where needed
• Locked up the gates to all
tennis courts
• Fertilized the parks
• Repaired hockey boards at
Friendly Hills, Wentworth
and Marie Avenue Parks
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He also put up hydrants
flags at Town Center and Free-
way Road area.
He jetted Lloyds Meats to the
Mendota Heights Road lift sta-
tion due to the buildup of
heavy grease from Lloyds. He
also, jetted South Freeway
Road (tree roots).
Street Department
The Street Crew accomplished
the following tasks this weeks:
• Finished installing street
name signs at Town Center
and Freeway Road addition
The Pipeline
November 20, 2003
• Graded Dodge Lane, the al-
ley on Hiawatha Avenue and
added class 5 to the cul-de-
sac at the end of Pilot Knob
Road and leveled it off
• Pulled out asphalt hot box
on truck #312 and mounted
snow removal equipment on
the truck
• Put in snow plowing mark-
ers posts for Town Center
Code Enforcement Report
Paul issued a building permit
this week to Rongitch Construc-
tion for 2180 Lexington Avenue
to demolish the house and
foundation in Nater Estates.
Rogers Lake
This week Park Construction,
the Wagon Wheel Trail/Rogers
Lake project contractor, com-
pleted the piling and poured the
concrete pile cap.
Somerset Neighborhood
Marc Mogan, Tom Knuth, and
John Tran have been out in the
Somerset neighborhood locat-
ing property irons, control
points and other existing sur-
vey data for the street project
for 2004.
Marc and Rich video taped the
existing streets, driveways and
landscaping features on
Wednesday of this week.
Engineerinq Conference
On Thursday and Friday Marc
and Jim attended a conference
in Brooklyn Center to earn con-
tinuing education credits to
maintain their engineering li-
censes.
Weather forecasters are
predicting our first
measurable amount of
snow for this weekend.
Last year we did our
first sanding of streets
on December 2, 2002,
after a dusting of snow.
In 2001, we plowed a 3
inch snowfall on
November 27th.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks.
They performed service
maintenance on the small
engines. They have begun
gearing up for winter work by
attaching plows to their
trucks for winter snow plow-
ing (they do the cul-de-sacs,
trails and parking lots).
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily.
Street Report
The Street Crew disposed of
ashes and debris remaining
from the Halloween bonfire
at the Mendota Plaza. They
brought seasonal equipment
to the water tower for winter
storage.
A 3M service representative
has been out to the shop,
and gave the guys some
ideas and tips in the use of
their sign making equipment
and their sign making proce-
dures. The photo shown is
an example of the sign style
at the right and lettering that
will be installed in the Town
Center development.
Town Center
Xcel finished installing under
ground electric cable and con-
duit for MCI and Comcast ca-
ble in a joint trench along
Market Street and Oak Street.
The next steps are splicing ca-
bles and conduits, placing a
few new poles, and removing
existing poles. This work is to
be done by different crews for
each utility.
Burow Pond
Garzke Construction finished
the fine grading operations
and the restoration of the dis-
turbed areas with seed and
mulch. The Burow Pond City
improvement project is now
finished with the completion
of this work.
Nater Estates
The developer's utility
tractor, Minger Con-
struction, installed an
extension of the City's
sanitary sewer main to
the lot line between
lots two and three and
set a new manhole
there with services for
each lot. They then
patched Cullen with
blacktop.
Town Center
Street Signs
con -
November 6, 2003
Code Enforcement Report
Code Enforcement has issued
a footing and foundation per-
mit to Carlson Levine, Inc. for
a building expansion at
Lloyd's Barbeque at 1455
Mendota Heights Road,
Somerset Neighborhood
The Engineering Department
has been out in the Somerset
neighborhood gathering pre-
liminary survey data that is
being used in the preparation
of the feasibility report for this
project.
Rogers Lake
The Rogers Lake cross culvert
project started at the end of
this week and consequently
the Engineering Department is
now involved with the inspec-
tion and coordination on this
project.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER October 30, 2003
Park Report
The Parks Crew picked up
trash daily in the parks. They
also completed the following
other tasks this week:
• They mulched leaves in
parks
• They cleaned up some
black paint that was
sprayed on doors and con-
crete surfaces at Kensing-
ton Park by vandals
• They removed a large wasp
nest from Mendakota Park
• They prepared the area at
Rogers Lake to move in the
lake aerator
• They removed the volley-
ball and tennis court nets
and stored them for the
winter
• They winterized and stored
all summer equipment
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He worked with Braun
Pump to replace the trans-
ducer at the Centre Pointe lift
station this week (used for
level control). He inspected
the sanitary and storm sewers
with RKI at Town Center this
week for final acceptance —
they had to clean some dirty
manholes.
He flushed and jetted some of
the Freeway Road neighbor-
hood sanitary sewers where he
knows that the roots are a
problem.
Street Report
The Street Crew preformed the
following tasks this week:
• They monitored and main-
tained the Halloween brush
pile
• They repaired a broken
storm sewer pipe located in
a resident's yard at the end
of Valley Curve
• They patched the Wood-
ridge Drive cul-de-sac and
some potholes on Sylvan -
dale Road and Maple Park
Drive
• They replaced some stolen
street name signs
• They worked with MnDOT to
remove a street light at
TH13 and Mendota Heights
Road that is no longer
needed because MnDOT in-
stalled a new one with their
new traffic signal light
Code Enforcement Report
RJ Ryan Construction has re-
quested a final inspection for
the St. Thomas Ice Arena. Dick
says that they can use the ice
but not the stands until they
make some changes.
Town Center
Xcel Energy is working on bury-
ing the overhead transmission
lines that run along TH110 in
front of Town Center. They are
also burying the Com Cast and
MCI cables that are co -located
on their poles. The Xcel work-
ers discovered that they do not
have a permit from MnDOT to
cross under Dodd Road
(TH149) and completion of the
project will be delayed until
that permit can be obtained.
Burow Pond
Ace Blacktop repaved the bitu-
minous trail located along Vic-
toria Road this week.
Sommerset Street Recon-
struction
Engineering continued to do
surveying in this neighborhood
for completing the feasibility re-
port analyzing the possibility for
repaving their streets next
summer.
Happy Halloween
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked
up trash daily in the
parks, cut grass, and
ground up leaves. They
also completed the fol-
lowing other tasks this
week:
They trimmed trees in
Wentworth Park and
on the pedway con-
necting the park to
Fourth Avenue. They
also cleaned the cul-
verts along this same
pedway
They removed the
soccer nets and goals
from the parks
They attended the
MSTMA conference to
learn about -
pavement mainte-
nance, drainage and
saw equipment demos
Street Report
The Street Crew accom-
plished the following
tasks this week:
They made up and re-
placed some stolen/
missing street name
signs
They put up the tem-
porary fence at Men-
dota Plaza for the Hal-
loween Bonfire
They worked on in-
stalling the new street
name signs for the
Freeway Road and
Town Center project
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He worked
with a homeowner on
Cheyenne Lane to raise
their water shut off box
to match the grade of
their new concrete drive-
way.
He flushed the sanitary
sewer main on Winston
Court (a known trouble
spot).
He is working with the
new homeowner at 1065
Douglas Road to solve a
sanitary sewer problem.
Ah Ah
October 16, 2003
Town Center
The contractor brought in
and spread topsoil for use
in sodding around the
Animal Hospital.
Freeway Road
Bituminous Roadways
paved the last driveway
in the Freeway Road area
this week (Ken Peterson).
Burow Farm
Gartzke Construction fin-
ished the site grading this
week and the easement
areas are ready for seed-
ing.
Sommerset
Engineering began the
surveying in the Som-
merset neighborhood for
use in completing a feasi-
bility study.
TH13 Traffic Signals
The new MnDOT traffic
signals located at TH13
and Mendota Heights
Road are now completed
and are operational.
NEWS Public Works
Engineering The Pipeline
Code Enforcement
LETTER October 9, 2003
Park Report
The Parks Crew picked up trash
daily in the parks, striped fields,
dragged ballfields and cut grass.
The parks crew also completed
the following other tasks this
week:
• They winterized the lawn
sprinkler systems at City
Hall, Mendakota and Ken-
sington Parks, the Fire Sta-
tion and the old fire station
sites
• They repaired sprinkler
heads on the same systems
• They removed a tree from
Wentworth Park
• They attended a Toro work-
shop to preview their new
equipment
Utility Report
Rich checked the City's seven
sanitary sewer lift stations daily.
He was called in late Friday for a
power -out alarm at the Culligan
lift station. He found the roto
phase making strange noises —
the roto phase converts two
phase power to three phase to
run the pumps. He called in To-
tal Electric to fix the problem,
but they were unable to get the
parts needed until Monday, so
John Ambrose and Rich had to
come back two times a day each
to pump the station down using
the portable generator. Total
fixed the problem Monday morn-
ing.
He was called in Sunday at
10:30 A.M. for the Mendota
Heights Road lift station. He
found that Xcel Energy's trans-
former had burned out. Xcel re-
placed the generator Sunday
night.
Street Report
The Street Crew completed the
following tasks this week:
• They removed some land-
scaping timber from Dr.
Hinson's lot for the Town
Center Project
• They installed the street
name signs at Hidden Creek,
Keokuk Lane and Pagel Road,
Warrior Drive and Highway
110, and at the Freeway
Road project
• They patched potholes in the
north end and at Somerset
areas
Code Enforcement Report
Paul issued a permit this week to
Rongitsch Construction, Inc. to
construct the first new home in
his new three lot development
(Nater Estates) located on Cullen
Lane and Lexington Avenue. He
issued a permit to Turner Exca-
vating to demolish the shed and
garage at Nater Estates to make
way for this new home.
He issued a permit to Hypertect,
Inc. and R.J. Ryan Construction
to finish the tenant space at
1180 Centre Pointe Curve to be
occupied by Health Partners.
Freeway Road
The contractor lowered six sani-
tary sewer manholes that had
been installed too high.
Town Center
Marc reached an agreement with
Dr. Hinson and adjusted the
grades at the southeast and
northeast corners of his lot where
the Town Center project left
steep grades. The contractor
also did some other minor grad-
ing throughout the site.
Burow Pond
Garzke finished the underground
utility work (storm sewer and
sanitary sewer) this week and
they are now completing the
grading operations.
Augusta Shores
We included installation of the fi-
nal lift of bituminous at Augusta
Shores within the Town Center
contract. Bituminous Roadways
installed that final 1-1/2" wearing
course on Friday.
Centre Pointe
Ryan Construction completed the
final modification to the Centre
Pointe Boulevard this week which
included moving a street light,
installing sewer and water ser-
vices, and replacing the curb and
gutter.
Wagon Wheel Trail
The Minnesota Department of
Transportation has notified the
City that our plans to replace the
cross -culvert in Roger's Lake
have been approved and we are
authorized to advance the status
of this project. Bids will be
opened on October 16th and pre-
sented to Council for award on
October 21st.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks,
striped fields, dragged
ballfields and cut grass.
They also completed the
following other tasks this
week:
• Earl F. Anderson added
some new play ele-
ments for the play
structure at Mendakota
Park this week. They
also enlarged the rub-
berized resilient play
area (for handicapped
access) and they re-
painted all the play
equipment that needed
it
• Pine Bend Paving in-
stalled the bituminous
pathway to the new
play equipment at Hag-
strom King Park this
week
The Mendakota Park
restrooms were vandal-
ized this week, and the
Parks Crew had to re-
pair the damage —
replaced the tank and
top of two toilets
• The Crew replaced the
corner boards to the
Friendly Hills Hockey
The Pipeline
rink and placed dirt
around the boards to
help hold in the water
from flooding
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He and John
Ambrose planted some
bushes that had to be re-
moved from the front yard
of a home on Knob Road
from curb and gutter place-
ment.
He worked with a private
contractor to remove a cast
iron service lead that was
projecting into the City 's
sanitary sewer main on Ivy
Hill Drive.
Street Report
The Street Crew accom-
plished the following tasks
this week:
• They patched potholes
on Wagon Wheel Trail
• Worked on repairs to
the street lights on Cen-
tre Pointe Boulevard
• Attended the annual Fall
Maintenance Expo for:
Snow plow training
Chain saw safety
October 3, 2003
training
• Gopher State One Call
updates
• Snow and Ice- differ-
ent material options to
salt
North Freeway Road
RKI removed the curb and
gutter at the Peterson resi-
dence, 645 North Freeway
Road, to improve the
boulevard and driveway
slopes. RKI also replaced
Ms. Otto's, 1954 South
Lane, boulevard topsoil
with screened -pulverized
topsoil. (She had com-
plained to the City Council
about bituminous and rocks
being in her topsoil).
Burow Pond
Gartzke the grading con-
tractor ran short of dirt on
this project and hauled in
borrow material Thursday
and Friday.
Hidden Creek
North West Bituminous
placed the final 1-1/2 inch
wearing course lift of bitu-
minous on all of the streets
this week. All that remains
to complete on this project
is striping the right turn
lane off Dodd Road.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks,
striped fields, dragged ball -
fields and cut grass. They also
completed the following other
tasks:
• They worked on repairing
skinned areas at Menda-
kota Park
• They sodded one roll
around infields at fields 2
and 3 at Mendakota Park
• They repaired sprinkler
heads and lines at Menda-
kota that the paving con-
tractor broke while resur-
facing the trails
• They installed a dog waste
sign at Wentworth Park
Street Report
The Street Crew accomplished
the following tasks this week:
• They removed a broken
tree limb at 2151 Theresa
Street
• They cleaned out a culvert
on Wagon Wheel Trail and
resodded the ditch
• They cut down a tree so
that the stump could be re-
moved on South Frontage
Road (blown down)
The Pipeline
• They worked on repairing
the street lights on Centre
Pointe (with Total Construc-
tion) (Roseville Properties
new building is under con-
struction and they are mov-
ing a light and redoing the
end of the median to re-
move a conflict with their
entrance)
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He worked on locating
some buried manholes within
an easement area (trees had
been planted right over the line
and next to the manholes). He
also uncovered a manhole that
had been buried on Dodd Road.
Code Enforcement Report
Paul issued a permit this week
to Total Service Company for
repair to the LeVigne residence,
1869 Eagle Ridge Drive Unit 1.
The LeVignes had used too
large of a wattage light bulb in
a 60 watt rated fixture, which
caused a fire.
He also issued a permit to
Mihm Custom Homes Inc to
construct a new home at 614
Hidden Creek Trail. The home
is a 12,142 square foot home
valued at about $2 million.
September 25, 2003
Freeway Road/Town Center
The sod subcontractor prepared
the boulevard areas for, and
laid sod this week. They were
asked repeatedly to bring in a
water truck to water the sod,
but they did not bring one until
late in the week —we hope it
was not too late, (but the sod is
guaranteed, so if it dies they
will have to replace it). This
completes sodding and seeding
for the Freeway Road area.
RKI conducted the mandrel
testing for the sanitary sewer
lines —everything passed. They
are finishing invert work on
manhole and catch basins and
installing manhole steps. The
sign contractor installed the last
of the street signs. The striping
subcontractor is scheduled to
complete the last of the street
striping work this week.
RKI's work is essentially com-
plete and ready for final inspec-
tions and preparation of a final
punch list.
Burow Pond
The grading of this site is about
complete and utility work is
scheduled to begin sometime
next week.
Hidden Creek
The contractor is preparing to
place the final lift of bituminous
on this project next Tuesday.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER September 18, 2003
Park Report
The Parks Crew picked up
trash daily in the parks,
striped fields, dragged ball -
fields and cut grass. They also
performed the following other
tasks this week:
• They seeded the new
berms that were installed
at the general skating ice
rinks
• They repaired sprinkler
heads at City Hall and Men-
dakota Park
• They removed stump
grindings from Friendly
Hills Park, filled the holes
with black dirt and seeded
them
• They trimmed up a tree in
Valley Park near the tennis
courts and chipped up the
limbs
• Pine Bend Paving com-
pleted repairs to and
patched the trails at five
locations where tree roots
had heaved and damaged
the surface. They over-
layed 1.2 miles of trails in
and around Mendakota
Park and installed a new
200 foot long trail segment
at Hagstrom-King Park to
provide access to the new
play structure
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He also raised a man-
hole cover located on Dodd
Road. He worked with Braun
Pump to perform service checks
of all the sanitary sewer lift sta-
tions —they all checked out OK.
He worked with Xcel Energy to
provide power to the new St.
Thomas Academy ice hockey
arena (it affected the City's lift
station). He and John Ambrose
cleaned a culvert on Wagon
Wheel Trail.
Street Report
The Street Crew performed the
following tasks this week:
• They removed broken tree
limbs at 625 Third Avenue,
Marie Avenue and Sutton
Lane
• They finished repairing
storm water catch basins
• They patched around the
catch basins and potholes
on Northland Drive
• They removed some "No
Parking" signs on TH110
Frontage Road
• Started to replace Freeway
Road street name signs
Code Enforcement Report
Paul issued a building permit
this week to Schomaker Con-
struction Company for a garage
addition at 635 Sibley Memorial
Highway within the Critical
area, the CAD permit was ap-
proved by the City Council at
their September 16 meeting.
He issued three sign permits to
Suburban Lighting for them to
install replacement signs at the
Amoco Station, 2030 Dodd
Road changing their name to
"BP" (British Petroleum).
He issued a permit to William
St. Martin for a garage addition
to their home at 1933 Crown
Point Drive (a front yard set-
back variance was approved by
City Council on September
2nd). Finally, he issued a per-
mit to Steve Landry, 2085
Valencour Circle to construct a
detached garage (a CUP and a
front yard set back variance
were issued by City Council on
July 15).
Town Center
The signing subcontractor in-
stalled new signs for the TH110
exit ramp and moved several
existing signs at MnDOT's re-
quest.
Freeway Road
The sodding subcontractor laid
2,200 square yards of sod.
They completed North Freeway
Road, the north half of South
Lane and started on South
Freeway Road.
TH13/Mendota Heights
Road Traffic Signal
MnDOT's new traffic signal lo-
cated at TH13 and Mendota
Heights Road is now installed, it
is not yet energized though.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks,
striped fields, dragged
ballfields and cut grass.
The Parks Crew competed
the following other tasks
this week:
They repaired the lawn
sprinkler system at
Mendakota Park
They replaced light
bulbs at Mendakota
Park
The worked
with a
con-
tractor to
grind
tree
stumps in
parks
this
week —removed
the
grindings,
installed
black dirt
and
re-
seeded
They
brought in fill
for
the
general skating
rinks
at Wentworth
and
Marie
Parks. They
lev-
eled
the areas
and
seeded
them
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He seal
coated his Northland Drive
sanitary sewer lift station
driveway and marked it for
The Pipeline
"No Parking". (It is located
within the Brown College
west parking lot).
He worked with a contrac-
tor to raise a sanitary
sewer manhole cover that
had been buried in Pilot
Knob Road (replaced curb
and patched street).
He also performed inspec-
tions for new sanitary
sewer connections at 2050
and 2054 Acacia Drive.
Street Report
The Street Crew performed
the following tasks this
week:
Made repairs to catch
basins and then patched
the street on Gryc Court
and Emerson Avenue
Patched potholes on
Staples Avenue
Patched street on Pilot
Knob Road where Rich
raised a manhole cover
Performed maintenance
on grader and on chip-
per
Removed broken tree
limbs from boulevard at
September 11, 2003
570 Hiawatha Avenue
and 613 Winston Court
Worked on making
street signs for Town
Center and Freeway
Road neighborhood
Code Enforcement Re-
port
Paul issued a permit this
week to Golden Construc-
tion to construct a new ad-
dition and remodeling of
the existing building lo-
cated at 780 South Plaza
Drive to house Greg Bol-
ton's Northwest Martial Arts
Facility (Boltz Tae Quan
Do).
He issued a permit to
Kirchner Construction for
Cliff Kirchner's garage addi-
tion at 737 Cheyenne Lane
(variance approved by City
Council).
Town Center
Triple A Landscaping com-
pleted most of the seeding
for Town Center this week.
Triple A Striping completed
lane markings for Market
Street the frontage road,
Dodd Road turn lanes and
the TH 110 exit ramp this
week.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks,
striped fields, dragged
ballfields and cut grass.
The Parks Crew also com-
pleted the following other
tasks this week:
They finished striping
soccer fields
They cut and removed
a dead apple tree from
Ivy Park, a dead ash
tree from Victoria
Highlands Park and six
dead oak trees from
Friendly Hills Park (we
had previously treated
these trees for oak wilt
but, they died any-
way).
Picked up and installed
replacement benches
in the playground ar-
eas at Friendly Hills
and Valley Parks
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He and
Tim installed nets on all
the lift station hatches, as
required by OSHA. The
The Pipeline
nets prevent someone
from falling into the wet
wells when they open the
hatches.
Rich also cleaned the built
up grease from the Veron-
ica Lane lift station's
floats.
Street Report
The Street Crew accom-
plished the following tasks
this week:
Supplied barricades for
a block party on James
Road
Began making up
street name signs for
Town Center
Repaired catch basins
where their joints are
failing causing the
roadways to sink
around them
John Ambrose fabri-
cated a hand gun clear-
ing trap for the Police
Department
Freeway Road
The contractor was pre-
paring boulevards to be
sodded.
September 4, 2003
Town Center
RKI finished constructing
the TH110 exit ramp. A
MnDOT traffic inspector is
currently deciding on how
to sign the ramp —he cur-
rently can not get consen-
sus in his department on
how to sign it. Once the
decision is made, the sign
company will have to spe-
cial order all the signs.
The off ramp can not be
opened to traffic until the
signs are in place and the
striping is completed.
The final lift of bituminous
was put on the Frontage
Road, Market Street, Dodd
Road turn lanes, the west
200' of Maple Street and
the eight foot bituminous
trail that parallels Dodd
Road. They continue to
raise sewer castings and
gate valves in Town Cen-
ter and the Freeway Road
area. The seed subcon-
tractor has begun seeding
between Market Street
and TH110.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks,
striped fields, dragged ball -
fields and cut grass. They
also completed the follow-
ing other tasks this week:
They repaired the
plumbing in Mendakota
Park's men's restroom
They removed the net-
ting for foul balls from
Mendakota Park
They setup the soccer
fields for play in the
neighborhood parks
They repaired sprinkler
heads at City Hall
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He cleaned
sanitary sewer mains on
Dorset Road, Mears Avenue
(roots) and the north half of
Delaware Avenue. He
cleaned out the Public
Works Garage's toilet's
sewer lead because they
were not draining —he found
sand in the line. He also
painted the three fire hy-
drants serving the Lexing-
ton Heights Apartments.
The Pipeline
Street Report
The Street Crew accom-
plished the following tasks
this week:
They cleaned storm
sewer inlets
They removed some old
unnecessary signs from
the Freeway Road
neighborhood
They cleaned the TH13
ditch at Garden Lane
They cleaned up the NE
corner of Keokuk Lane
and Pagel Road to im-
prove the sight distance
Dave worked with Com-
cast to determine how to
repair a storm sewer line
on Ocala where they
"shot" their cable through
our sewer line
Town Center
RKI placed the last of the
Class 5 gravel base on Mar-
ket Street and the Dodd
Road turn lane —these roads
are now ready for paving
with bituminous.
Xcel installed the three
phase power to the CDA's
August 21, 2003
Senior Facility this week.
Installation of the elevators
had been held up pending
installation of the three
phase power. RKI also
worked on boulevards this
week and began grading for
the eight foot bituminous
trail along Dodd Road.
Freeway Road
RKI prepared the boulevards
for receiving sod. They in-
stalled a rip rap flume from
the end of Knob Road to
Warrior pond for erosion
control.
Bituminous Roadways fin-
ished installing the last of
the bituminous driveway
aprons. They began patch-
ing street areas where wet
subgrade has caused the bi-
tuminous base to crack.
They removed a 20" diame-
ter Chinese Elm tree from
the intersection of Oak
Street and North Freeway
Road in order to grade the
homeowners boulevard to
the new curb.
St, Thomas Academy
Veit finished installing the
City's sanitary sewer in front
of the hockey arena and all
of their internal utilities this
week.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks
striped fields, dragged ball -
fields and cut grass. The
Parks Crew also completed
the following other tasks this
week:
• They repaired sprinkler
heads at Kensington Park,
City Hall and the Fire Sta-
tion
• They fertilized the soccer
fields at Kensington and
Mendakota Parks
• They began trimming
overhanging trees and
brush from pedways on
Lexington Avenue, Marie
Avenue and at Victoria
Highlands.
Street Crew
The Street Crew accom-
plished the following tasks
this week:
• Cleaned up around the
Public Works Garage Area
• Assisted with Safety
Camp
• Provided barricades for a
block party
• Patched potholes at 2nd
Avenue, Eagle Ridge
Drive, and Stratford Road
The Pipeline
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He dealt with a power
outage at the Northland lift
station on Wednesday for
three hours and at the St.
Thomas Academy lift station
on Friday.
He and his helper cleaned
sanitary sewers on Dodd
Road, Beebe Avenue, Ivy Hill
Drive and by Lloyds Meats
(greasy buildup).
He performed a sewer inspec-
tion for a new home connec-
tion at 630 Hidden Creek.
Code Enforcement Report
Paul issued a building permit
this week to Hoffman Homes
for their final two townhomes.
Those homes will likely be fin-
ished this winter and the pro-
ject will be closed out. He is-
sued a permit to Mihm cus-
tom Homes this week to begin
construction of a one story
home at 660 Hidden Creek
Trail (estimated value $800K).
There are now five homes un-
der construction in Hidden
Creek.
Town Center
RKI installed concrete cable-
crete at the inlet to the south-
west pond located in the Dodd
August 14, 2003
Road/TH110 intersection to
prevent erosion. Bituminous
Roadway placed the bitumi-
nous base for the new TH110
exit widening. Fisher Con-
crete installed the last of the
curb and gutter on Market
Street and did the curb and
gutter for the turn lane. The
grading crew worked on the
boulevard slope between Mar-
ket Street and TH110.
Freeway Road
The RKI grading crew worked
on fixing driveway aprons and
on restoring the boulevard.
Bituminous Roadways finished
paving the first lift of asphalt
on North Freeway Road and
on Knob Road. All of the first
lift of bituminous is now com-
pleted installation of the sec-
ond lift will be delayed until
next spring to allow time for
any more settlement over the
watermain trenches to occur.
They began work on restoring
driveways.
St. Thomas Academy
After an approval from City
Engineering to raise the sani-
tary sewer elevation to be out
of the ground water level, Veit
made progress on installing
the line.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks striped
fields, dragged ballfields and
cut grass. The Parks Crew
also accomplished the follow-
ing other tasks this week:
• Aerated the lawns at Ken-
sington soccer fields, Men-
dakota ballfields and soccer
field, neighborhood park
ballfields, the Public Works
Garage and the Civic Cen-
ter ballfield
• Swept and top dressed the
Kensington and Mendakota
soccer fields and #3 Men-
dakota softball field
• Applied toner to park signs
Street Report
The Street Crew accomplished
the following tasks this week:
• Painted the crosswalks on
Marie Avenue, Trail Road,
Huber Drive and Mendota
Heights Road
• Patched street on Warrior
Drive —it was at a catch ba-
sin where we have been
experiencing failures
• Disposed of woodchip pile
by giving them to the Con-
gregational Church on
TH110—for their play-
ground that they are in-
stalling for their new day
care activities
• Replaced burned out bulbs
for traffic signal at TH55
and Mendota Heights Road
The Polpelmine
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. Power was out Friday
and Saturday at the Northland
Drive lift station. Rich was out
of town, so Terry Blum came in
and restored the power.
Rich worked with Braun Pump
to replace the controller at the
St. Thomas Academy lift station
(the pumps were not alternat-
ing). The float transducer was
also not working properly and
was replaced.
Freeway Road
Fisher Concrete, the curb and
gutter subcontractor, finished
all of the rest of the curb and
gutter and driveways on Knob
Road this week and the con-
crete work is now totally com-
pleted in the Freeway Road
neighborhood.
Bituminous Roadways, the bitu-
minous contractor paved South
Lane and the last 400 feet of
North Freeway Road this week.
They then backfilled behind the
curbs. They moved all the
mailboxes back in place. They
are starting to replace street
signs today.
Town Center
Bituminous Roadways com-
pleted the bituminous base on
the Frontage Road and the first
200' feet of the new TH110 exit
ramp.
August 8, 2003
The grading crew worked on in-
stalling the Class 5 gravel for
widening the deceleration lane
for the TH110 exit ramp. They
removed curb and gutter and
concrete aprons on Dodd Road
and placed the class 5 gravel in
preparation for installing the
turn lane onto Market Street.
They placed gravel on the west
200 feet of Market Street adja-
cent to Dodd Road, all in prepa-
ration for installing the new
curb and gutter and pavement.
Mueller and Quality Under-
ground finished phase 1
(everywhere curb and gutter
has been installed and future
buildings are not affected) of
installing the private utility
work (electric, gas, telephone,
cable TV and street lights).
Hidden Creek
The Developer's Landscaper
sodded and planted trees on
the outlots adjacent to Dodd
Road.
Code Enforcement
Paul issued a permit this week
to Mihm Custom Homes, Inc. to
construct a new home at 680
Hidden Creek Trail. The home
has a very steep roof line that
caused the home to exceed the
height requirements in the R-1
Zoning District, on Tuesday
evening the City Council
granted a variance allowing the
construction. The home's
evaluation is estimated to be
$900K.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER July 31, 2003
Park Report
The Parks Crew picked up
trash daily in the parks striped
fields, dragged ballfields and
cut grass. The Parks Crew
also accomplished the follow-
ing other tasks this week:
• Attended a Turf and
Grounds Field Day that was
sponsored by the U of M
• Trimmed overhanging tree
limbs at the Civic Center
Site, along pedways on
Marie Avenue and in Valley
and Wentworth Parks
• Repaired landscaping rock
at Kensington Park
• Trimmed hedge line along
pedway in Kensington Park
South
• Removed weeds from
around park signs and at
Public Works Garage
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. Rich and his helper
cleaned sanitary sewers at the
following locations:
• Maple Park Drive
• Maple Park Court
• Sylvandale
• The easement between
Woodridge Court and Maple
Park Court (couldn't locate
two of the manholes —he
will find them later)
He watered the newly planted
trees in Mendakota and Marie
Parks.
Street Report
The Street Crew accomplished
the following tasks this week:
• Repaired a sign and in-
stalled two new bus stop
signs
• Attended Gopher One Call
meetings
• Patched potholes on 3rd
Avenue, Clement Street,
Dorset Road, Mears Avenue
and Delaware Avenue
Town Center
RKI installed the class 5 gravel
base for the new TH110 exit
ramp serving Town Center this
week, the bituminous surface
will be paved next week. Muel-
ler Pipeline and Quality Under-
ground who are subcontractors
for the private utilities (Xcel,
Qwest, ComCast) began install-
ing underground gas lines,
electric lines, street light
power, cable TV and telephone
lines this week. They install all
of these utilities in a common
trench whenever feasible. They
started this work on Oak
Street.
Freeway Road
RKI placed the class 5 gravel
and reclaimed bituminous sur-
face base on Knob Road, North
Freeway Road, and the TH110
Frontage Road in preparation
for installing the curb and gut-
ter. The curb and gutter crew
finished installing curb and gut-
ter on the Frontage Road,
South Lane, North Freeway
Road and most of Knob Road.
The grading crew then began
placing the class 5 base on all
these streets in preparation for
installing the bituminous sur-
face. They also began backfill-
ing the boulevards behind the
new curb.
Hidden Creek
Southview Design, the devel-
oper's landscaping contractor,
worked on planting more trees,
they installed an irrigation sys-
tem on Nature Way, they sod-
ded Nature Way and they
worked on finishing the en-
trance monuments.
Saint Thomas Academy Ice
Arena
Veit Construction started instal-
lation of sanitary sewer main
along Mendota Heights Road —
this line will be a City main that
serves the Visitation property
to the east. Veit encountered
extremely wet conditions at the
pipe level, they worked two
days and were only able to in-
stall 3 pipe. They halted work
until well points could be in-
stalled to lower the water table
level. They spent the remain-
der of the week installing pri-
vate watermains and storm
sewers for the ice arena.
I-35E
MnDOT opened the southbound
ramp from I35 to TH13 this
week.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks striped
fields, dragged ballfields and
cut grass. The Parks Crew
completed the following other
tasks this week:
• They prepared Mendakota
Park for the AAU State 12
and 13 year old baseball
tournament (installed
pitching mounds and 75
foot bases on all four
fields)
• Trimmed shrubs at Menda-
kota Park
• Repaired sprinkler heads at
Mendakota Park
• Replaced park sign plant-
ings at Marie Park and in-
stalled new landscape rock
Street Report
The Street Crew accomplished
the following tasks this week:
• They prepared the street
patch on Mendota Heights
Road for paving (where the
sanitary sewer force main
was repaired)
• They worked with Bitumi-
nous Roadways to com-
plete the first lift of the
Mendota Heights Road
patch
• Supplied barricades for a
block party on Round Hill
Road
The Polpefine
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He also televised the fol-
lowing sewer lines:
• Pagel Road storm sewer —
found a crushed pipe
• Ocala Lane storm sewer —
found a telephone wire
bored through it
• Ivy Hill Drive —sanitary
sewer - (where the jetter
got stuck) found a 6 inch
service pipe protruding into
the main
He raised a sanitary sewer
manhole that was buried by
road construction on Pilot Knob
Road. He watered the new
plantings installed by the Parks
Crew.
Town Center
The RKI grading crew prepared
the remaining streets for a bi-
tuminous surfacing. Bitumi-
nous Roadways the paving sub-
contractor paved Maple Street,
Main Street, Karl Hohenstein
Place and Oak Street this week
with the first lift of bituminous.
RKI started to prepare the SW
storm water holding pond for
its impervious liner and they in-
stalled concrete cable-crete
mats at the storm water inlets
to the pond for erosion control.
July 24, 2003
Freeway Road
St. Paul Regional Water Ser-
vices replaced two existing hy-
drants with new hydrants on
the TH110 Frontage Road. RKI
prepared South Freeway Road
for bituminous and Bituminous
Roadways paved the bitumi-
nous base. RKI prepared the
Frontage Road for bituminous,
South Lane for curb and gutter
and they started to work on
North Freeway Road for curb
and gutter. (I received the at-
tached letter complimenting
RKI and their foreman this
week).
Hidden Creek
Imperial Developers came back
to raise more manholes and
watermain gate vales in the
street. The developer's land-
scaper is planting trees and in-
stalling entrance monuments.
Traffic Counts
SEH does traffic counts on the
City's MSA roads (required to
be done every two years by
MSA). Attached is a spread
sheet showing the results of
those counts.
Attachments:
Freeway Road Letter
Traffic Count Spreadsheet
Michele R. Towle
636 S. Freeway Rd.
Mendota Hts., MN 55118
651-456-5877
Jim Danielson, Public Works
City of Mendota Heights
1101 Victoria Curve
Mendota Heights, MN 55118
July 23, 2003
Dear Mr. Danielson,
I am writing you this letter to thank you and many others for the work being done
to our neighborhood's roads, sewer, and water system. I am looking forward to the
completion of the project and I am confident it is going to be a wonderful improvement.
Secondly, I want you to be aware of the courtesy and professionalism
demonstrated daily by the road construction crew. I met the Foreman for the project a
couple of weeks ago when she came to our front door with a notice regarding a restriction
on using our driveway. She had put the notice in a plastic clear sleeve and gave it to me.
I knew she was the Foreman for the road construction crew because I spoke with one of
the guys on the crew at the end of May. We had planned and invited over one hundred
people to our daughter's graduation party to be held on June 7"'. I was inquiring about
the road status and this guy said the Foreman would know best. Then, he told me it was a
woman and she was doing a great job moving things along. He said she really gets the
job done and she doesn't take any grief from anybody either. He said, "I've got a lot of
respect for her." I think everyone on the crew knew we were having a party that weekend
and were very concerned the road was in the best shape it could be for June 7'. They
even asked how the party went!
Well, I have had the opportunity to observe her and that day at my door, I had the
opportunity to tell her what this guy had said about her. She thanked me and with a little
grin, asked if I remembered who it was. Unfortunately, I would remember if I saw him,
but there are lots of guys out there everyday. I told her how much I appreciated the long
hours and efficiency the road construction crew has executed daily. I have asked several
times if I could get them cold water or lemonade, cookies and they always say no thanks.
Someday, I am just going to make cookies and bring out some cold water and pop and
tell them it is time to take a little break. They deserve it!
In closing, this letter is a plug for the female Foreman. I had to write it because
she is doing a great job and of course, being of the female gender, I wanted to
acknowledge your wise choice in hiring her for the job.
Sincerely,
Michele R. Towle
Cc: Bill Knutson, Inc
MENDOTA HEIGHTS TRAFFIC COUNTS ON MSA ROUTES
Road Location 2003 ADT 2001 AD T 1999 ADT
Acacia Blvd/Pilot Knob Rd West of TH 55 1134 1168 Not in System
North of TH 13 2874
Chippewa Avenue North of TH 149 621 706 331
South of TH 13 831
1997 AD T 1925 ADT 1993 ART
566 463 523
Decorah Lane
East of TH 149 (Dodd Road)
1761
1954
2126
2210
Not on system
Not on system
West of Huber Drive
No
Counts
No
Counts
2428
1359
Not on system
Not on system
Emerson Avenue
East of TH 149 (Dodd Road)
955
832
833
778
Not on system
Not on system
Huber Drive
West of Delaware Ave.
1329
1470
1612
1474
1691
1393
North of Mendota Heights Road
1259
1103
1215
1141
1233
729
Lake Drive
West of TH 149 (Dodd Road)
406
296
639
618
Not on system
Not on system
Lexington Avenue
North of Wagon Wheel Trail
3794
3497
3393
3323
3273
3584
South of TH 110
9146
7543
7019
5650
5562
4883
North of TH 110
7660
5008
4912
4848
6414
3938
South of Marie Avenue
3620
3333
2985
3141
3036
2437
North of Mendota Heights Road
2750
2349
2334
No Counts
3101
2805
South of TH 113
2732
2248
No Counts
Marie Avenue
West of County Road 63 (Delaware Ave.)
No
Counts
No
Counts
2838
4455
2907
2802
East of TH 149 (Dodd Road)
2682
2901
2693
4653
3035
2576
West of TH 149 (Dodd Road)
3219
3288
3302
3959
3433
2966
East of Victoria Road
No
Counts
No
Counts
3519
3952
3409
3066
West of Victoria Road
1935
1825
1716
1964
1758
1778
East of Lexington Avenue
1059
1267
1104
1201
827
821
Mendota Heights Road
West of Delaware Avenue
1864
1582
1952
1418
1501
1466
East of TH 149 (Dodd Road)
4387
3781
3678
3739
3304
3105
West of TH 149 (Dodd Road)
No
Counts
No
Counts
3951
2605
2940
2223
East of Lexington Avenue
4420
3294
3507
3549
2541
1983
East of TH 55
7734
6964
7519
6827
3282
3345
West of TH 55
3708
3956
3510
4246
2788
2107
East of Pilot Knob Road
No
Counts
No
Counts
4241
3895
3661
2862
East of TH 13
4180
3309
3270
2804
2504
3441
West of Visitation Drive
2922
3611
Northland Drive
West of TH 55
No
Counts
No
Counts
1241
1177
Not on system
Not on system
East of Pilot Knob Road (Cty Rd 31)
4040
4543
3777
1620
Not on system
Not on system
South Plaza Drive
East of TH 149 (Dodd Road)
1009
1049
904
1855
1925
1364
Victoria Road
North of Marie Avenue
No
Counts
No
Counts
3099
3412
3762
3343
Cry Rd 45
South of TH 13
2709
4114
3453
4005
4442
4122
East of Lexington Avenue
2419
1167
South of Marie Avenue
1371
Wagon Wheel Trail
West of TH 149 (Dodd Road)
1085
1008
802
937
993
1022
East of Lexington Avenue
805
782
749
693
482
728
Me. IFOXIIIIII
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks
striped fields, dragged ball -
fields and cut grass. The
Parks Crew also completed
the following other tasks
this week:
Repaired the warning
track at the Civic Center
ballfield which washed
out from the storm
Repaired the women's
toilet that was vandal-
ized at Mendakota Park.
(A cherry bomb blew out
the bottom of the toilet).
Repaired field 1 and field
2 at Mendakota Park —
patched the rec rock ar-
eas
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He and Dave
checked out a plastic storm
sewer pipe on Pagel Road
that was crushed. He will
work with Marc to deter-
mine the cause. He per-
formed a sanitary sewer in-
spection for a new connec-
tion at 1423 Knollwood
Lane.
The Pipeline
The power was out at the
Lilydale lift station on Mon-
day night from 8:00-10:00
P.M. He had to take the
City's mobile generator to
the site to operate the
pumps.
He and his summer helper
cleaned the sanitary sewers
in Valley Lane, Kirchner Ave-
nue, Kirchner easement and
Butler Avenue.
Street Report
The Street Crew completed
the following tasks this
week:
July 3, 2003
Removed a dead boule-
vard tree at 788 Pond
Haven Lane
Patched streets on Fourth
Avenue, Third Avenue,
Vandall Street and Men-
dota Heights Road
Repaired the driveway
access to the site ac-
quired from Resurrection
Cemetery for storing
street sweepings
Hauled rec rock to Men-
dakota Park for the Parks
Crew
Have a safe and happy Fourth of July
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Park Report
The Parks Crew picked up
trash daily in the parks
striped fields, dragged ball -
fields and cut grass. The
Parks Crew also completed
the following other tasks this
week:
• Finished painting Friendly
Hills hockey rink surface
• Prepared Mendakota Park
for the AAU National
Qualifiers Tournament
• Cut up, cleaned up, and
chipped up downed trees
and limbs from Tuesday
night's storm
• Put down the 2nd applica-
tion of crab grass preven-
tor to City Hall, Public
Works Garage, Friendly
Hills, Mendakota, Kensing-
ton, Victoria Highlands
Parks, and the old fire hall
sites.
Street Report
The Street Crew accomplished
the following tasks this week:
• Cleaned storm grates after
Tuesday's storm
• Cut up and removed trees
downed from Tuesday's
storm
Disposed of a dead deer
fi it D 9 M An
3=9
• Patched potholes on Hunter
Lane, Orchard Lane, Som-
merset neighborhood and
in the Industrial Park
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He has also been busy
this week dealing with power
outages from the storms: at
the Veronica lift station, on
Tuesday at 4:30 AM, at the
Northland Drive and Mendota
Heights Road lift stations at
12:15 AM on Wednesday,
then, 40 minutes after he re-
turned home from dealing with
those, he was called back
again for the Veronica lift sta-
tion and the Lilydale lift sta-
tion. (A couple busy nights for
Rich).
He performed an inspection for
a new connection to the sani-
tary sewer for a townhouse at
2065 Acacia Drive.
He pulled the pumps at the
Northland lift station to re-
move some rags that were
stuck in them.
Town Center
RKI put Class 5 gravel down
this week on most of Market
Street, the south half of Oak
Street and all of Maple Street
this week. They installed curb
and gutter on most of Market
Street, the south half of Oak
Street and the east half of Ma-
ple Street. St. Paul Regional
June 26, 2003
Water Services installed a two
inch water service on Market
Street to be used for the City's
irrigation system.
Freeway Road
RKI reclaimed all the remain-
ing bituminous surfaces within
the Freeway Road area. (The
next step will be grading base
for curb and gutter). Wednes-
day after the rain storms, they
repaired driveway washouts.
They began to remove mail-
boxes and put them in tempo-
rary locations out of the way
for street construction. St.
Paul Regional Water Services
installed a new water service
for a homeowner on North
Freeway Road because his ex-
isting service had a blockage
after they hooked it to their
new main.
Hidden Creek
Mueller Pipeline finished in-
stalling the private utilities to
this development this week
(electric, telephone, cable TV
and gas).
Rogers Lake
Pat Lynch and Rich Walsh from
the DNR met with Engineering
Staff this week to "brainstorm"
Cliff Timm's request for im-
provements to Rogers Lake.
Staff will present their findings
and recommendations at the
second Council meeting in
July.
NEWS
Public Works EThe Pipeline
ngineering
Code Enforcement
LETTER June 12, 2003
Park Report
The Parks Crew picked up
trash daily in the parks striped
fields, dragged ballfields and
cut grass. The Parks Crew ac-
complished the following other
tasks this week:
• Prepared for the Parks
Celebration
• Removed and chipped
buckthorn in Friendly Hills
Park
• Fertilized lawns at Menda-
kota and Kensington Parks,
City Hall, Fire Department
and the Public Works Ga-
rage
• Repaired vandalized
women's restroom at Ken-
sington Park
Painted blacktop surface
white inside hockey boards
at Friendly Hills Park
• Cut dead trees and chipped
at City Hall, Fire Depart-
ment, and at Hagstrom
King, Kensington and
Friendly Hills Parks
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He and his summer
helper used the sewer jetter to
clean sanitary sewers at Junc-
tion Lane, John Street, Esther
Lane, and Chippewa Avenue.
He worked with Pipe Services
to use a vac -all to clean out
the lift stations and 10 storm
sewer catch basins.
Street Report
The Street Crew accomplished
the following tasks this week:
• Cleaned out culvert with the
backhoe at Mendota Heights
Road and Delaware Avenue
and Orchard Lane west of
Lexington Avenue
Patched potholes on Men-
dota Heights Road
• Removed dead trees at
1728 Trail Road and 1791
Overlook
Installed "No Parking" signs
on Centre Pointe Drive
Hidden Creek
The Hidden Creek contractor
seeded and mulched the site
this week. They also began
raising manhole castings and
valves in the street.
Code Enforcement Report
Paul issued a permit this week
to American Tower Company
for them to install, Council ap-
proved new cellular phone an-
tennas for AT&T on Henry
Sibley High School.
He also issued a permit to Deily
Construction this week to alter
a space at 2535 Pilot Knob
Road for Brown College to add
about 10,000 square feet of
new classrooms.
Finally, he issued a permit to
Hoffman Homes to construct
another two unit townhome at
2050 and 2054 Acacia Drive.
Town Center
RKI finished installing curb,
gutters and driveway aprons on
Linden Street, 1/2 of Karl
Hohenstein Place and 1/2 of
Main Street this week. They
are now working on grading
and installing Class 5 gravel on
the rest of the Town Center
streets to prepare them for
paving. Xcel was at the site
placing new temporary power
poles to relocate some that are
in conflict with street construc-
tion.
Qwest lowered telephone cable
under the new TH110 exit ramp
now being constructed. CBS,
Dakota County CDA's contrac-
tor constructing the new senior
facility, began site grading and
parking lot construction this
week. They also began hook-
ing the building up to City sani-
tary sewer and water and in-
stalling their storm water pipes
and catch basins.
Freeway Road
The water main replacement
crew finished replacement of all
the water main this week and
began their testing procedure
before putting the new mains
into service. Xcel finished relo-
cating their gas main on Knob
Road.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER June 6, 2003
Park Report
The Parks Crew picked up
trash daily in the parks
striped fields, dragged ball -
fields and cut grass. The
Parks Crew completed the
following other tasks this
week:
• Cut up and removed a
downed tree in Friendly
Hills Park
• Repaired a sprinkler head
in Kensington Park
• Removed the tennis net
posts from Rogers Lake
Park tennis courts to pre-
pare for installation of the
skate park
• Swept the pedway on Pi-
lot Knob Road
• Prepared the hockey rink
surface at Friendly Hills
Park to be painted
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He and his summer
helper cleaned the sanitary
sewers in London Road,
Brompton Court, Diego Lane
and Winston Circle this week.
The residents living at 1745
James Road called the City to
report sewage backing up in
their basement. We checked
and the problem was in their
service lead. They called Ro-
tor Rooter. Rich cleaned out
the City's lines after Rotor
Rooter completed their work.
Street Report
The Street Crew accomplished
the following tasks this week:
• Removed a dead boule-
vard tree on Decorah Lane
Removed a downed tree
limb from Wachtler Ave-
nue at Hilltop Court
• Patched a pothole on Men
dota Heights Road east of
Dodd Road
Replaced some street
name signs
Installed a stop sign at Na-
ture Way and Marie
Worked with Rich to raise
a buried sanitary manhole
at TH13 and Brompton
Code Enforcement Report
Dick Gill reports that this
week R.J. Ryan Construction
finished pouring their footings
for St. Thomas Academy's
new ice arena now being con-
structed on I-494 south of
their campus on Mendota
Heights Road. They have now
begun laying up their ma-
sonry walls.
CBS Construction began
painting the walls and ceilings
on the third floor of the senior
center now being constructed
at Town Center. They are
also well under way installing
the dry wall on the second
floor.
Town Center
RKI grading crew worked
placing Class 5 gravel on Lin-
den Street, Karl Hohenstein
Place and Main Street. Sub-
ject to favorable weather con-
ditions, curb and gutter will
be installed on all these
streets this week. They
started subgrade work for
constructing the streets on
Oak Street, Maple Street and
the TH110 exit ramp this
week (they hit two gas main
while doing this work). They
also hit the telephone line
when removing the pile of ex-
cess soil from along TH110.
Freeway Road
The water main replacement
crew will finish work on North
Freeway Road this week.
They plan on doing South
Lane next week. This will
complete the water main re-
placement work. Xcel Energy
finished installing new gas
mains on Knob Road this
week and are connecting
house services to the new
mains.
NEWS
Public WorksEngineering The Pipeline
Code Enforcement
LETTER May 30, 2003
Park Revort
The Parks Crew picked up
trash daily in the parks
striped fields, dragged ball -
fields and cut grass. They
also completed the following
other tasks this week:
• Repaired the sprinkler
systems at City Hall and
at Mendakota and Ken-
sington Parks
Removed the berms that
had built up around the
infields at Mendakota Park
and removed excess rec.
rock
Street Revort
The Street Crew patched pot-
holes this week at the follow-
ing locations:
South Plaza Drive
2251 Copperfield Drive
• Medallion Drive
Mendota Heights Road
east of Dodd Road
Huber Drive
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He completed yard
restoration work at 741
Knollwood Lane where he
had uncovered and raised a
sanitary sewer manhole that
had been buried by the home-
owner. After he was done, he
flushed the line clean. He jet-
ted clean the sanitary sewer
line from Lloyds Meats. The
line was extremely greasy —he
will work with Lloyds to deter-
mine if there is a problem
with their grease trap.
Town Center
RKI's pipe crew completed
some odds and ends type of
work this week. They in-
stalled the 48" storm sewer
outlet pipe located on the
west side of Dodd Road. The
pipe had to be redesigned be-
cause of a conflict with Exxon
Mobile's pipeline. The grading
crew worked on preparing the
subgrade for streets.
Freeway Road
The combined St. Paul Re-
gional Water Services, RKI
water replacement crew com-
pleted removal of the existing
8" CIP water pipe on Freeway
Road and installation of a new
8" DIP this week. They intend
to start work on North Free-
way Road next week. Xcel
Energy crews began relocat-
ing their gas mains on Knob
Road this week.
Hidden Creek
Northwest Bituminous finished
installing the Class 5 base
material and the first lift of bi-
tuminous on the streets this
week. The developer has
agreed to hold off on installing
the final lift of bituminous un-
til this fall or next spring due
to conflicts with ongoing
house construction.
Code Enforcement Report
Paul issued a building
permit
this week to Johnson
Engi-
neering to construct a new
single family home at
2215
Alice Lane. There are now
only two lots remaining
in this
subdivision.
He also issued a permit for
the Bainey Group; Inc. to con-
struct an 80,744 square foot
tenant space remodeling at
2360 Pilot Knob Road to be
occupied by Land O Lakes.
Marc
Marc hurt his back playing ball
with his son two weekends
ago and has been out with the
injury ever since. He planned
on returning this week, how-
ever he took a turn for the
worse over last weekend and
went to the hospital. There
he was fed pain relief intrave-
nously and received an MRI
that revealed two herniated
disks. He has been out all
this week too and meets with
his neurosurgeon next
Wednesday to determine a
treatment.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER May 23, 2003
Park Report
The Parks Crew picked up
trash daily in the parks striped
fields, dragged ballfields and
cut grass. The Parks Crew
also completed the following
other tasks this week:
• Replaced broken play shov-
els in the sand boxes at
Mendakota, Wentworth and
Valley Parks (popular item)
• Sprayed parks for weeds
• Cleaned up around Ivy
Park —trash around pond,
and leaves around play-
ground timbers and back-
stop
• Planted annual flowers at
Mendakota Park
• Planted crab apple trees at
City Hall —donated by Gar-
den Club
• Cleaned the pedway in Val-
ley Park where the I-35E
slope had slid onto it.
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He also sprayed for
weeds in the following parks:
Wentworth, Ivy, Friendly Hills,
Rogers, Kensington and the
Curley Tot Lot.
He cleaned the sanitary sewer
in Sutcliff Court and in TH13
from Sutcliff to Downing
Street. He arranged with West
St. Paul to use their TV equip-
ment to televise the sanitary
sewer in Lexington Avenue
where he had a backup last
week. He discovered our line
did have roots growing in it.
Street Report
The Street Crew completed the
following tasks this week:
• Cleaned storm sewer grates
• Made up street name signs
• Patched streets within the
Sommerset area —they are
a mess and with the upcom-
ing street project all the
work is to be a waste. We
are trying to do as little as
possible while still making
the streets safe and pass-
able.
Town Center
RKI, using up to 15 belly dump
trucks were loading and remov-
ing the piles of excess soil from
the Town Center site grading
project. We estimate that
there was in the neighborhood
of 7000 yards of material which
means there will be around 500
truck loads to be removed.
RKI's pipe crew finished the last
of the storm sewer lines. They
moved in their grading crew
and began shaping the streets
to subgrade in preparation for
paving.
Freeway Road
The combination RKI, St. Paul
Regional Water watermain re-
placement crew finished replac-
ing the watermain on Knob
Road and started replacing it on
South Freeway Road at Oak
Street this week. RKI had a
crew rebuilding sanitary sewer
manholes to fit the new street
grades.
Imperial Developers had a crew
doing boulevard and general
site grading this week. North
Country Concrete, the curb and
gutter crew finished installing
the last of the curb and gutter
this week. Northwest Bitumi-
nous, the black top contractor,
moved. in their grading crew
this week to place the last of
the Class 5 gravel base in
preparation for installing the
first lift of bituminous.
Watermain Woes
We knew from past experience
with watermain replacement on
Decorah that there would be
problems with the watermain
replacement on Freeway Road,
we iust did not know how bad it
could get. So far we have dealt
with_:
• Broken gas services
• Broken sanitary sewer ser-
vices and flooded basement
(always on a weekend)
• Gas mains in the watermain
trench
• Poor and wet soil conditions
• Manhole castings knocked
off and sanitary sewers
filled with dirt and blocked
• Electrical cable hit, knocking
the neighborhood out of
power
• Temporary water mains
driven over and broken
• People stuck out of, or in
their driveways
• Wrong hydrants
• Slow pace of work
to name a few of the problems.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER May 16, 2003
Park Report
The Parks Crew picked up trash
daily in the parks, striped fields,
dragged ballfields and cut grass.
The Parks Crew also performed
the following other tasks this
week:
• Striped Kensington South
soccer fields
• Installed soccer goals at
Mendakota and Friendly Hills
Middle School for the Sibley
Sting Soccer Program
• Sprayed for weeds in the
parks
Utility Report
Rich checked the City's seven
sanitary sewer lift stations daily.
He cleaned sanitary sewer lines
in Winston Court, Hiawatha Ave-
nue, Garden Lane and TH13
from Garden to Sutcliff this
week.
He was called in this weekend to
respond to a sanitary sewer
backup on Knob Road. It turned
out that RKI, who was digging
the trench for St. Paul Regional
Water Service to replace the wa-
termain, had broken and
blocked a resident's sewer ser-
vice. Their sump pump was
connected to the sanitary sewer
and, due to the heavy rain, had
filled their basement. Rich pur-
chased some supplies and redi-
rected their sump pump to drain
outside.
He sprayed the broadleaf weeds
at Mendakota Park, Fire Depart-
ment, Old Fire Department site,
and the Friendly Hills Tot Lot.
His summer helper from last
year, Luke Carlson, returned to
work this week.
He responded to a sanitary sewer
backup at 2218 Lexington Ave-
nue. He removed roots from the
City's main. It appeared as if the
roots had been cut from a private
service and lodged in our main.
He will televise the main next
week to make sure the problem
was not caused by roots in our
line.
Finally, he performed an inspec-
tion at 1065 Douglas Road for a
new connection to the City's
main.
Street Report
The Street Crew accomplished
the following tasks this week:
• Patched potholes on Knoll -
wood Court and Lane and Ivy
Falls Avenue
Adjusted detour signage at
Town Center
Worked on sod damage com-
plaints
• They opened the culverts un-
der Huber Drive that the bea-
vers had dammed and re-
moved their lodge. Note: I
received several calls from
residents whose sump pumps
were running continually be-
cause of the high water ask-
ing that we remove the
dams. Then after they were
done, I received several calls
complaining that we had re-
moved them. (We have to
keep the drainage way open).
Code Enforcement Report
Paul issued a building permit this
week to Timco Construction
Company to remodel the Center
for Diagnostic Imaging located at
910 Sibley Memorial Highway.
Town Center
There are still
three RKI crews
working at the
site. Two crews
are working
on installing the
storm sewer.
All the storm
sewer for Town Center is in-
stalled. They
are pumping the
pond dry now,
so that they can
finish grading
the pond and in-
stall the pond
liner. All the wa-
termain tests
have passed and
the watermain
is in service.
Freeway Road
One crew began installing storm
sewer in South Lane this week
including ditch aprons so that all
driveway culverts can be re-
moved. St. Paul Regional Water
Services, assisted by RKI should
complete replacement of the 6"
CIP with 8" DIP this week in
Knob Road. They plan on doing
South Freeway Road next week.
Hidden Creek
Imperial Developers prepared the
base for construction of the new
road connection to Marie Avenue.
They started constructing the
turn lane from Dodd Road to Hid-
den Creek Trail.
NEWS
Public WorksEngineering The Pipeline
Code Enforcement
LETTER May 9, 2003
Park Report
The Parks Crew picked up
trash daily in the parks,
striped fields, dragged ball -
fields and cut grass. The
Parks Crew also performed the
following other tasks this
week:
• Maintained the sprinkler
systems at Mendakota Park
and at City Hall
• Filled holes and seeded
them on the soccer fields
at Mendakota Park
• Started lawn sprinkler sys-
tem at City Hall
• Repaired the ramp to the
fishing dock at Roger Lake
Park
• Picked up lake weeds at
Rogers Lake Park
• Removed leaves from be-
hind backstops
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He worked with John
Ambrose to clean and open a
storm sewer pipe that was
blocked with leaves and sand.
He performed inspections for
new connections to the City 's
sanitary sewer at 2077 and
2073 Acacia Drive. He also
performed an air pressure test
on the new mains at Town
Center.
Street Report
The Street Crew performed the
following tasks this week:
• Removed wing posts from
the dump trucks
• Picked up cones, etc from
Spring Clean Up
• Provided barricades at
Henry Sibley from mock car
crash
• Patched and overlayed
street at Summit Lane
• Maintained the road repair
patch on Mendota Heights
Road for the sanitary sewer
repair
Code Enforcement Report
Paul issued a building permit
this week to Hoffman Homes
Construction for another build-
ing of two townhomes at 2095
and 2101 Lake Augusta Drive.
Hoffman tells Paul that they
have two buildings/four units
remaining to construct but that
these units are sold and per-
mits will be applied for soon.
Hoffman is very happy with the
results of this development and
they wish that they had some
more land left.
Paul issued a footing and foun-
dation permit to R.J. Ryan this
week to begin construction of
St. Thomas Academy's new ice
arena. The building is to be lo-
cated at 950 Mendota Heights
Road, south of their school
campus and adjacent to I-494
and I-35E.
Town Center
RKI pressure tested their new
sanitary sewer mains which
passed the test. They pressure
tested the water main and
found two leaks. They spent 6-
7 hours finding the leaks which
both were at fittings. They
tightened the fittings and then
passed the test. They contin-
ued to work on the final stages
of the storm sewer. They have
about two days of work left on
storm sewer. They began
storm sewer work on the Free-
way Road neighborhood area.
The third crew, a combination
of RKI and St. Paul Regional
Water Services began removal
of the 6" CIP and installation of
8" DIP on Knob Road. Work
was very slow going because of
the proximity of gas mains.
They encountered very poor
soils which will have to be sub -
cut and removed when the
street work is done.
RKI poured concrete inverts
(bottoms) in all storm sewer
manholes. EGM finished boring
the 48" diameter steel casing
pipe under Dodd Road for the
outlet from the Dodd Road and
Highway 110 storm water
pond.
Hidden Creek
Imperial spent the week site
grading and putting down class
5 gravel for curb and gutter.
The curb and gutter subcon-
tractor finished all the curb and
gutter except for the radius and
Marie Avenue and at Dodd
Road.
NEWS
Public WorksEngineering The Pipeline
Code Enforcement
LETTER May 2, 2003
Park Report
The Parks
Crew picked up
trash daily
from the parks,
dragged and chalked fields,
striped foul
lines and cut
grass. The
Crew also com-
pleted the
following other
tasks this week:
• Blocked up the wall at
North Kensington Park
comfort station
• Removed the old redwood
playground equipment
from Wentworth Park to
make way for the new one
• Put down crabgrass pre-
ventor at City Hall, Fire
Hall, the Public Works Ga-
rage and Mendakota and
Kensington Parks
• Started up lawn sprinklers
and repaired the broken
heads at Mendakota and
Kensington Parks and the
Fire Hall.
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He cleaned the grease
off the floats at Lilydale's sani-
tary sewer lift station and
checked their storm sewer sys-
tem. He helped the Parks
Crew plant trees. He prepared
the sprayer for his spring
spraying of broadleaf weeds in
parks (plans on starting Mon-
day, May Sth).
Street Report
The Street Crew completed the
following tasks this week:
• Brought barricades to the
spring clean up site
• Cleaned up stump grindings
at 760 Keokuk Lane
• Reinstalled "No Parking"
signs that were taken from
Warrior Drive, Marie Avenue
and Ridgewood Drive
Patched potholes at 1812
Valley Curve, Clement Ave-
nue, First Avenue, Crown
Point (all complaints), City
Hall, and Delaware Avenue
at Emerson Avenue
Overlayed the Miriam and
Chippewa Avenue intersec-
tion
Code Enforcement Report
Paul issued a permit to Hoffman
Homes Construction this week
to construct another one -
building, two -unit town home at
2065 and 2069 Acacia Drive in
Augusta Shores. He issued a
permit to Santanni Homes for a
new home to be constructed at
1065 Douglas Road. This home
is being constructed on a re-
maining vacant lot in the old
Tilsen Highland Heights
neighborhood. Because it is a
lot in the Critical Area, it was
reviewed by the Planning Com-
mission and the City Council
prior to Paul issuing the permit.
Town Center
RKI still has two crews working
at Town Center. The crews
were installing storm sewer
mains, stubs and catch basins
this week. They have finished
installing all the sanitary sewer
mains and all the water mains.
EIM, the boring subcontractor,
completed boring a 24" diame-
ter steel casing pipe under
Dodd Road and installed the 8"
DIP main in the casing to serve
the site. They also started bor-
ing a 48" diameter steel casing
pipe under Dodd Road to be
used to drain the southwest
pond.
St. Paul Regional Water Ser-
vices (SPRWS) started installing
a temporary plastic water main
on Knob Road to keep residents
supplied with water while they
replace the old 6" CIP with 8"
DIP.
Ace Blacktop reclaimed (ground
up) the old bituminous surface
in the Freeway Road neighbor-
hood over future water pipe
and storm sewer pipe installa-
tion areas. They left as many
areas intact as possible to drive
on.
Hidden Creek
Imperial Developers started fin-
ish grading, storm water ponds,
boulevard areas and outlot ar-
eas this week.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER April 25, 2003
Park Report
The parks crew picked up
trash daily from the parks.
The Parks crew completed
the following other jobs
this week:
Dragged ballfields and
striped foul lines at the
Civic Center and Men-
dakota Parks
Repaired the warning
tracks at the Civic Cen-
ter and Mendakota ball -
fields
Installed bases at the
Civic Center ballfield
Swept the Civic Center
ballfield and City Hall
yards
Repaired the pitcher's
mound at the Civic
Center ballfield
Performed the demoli-
tion required for re-
moving the restroom
walls at the North
Kenlsington Park rest -
rooms —the restrooms
were repeated targets
for vandalism and are
being converted to
parks storage
Removed a dead tree
from Wentworth Park
Picked up trees and
planted them in Ivy
Falls, Wentworth,
Rogers Lake and Hag-
strom-King Parks
Street Report
The Street Crew accom-
plished the following tasks
this week:
• Installed some missing
street name signs
• Worked on sod damage
repairs
• Reinforced a wood re-
taining wall near a creek
• Finished mailbox repairs
• Attended the annual
maintenance expo
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He and John
Abmrose finished jetting
the sanitary sewers clean in
the Freeway Road area. He
found roots in the line at
two spots in South Freeway
Road and gravel in the line
on the 110 Frontage Road
(hopefully not from a bro-
ken pipe).
Last week we hired Impe-
rial Developers to repair a
leak in the force main lo-
cated on Mendota Heights
Road —during the time the
main was being repaired —
tanker trucks were used to
pump the wet well down
and transport the raw sew-
age around the force main.
This procedure may have
dislodged some "stuff' that
was in the wet well be-
cause this week one of the
pumps was plugged with a
broom handle and some
carpet. Rich hired Braun
Pump to help him remove
the "stuff' and put the
pump back in operation.
Code Enforcement Re-
port
Paul issued a permit this
week to Mihm Custom
Homes, Inc. to begin con-
struction of the second
home in Hidden Creek Es-
tates. The home will be lo-
cated at 697 Hidden Creek
Trail (the second lot in on
the north from Dodd Road).
The builder's estimated
value was $575K.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER April 18, 2003
Force Main Repair
This Monday, Public Works
was informed by the Police
Department that cars were
"bottoming out" on Mendota
Heights Road. Tom Olund
and I investigated and dis-
covered a sink hole forming
over the City's sanitary
sewer force main. We
placed barricades around
the sink hole. We con-
tacted St. Paul Regional
Water Services to have
them test to ensure that the
problem was not a water
main break (it was not) and
we asked the Police to keep
an eye on the hole to make
sure it did not get worse.
We called several contrac-
tors to find one who could
be available immediately to
fix the problem. Imperial
Developers, who are doing
the work at Hidden Creek
was located nearby and was
available to do the work.
They began work on Thurs-
day morning (Wednesday
was too rainy a day).
We were concerned about
what could have caused the
break and how severe it
was, but upon uncovering it
we discovered it to be a
small (1/2" diameter) hole
in the top of the pipe. The
hole, as best we could tell,
was caused by a defect in
manufacturing the pipe
(over 30 years old).
We were delayed in repairing
the hole because the pump
which was to remove sew-
age from the wet well during
the repairs did not work and
it took several hours for the
pump contractor to provide
an operable replacement.
The repairs were made and
the road put back in service
late Thursday. We will keep
the surface as Class 5 gravel
for awhile to allow as much
settling as possible before
we put on the final bitumi-
nous surface.
Code Enforcement Report
Dick reports that the shop
drawings from the window
manufacturer for the CDA's
Senior Building at Town Cen-
ter were in error (too small
an opening), so all the win-
dows were too large to fit in
the rough openings. Every
window opening had to be
enlarged (at the window
manufacturer's expense). It
took one week to fix the
window openings. If they
were to manufacture new
windows, it would have been
three months.
Town Center
Knutson added a second
crew to the Town Center
public improvement project
this week. Both crews are
working on installing
sanitary sewer, water
mains and storm
sewers on Linden
Street, Market Street
and Karl Hohenstein
Place.
Hidden Creek
..N Imperial Developers
t
r finished installing a
culvert under Hidden
NOW Repair of the Force Main Creek Trail next to
Dodd Road and they
moved a fire hydrant in the
cul-de-sac this week.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER April 11, 2003
Parks Report
The Parks Crew picked up
trash daily from the parks.
The Parks Crew also com-
pleted the following other
tasks this week:
They dragged ballfields
Turned on the water at
Mendakota and Kensing-
ton Parks
Repaired some picnic ta-
bles
Installed the bases at
the Mendakota ballfields
They installed the over-
head netting at Menda-
kota Park
Attended a training ses-
sion on home plate,
mound and base repairs
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He and John
Ambrose worked this week
on cleaning the sanitary
sewer lines in the Freeway
Road area so that they can
be televised. This week he
finished Knob Road (found
roots at three spots), South
Lane (roots in one spot),
and the 110 Frontage Road
(gravel).
He replaced a hydrant flag
on Orchard Hill, and toured
the Mendota Heights Road
lift station with prospective
bidders on the replacement
project.
Street Report
The Street Crew completed
the following tasks this
week:
Installed some "No Park-
ing" signs near Brown
College
Removed and disposed of
some large limbs that
were blocking a creek by
Marie Avenue
Removed the plow equip-
ment from truck #312
and installed the hot box
to use for patching pot
holes
They worked on some
mailbox repairs
St Paul Water Agreement
The City Council at their
April 1st meeting, approved
a Memorandum of Under-
standing with St. Paul Re-
gional Water Services that
will turn over the City's wa-
ter supply assets to St. Paul
in exchange for them main-
taining and improving them
at no cost to Mendota
Heights, and for reducing
water users bills by 201/6.
Bernie Bullert, General Man-
ager, St. Paul Regional Wa-
ter Services called me this
week to inform me that his
Board had approved the
agreement this Tuesday.
Town Center Update
Marc Mogan conducted a
preconstruction meeting last
Friday with Richard Knutson,
Inc., the City's contactor for
installing the public improve-
ments in Town Center. At
the meeting there were rep-
resentatives from all the pri-
vate utilities, the developer,
and his architect, the CDA's
contractor, St. Paul Regional
Water Services and Protec
Environmental. It was a
very large meeting.
Richard Knutson arrived on
the site with their equipment
this Monday and began work
Tuesday. They had in-
stalled the sanitary sewer
line in Linden Street by
Thursday, and then began
installing the watermain in
Maple Street.
N E W S
Public Works
Engineering The Pipel i n e
Code Enforcement
LETTER April 4, 2003
Parks Report
The Parks Crew picked up
trash daily from the
parks. They also accom-
plished the following
other tasks this week:
They put up the tennis
nets
Trimmed the shrubs
from around park
signs, and removed
leaves
Trimmed trees in the
parks and disposed of
the limbs
They dragged the ball
fields
Worked on repairs to
the drinking fountain
in Mendakota Park —
the fountain is fre-
quently vandalized
They installed more
trash barrels in the
parks
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He helped
the Street Crew install
some new storm sewer
grates for catch basins lo-
cated on Bachelor Avenue
and on Enterprise Drive.
He worked with Visu
Sewer (sewer contractor)
to install a lining in the
sanitary sewer near 1900
Victoria Road. Rich was
having trouble with roots
entering the main at this
location and had two
back ups that entered the
basement of one of the
town house units. He also
helped the Parks Crew by
blowing leaves off the Val-
ley Park pedway.
Street Report
The Street Crew accom-
plished the following tasks
this week:
Used cold -mix asphalt
to install temporary
patches on potholes
until the asphalt plants
open and permanent
ones can be done
John Ambrose per-
formed some welding
repairs
Replaced some broken
storm sewer grates
Made plans to install
some "No Parking"
signs in Centre Pointe
Code Enforcement Re-
port
Paul issued a building per-
mit this week for J and D
Builders to construct the
16' x 14' addition to the
Country Day School. Day
care in residential districts
is allowed by conditional
use permit and the City
Council issued that permit
at its last meeting.
Attached is a copy of a
Star & Tribune news arti-
cle on rotting problems
associated with new
stucco homes. We are
aware of a couple in-
stances that this prob-
lem has occurred in Men-
dota Heights. We do have
a large number of new
stucco homes in Mendota
Heights and hope the
problem is not wide
spread.
NEWS
Public Works Engineering The Popeline
Code Enforcement
LETTER March 28, 2003
Parks Report
The Parks Crew picked up
trash daily from the parks.
The Parks Crew completed the
following other tasks this
week:
Swept pedways
• Removed "thin ice" signs
from Rogers Lake aerator
area
• Removed the aerator from
Rogers Lake and put in
storage at the Public Works
Garage. (Note: for the
second winter in a row the
City was not notified by the
DNR to run the aerator)
Trimmed the shrubs
around the Public Works
Garage
Removed a downed tree
from North Kensington
Park
• Stripped out the bathroom
at North Kensington Park
to be remodeld for storage
Utility Report
Rich was on vacation this week
so Tom Olund checked the
sanitary sewer lift stations this
week for him.
Street Report
The Street Crew worked this
week with Pearson Bros., Inc.
the City's street sweeping con-
tractor to sweep the City's
streets. This was a new con-
tractor for the City and they did
a great job. They had 6 ma-
chines, and worked, beginning
on Monday through noon on
Thursday. They began every-
day at 6:00 A.M. and worked
until 6:00 P.M. The sweeping
contractor sweeps up the sand
from the street and dumps it in
the City's trucks for disposal.
Code Enforcement Report
Paul issued a building permit
this week to Hoffman Homes to
construct another one of their
two unit townhomes on Acacia
Drive. Hoffman Homes now
only has 4 buildings remaining
on 8 lots.
He also issued a permit this
week to Steven Hanson, Inc. to
repair the fire dam-
aged home at 1562
Wachtler Avenue.
The home was se-
verely damaged by
fire on January 20,
2003. Paul said that
although the struc-
ture was severely
damaged by the fire,
they do not need to
demolish the build-
ing, they are able to
reconstruct what
was damaged —
walls, rafters, wiring
and plumbing.
House Flooded
A neighbor living next to 900
Mendakota Court called Public
Works on Wednesday to report
that a large quantity of water
was running out of the south
side of the home. We con-
tacted St. Paul Regional Water
Services and they shut off the
water at the curb stop. The
homeowner has been out of
town for a long time, leaving
the home vacant. The neighbor
was able to contact him and in-
form him of the problem.
We are unsure of what caused
the problem, however we sus-
pect that the temperature in-
side the home probably went
below freezing causing a pipe
to burst. St. Paul Regional Wa-
ter Services informed us that
the meter showed that over
one million gallons of water
went through it last month (half
the size of the water tower).
Water damaged house on Mendakota Court
NEWS
Public Works T h e P i e l i n e
Engineering
Code Enforcement
LETTER March 21, 2003
Parks Report
The Parks Crew picked up
trash daily from the parks.
They also completed the fol-
lowing other tasks this week.
• They worked on maintain-
ing winter equipment and
putting it in storage for
summer and on bringing
out summer equipment
• They started sweeping the
pedways
• They worked on removing
some downed trees from
the pedway in Valley Park
• They inspected pedways to
determine which ones need
repairs this summer
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He worked with the
Street Crew to open frozen
culverts with his sewer jetter—
(culverts on Hunter Lane, Cal-
lahan Place, Wesley Lane, Or-
chard Place, Dodd Road and
Marie Avenue were all frozen).
He was called in on Saturday
to open a blocked outlet to a
pond near Westview Court.
He cleaned grease from the
floats at the Veronica and
Northland lift stations.
He worked at the Lilydale lift
station to solve a blockage
that was preventing one of
their pumps from operating.
Street Report
The Street Crew worked with
Rich to open frozen culverts.
They fixed some potholes in the
Crown Point area.
Pearson Brothers were the low
bidder on this years street
sweeping contract. They have
notified Public Works that they
will begin sweeping streets next
week (the earlier the better as
it prevents sand from being
washed into the storm sewers).
The only concern is that if we
have a serious ice storm after
sweeping, and we have to put
down more sand it will have to
be swept up.
The City's Street Crew works
with the sweeping contractor to
haul away and dispose of the
swept up sand, so they re-
moved the sanders from the
dump trucks this week so that
they would be ready to haul
and dispose of the sand on
Monday.
They worked on making some
replacement street name signs
and installing them.
Water Main Repairs
St. Paul
Regional Water Ser-
vices crews were called out
Thursday
morning to repair a
break in
the cast iron water
main on
Cherry Hill Road just
north of
the Lower Colonial
Drive intersection. They fin-
ished their
repair work on
Thursday.
Flashing barricades
protected
the pavement area
that was
removed in conjunc-
tion with the excavation neces-
sary to expose and repair the
water main. They placed a cold
mix bituminous patch on the
street.
Skate Park
On Thursday evening Guy, a
representative from SkateWave
(modular skatepark system),
thirteen skate enthusiasts, four
parents, and two park commis-
sioners participated in a work-
shop to select a list of obstacles
that will be sent to several ven-
dors for bids. The Commission
has requested bids from both
vendors that supply an all steel
product and those using a
wood/resin (super tough maso-
nite) product for the skate sur-
face, with steel for the support
frames. Vendors bids will be re-
viewed on April Sth and sent to
the City Council for considera-
tion and award on April 15th. If
approved, the park would be
open before July Vt
NPDES Phase II MS4 Gen-
eral Stormwater Permit
Marc, Guy and Jim met, on
Thursday, with Eric Ealy and
Drew Budelis, the consultants
preparing our permit applica-
tion, to continue work on the
next stage in the process to
complete the City's permit
document that must be submit-
ted by May gth to the Minn.
P.C.A. Items covered at this
meeting were the "Self -
Assessment Memo", "Ordinance
Review", and preliminary BMP
(Best Management Practices)
and Measurable Goal Options".
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER March 14, 2003
Parks Report
The Parks Crew picked up the
trash daily from the parks. The
Crew began changing over equip-
ment from being snow removal
equipment to lawn maintenance
equipment. They attended an Ex -
mark seminar to learn how to op-
erate and maintain our new Ex -
mark lawn mower, and they at-
tended a seminar put on by Toro
to learn how to troubleshoot and
repair lawn irrigation systems.
Utility Report
Rich checked the City's seven
sanitary sewer lift stations daily.
He worked with Keating Electric
Company to analyze the City's
portable generator for conversion
to be able to run the City's lift sta-
tion on Mendota Heights Road af-
ter it is remodeled this summer.
He worked with a pump mainte-
nance company numerous times
this week to try and solve a prob-
lem with the Lilydale lift station.
Mendota Heights has an agree-
ment with Lilydale which provides
for Rich to do this work for them.
Code Enforcement Report
Paul issued a permit this week to
R.J. Ryan Construction to remodel
2060 Centre Pointe Blvd., Suite
#10 for occupancy by Permasteel.
He issued a permit to Fendler
Construction this week for them to
remodel 1395 Commerce Drive
into an office and vault area to be
occupied by Associated Bank.
N. U. R. T.
NORTH URBAN REGIONAL
TRAIL
County staff met with Jim, Marc
and Guy on Thursday to discuss
their preliminary layout for a pro-
posed trail alignment along the
north side of Hwy. 110 from Dodd
Rd. to Delaware Ave. Once com-
pleted, the NURT trail will begin
near the Lilydale Yacht Club, go
through Valley Park, along Hwy
110 to the new Dakota County
Government Center, then continue
on through West St. Paul, cross
over the Layette Freeway then
down through South St. Paul to the
river. Funding for design and con-
struction is 80% Federal and 20%
County. If a contract has not been
awarded by September 2004, the
Federal funding will be lost and the
project put on hold.
The preliminary design, with the
trail located between Hwy 110 and
the Frontage Road, has encoun-
tered several serious conflicts that
may have no solution and require
the trail to be located on the north
side of the Frontage Road, between
Oak Street and Delaware Avenue.
The County will be working on
these design issues and plans to
have an informational open house,
possibly in May.
NPDES Phase II Permit Update
The City submitted an NPDES
Phase II Notice of Intent Form at
the end of last week to the Minne-
sota Pollution Control Agency
(MPCA) that was prepared by Bon-
estoo Rosene Anderlik Associates
(BRAA) documenting that the City
is finalizing their NPDES Phase II
Permit, and
intends to
submit it by
the May 9th, Date Eve
2003 dead-
line. Staff 3/8/03 5" s
will be meet-
ing with 3/11/03 I-1/
(BRAA) next
Thursday for
a second time to discuss the goals
and refine the details that will be
included in the final NPDES Phase
II Permit application.
On March 7th, the City was in-
formed that we were not required
to submit an industrial discharge
permit to the PCA for the Public
Works Garage.
Town Center Update
The Engineering Department is
pleased to report that MnDOT
started their review of the Town
Center storm water system this
week. The data and results that
were submitted by Barr Engineer-
ing to MnDOT in accordance with
the method they stipulated show
that the anticipated flows and flood
elevations were generally reduced
from those that Barr had modeled
initially. We expect that this infor-
mation will lead to issuance of the
required MnDOT permit soon.
Street Report
The Street Crew worked on repairs
to some "custom" mailboxes that
were damaged during snowplow-
ing. They worked on making some
street name signs. They attended
the annual "Work Zone Safety"
seminar. Some of the topics cov-
ered were: Traffic Control, Sign -
age, OSHA Standards, and other
miscellaneous work zone safety
classes.
Snow Event
nt: Response:
nowfall plowed all areas
2" snowfall sanding and scraping
as required.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER March 7, 2003
Parks Report
The Parks Crew picked up the
trash daily from the parks.
They also completed the fol-
lowing other tasks this week:
• They worked with the
Street Crew on making
street signs
• They maintained the com
pressor
• They closed down the ice
skating rinks for the year
effective Monday, March
3rd
• They cleaned out the
warming houses —dried out
flooding hoses and put
them in storage
They repaired the power
broom
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He flushed the sanitary
sewer line in North Freeway
Road after a resident called to
report that he had cut the
roots out of his service lead.
(Resident's roots in City lines
have already caused one
backup in that neighborhood).
He cleaned the Public Works
Garage's drains of sand. Fi-
nally, he worked with Barr En-
gineering to analyze the City's
lift station located on Mendota
Heights Road for hazardous
material. They did that in an-
ticipation of demolishing the
station after the new one is
constructed.
Code Enforcement Report
CBS is the CDA's contractor
that is constructing their senior
facility at Town Center. CBS
has completed the foundations,
framed the first and second
floors and are beginning to
work on the third floor. The
building is yellow because that
is the color of the fiberglass re-
inforced sheathing. This is a
new type of sheathing that is
more weather resistant. They
are also beginning to pour the
floors for the parking garage
(basement).
Town Center
The City still has not received
the required MnDOT sanitary
sewer and storm water permits
for the Town Center Redevelop-
ment Project that we had ap-
plied for during the first week
of December. Marc and I met
on Monday with Mary Lacho of
MnDot (the permit reviewer)
along with several of her super-
visors and co-workers in an ef-
fort to expedite the process.
Mary will not accept the input
assumptions and results of the
computer modeling
that Barr Engineer-
ing performed for
the City, and in-
sisted that Barr En-
gineering model
the system again using input
data and modeling assumptions
that meets her requirements.
Staff authorized a $2000 pur-
chase order for Barr Engineer-
ing to complete this task, and
the information she has re-
quested has been provided to
MnDot.
Street Report
The Street Crew accomplished
the following tasks this week:
Repaired a broken sander
• Cleaned bridge deck side-
walks
• Removed trash "donated"
on Valencourt Circle
Replaced burned out light
bulbs at the traffic signal on
Mendota Heights Road and
Dodd Road
Removed a large downed
tree limb from a resident's
fence on Laura Court. Tree
was located on unimproved
Emerson Avenue
• Repaired mailboxes hit by
snowplows
Snow Events
Date: Event: Response:
2/3/03 2" Plowed all over
NEWS
Public Works Engineering - The Pipeline
Code Enforcement
LETTER February 21, 2003
Parks Report
The Parks Crew picked up the
trash daily from the parks.
This week they also main-
tained the ice skating rinks
by checking warming houses
and cleaning the ice. Al-
though the ice has been very
wet this week with the warm
weather, we have kept them
open (it's supposed to be
cold this weekend). It will not
be long now before they will
have to closed for the sea-
son.
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He worked with the
resident at 762 Lower Colo-
nial Drive to analyze a sani-
tary sewer backup. He deter-
mined that the blockage was
in their private service. He
did the same thing for the
resident at 1975 Walsh
Lane— with the same result.
He installed a replacement
hydrant flag. He flushed the
City's sanitation sewer line in
front of 1173 Dodd Road af-
ter that resident removed
some roots from their private
service connection.
Street Report
The Street crew accom-
plished the following this
week:
Cleaned bridge decks
Replaced some crime
watch signs
• Maintained some barri-
cades
• Started working on re-
placement street name
signs for the Freeway
Road neighborhood.
(They always do replace-
ment signs with the street
rehabilitation projects).
Code Enforcement Report
Paul issued a building permit
this week to United Properties
Construction to expand the
tenant space for Fidelity Na-
tional Foreclosure and Bank-
ruptcy Solutions. Fidelity's
new space is located at 1270
Northland Drive, Suite #250
and is to be over 30,000
square feet.
He also issued a permit this
week to Streeter and Associ-
ates Inc. to begin constructing
the first new home in the
Hidden Creek Development at
645 Hidden Creek Trail.
He issued a permit to C70
Builders for an office space
remodeling of the first and
second floors of the American
Bank located kitty corner
across from City Hall at 1060
Dakota Drive.
Update on NPDES Phase II
Permit
This week the Engineering
staff was asked to fill out a
lengthy questionnaire form by
Bonestoo Rosene Anderlik
(BRA) related to the work be-
ing done in conjunction with
preparing the National Pollu-
tion Discharge Elimination
System (NPDES) Phase II Per-
mit required by the Environ-
mental Protection Agency as
mandated under the Federal
Clean Water Act. We were
also recently notified by the
MPCA that the deadline for
submitting these NPDES
Phase II Permits has been ex-
tended by 60 days until May
9th, 2003.
LMRWMO News
Board members of the Lower
Mississippi River Watershed
Management Organization
(LMRWMO) attended their
regularly scheduled watershed
meeting this week. One of
the major items on the
agenda was the presentation
and review of the watersheds'
storm water quality modeling
study that was performed by
Barr Engineering. The report
predicts the amount of phos-
phorus transported from dif-
ferent land uses in the water-
shed and identifies potential
structural improvements and
practices that could be imple-
mented to improve the water
quality of receiving waters.
NEWS
Public Works Engineering The Pipeline
Code Enforcement
LETTER February 14, 2003
Parks Report
The Parks Crew picked up
the trash daily from the
parks. They also completed
the following other tasks
this week:
Checked rinks and
warming houses daily
Broomed and removed
snow from the skating
rinks
Cleaned pedways
Worked on finishing
painting the mechanic's
area
Repaired a light at the
Wentworth Park warm-
ing house
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He had to
work with Lilydale's lift sta-
tion contractor to repair a
starter for their pump. This
work was done under war-
ranty as their pump is less
than one year old. He com-
pleted his record keeping
work this week annotating
where he cleaned sewers in
2002. (Needs to be done
for insurance reasons and
to keep track of lines
cleaned for scheduling future
work).
Street Report
The Street Crew worked on
mailbox repairs, did some
clean up plowing and sand-
ing of some slippery areas.
Watermain Break
There was a watermain
break at Copperfield Drive
and Stone Road on Thursday
of this week. Because the
ground was frozen deep, the
repairs took an extra long
time and residents were out
of water until after dark.
(This area has the new duc-
tile iron pipe mains which
usually don't break, but a
valve failed). While there, a
resident told Tom Knuth of a
fish kill in Copperfield Pond.
Tom investigated and found
a sizable number of small
sunfish and some large
perch that had died.
NPDES Permit Meeting
Members of Public Works,
Engineering and Patrick Hol-
lister met with Drew Budelis
of Bonestroo staff on Thurs-
day to begin working on the
NPDES permit. Thursday
was 'self assessment" day
where Drew asked questions
of the City's storm system
operation so that he could
"fill in the blanks" on the
permit. This permit will ad-
dress the general quality of
the storm water of Mendota
Heights'. The original dead-
line for submitting this per-
mit to the MPCA was March
10th, however Drew in-
formed us that the deadline
has been extended 60 days.
Industrial Permit —for
PWG
The City also needs a NPDES
Industrial Users Permit for
the Public Works Garage.
We toured the area with
Chad Engels, Bonstroo on
Wednesday to prepare for
completing that permit. The
MPCA still has not finalized
the permit requirements for
that permit and it was sup-
pose to be submitted by
March loth.
�
Happy Presidents' Day i
NEWS
PEngineering
ublic Works The P e l n e
Code Enforcement
LETTER February 6, 2003
Parks Report
The Parks Crew picked up
the trash daily from the
parks and, plowed snow
from the cul-de-sacs. The
Parks Crew also cleared
snow from the ice skating
rinks, the parks parking lots
and the pedways.
They power washed the
walls in the mechanics bays
in preparation to paint
them. They unthawed cul-
verts under the pedway be-
tween Fourth Avenue and
Wentworth Park and at-
tended a seminar on wood
chipper safety.
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He plowed
Date: Event:
1-28-03 1/2"
1-30-03 1/2"
1-31-03 1"
2-2-03 1"
2-3-03 6"
his normal route on the
north end and he cleaned
the snow from his lift station
lots and driveways.
Code Enforcement Report
The City's new recreational
vehicle ordinance was
adopted by the City Council
on December 17th and went
into effect on February 2nd
after it was published.
Paul, Dick, Jim, Carl and Pat
met on Wednesday, Febru-
ary 5th, to discuss proce-
dures for implementing this
ordinance. At the meeting,
we finalized a permit form
for allowing temporary park-
ing for recreational camping
vehicles and designated a
placard for putting in the
window of the vehicles indi-
cating that it is permitted.
Snow Events
Response:
The City has already re-
ceived three complaints on
recreational vehicles. In-
spections were made on the
complaints and letters sent
to the violators.
Mosouito Control
I received the attached letter
from The Metropolitan Mos-
quito Control District this
week advising the City of
their expanded efforts that
are planned for the 2003
season.
Street Report
The Street Crew mixed sand
and salt to put on streets,
repaired mailboxes that
were damaged from being
hit by the wet heavy snow,
and replaced a worn out
spinner motor on truck #308
(for spreading salt/sand).
Scrape main lines and sand neighborhoods
Scrape main lines and sand neighborhoods
Plow curb to curb (First of the season)
Scrape main lines
Plow all areas
2-6-03 2" (forecasted dusting) Plow all areas
An0 A ice"
Y [ U
„„EP1N sr' 5EYMETROPOLITAN MOSQUITO CONTROL DISTRICT
METRO COUNTIES GOVERNMENT CENTER
2099 UNIVERSITY AVENUE WEST ■ ST. PAUL, MINNESOTA 55104-3431
...IT nA�n,A� 651-645-9149 ■ FAX 651-645-3246 TTY use Minnesota Relay Service
JOSEPH F. SANZONE, BCE W.J. CAESAR
Director Business Admin.
January 30, 2003
James Danielson
Director, Public Works
City of Mendota Heights
1101 Victoria Curve
Mendota Heights, MN 55118-4106
Mr. Danielson:
hi December, representatives from the Metropolitan Mosquito Control District (MMCD) met
with the City of St. Paul Division of Parks and Recreation Advisory Committee. Information was
provided describing how MMCD controls mosquitoes, and the control materials used. In
addition, the group discussed mosquito transmitted disease, including West Nile Virus, and efforts
to reduce risk. After the presentation, the advisory committee voted unanimously to recommend
removing any restrictions on the control of mosquitoes on land managed by the City of St. Paul
Division of Parks and Recreation.
MMCD's plan for 2003 is to aggressively monitor mosquito populations in the Pickerel and
Crosby Lake areas, and provide control when populations exceed threshold levels. MMCD is
confident these control measures will reduce the number of mosquitoes in the surrounding areas,
and help make this upcoming summer more enjoyable.
If you have any questions regarding MMCD's plan for 2003, please contact me.
Respectfully,
A�
Jim Stark
(651)643-8363
jimstark@visi.com
cc: Patrice Bataglia,Dakota County Commissioner, Jim L. Toye, Mayor of Mendota, Tom Peine,
Ivy Falls Neighborhood Association
AFFIRMATIVE ACTION EMPLOYER
® Printed on recycled paper containing at least 15%post-consumer paper fibers
NEWS
Public Works The Pipeline
Engineering
Code Enforcement
LETTER January 24, 2003
Parks Report
The Parks Crew picked up
the trash daily from the
parks. They worked on
ice rink maintenance this
week— broomed rinks
and flooded rinks. They
also worked on equip-
ment maintenance.
Utility Report
Rich checked the City's
seven sanitary sewer lift
stations daily. He inves-
tigated a sanitary sewer
backup at 1183 Dodd
Road and found the prob-
lem to be in the home-
owner's private service.
He and Tom Olund at-
tended their annual sani-
tary sewer operator's
school held at the Radis-
son Hotel in Bloomington,
Minnesota. They need to
attend this school every
year in order to keep
their operator's licenses
current.
Street Report
The Street Crew trimmed
trees located in the boule-
vard in the Friendly Hills
neighborhood this week.
They used cold mix black-
top to patch some pot-
holes at various locations.
A resident returned a
street name sign to the
City this week that they
found at a garage sale?
Building Maintenance
Len's two maintenance
stalls are cleaned out to
make room for the new
hoist to be installed. That
work will be completed
this week. Because there
is no snow, there is time
for public works available
to do some more mainte-
nance on the shop. The
guys are going to buy
some paint, steam clean
the walls, rent a lift and
repaint the shop area
starting this week.
Code Enforcement Re-
port
Paul issued the full build-
ing permit this week to
CBS Construction Service,
Inc. to finish the CDA's
new senior facility being
constructed at Town Cen-
ter.
He also issued a permit to
Lemaster Construction for
completing repairs to the
garage at 1295 Kendon
Lane. This garage was
damaged by a fire on De-
cember 1, 2002. The
owner's son was winteriz-
ing his motorcycle and left
some gas in an open con-
tainer that gas was ignited
after the garage heater
was turned on.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Parks Report
The Parks Crew picked
up the trash daily from
the parks. They also
worked on flooding
rinks and checking
warming houses this
week. They attended
an expo on Parks at
the Minneapolis Con-
vention Center this
week.
Utility Report
Rich checked the City's
seven sanitary sewer
lift stations daily. He
worked with the Street
Crew to clear some
overgrown branches
and trees from around
his lift stations. He
used some of the chips
around his Culligan
Lane lift station. A
resident on Freeway
Road notified Rich that
they had cleared roots
from their line so he
cleaned the City's line
afterwards. (Thanks
to that resident we will
The Pipeline
not have another
blockage in our line).
Street Report
The Street Crew
worked on trimming
boulevard trees this
week. There has been
a big demand for the
chips from our resi-
dents which saves us
on disposal costs.
They cleaned up leaves
from the street on Val-
ley Curve and on Marie
Avenue.
New Hoist
The City's heavy duty
hoist failed this fall and
the City Council au-
thorized a replacement.
West Side Equipment
was the low bidder and
began installing the re-
placement hoist this
Wednesday. They say
it will take them about
one week to finish their
work. Len needs this
hoist for repairing all of
January 9, 2003
the City's heavier
equipment, but the
snow plows would be
the most critical this
time of year. Hope-
fully, the snow holds
off until the work is
completed.
Code Enforcement
Report
Next week Paul and
Dick will be attending
their annual Institute
for Building Officials
Conference. This con-
ference is put on by the
State for building offi-
cials as part of the re-
quirements for main-
taining their certifica-
tion. The conference is
being held at the Earle
Brown Continuing Edu-
cation Center on the
University of Minnesota
St. Paul Campus. As
he has done in the
past, Russ Wahl will be
filling in for them while
they are gone.
NEWS
Public Works
Engineering
Code Enforcement
LETTER
Parks Report
The Parks Crew picked up the
trash daily from the parks.
They also completed the fol-
lowing tasks:
Flooding ice skating rinks
• Put out hockey nets
• Posted thin ice signs on
Rogers Lake around aera-
tor
Utility Report
Rich checked the City's seven
sanitary sewer lift stations
daily. He and Tom Knuth
measured the infiltration in a
sanitary sewer line that goes
through a swamp near Ridge-
wood Drive. We have com-
pleted some minor repairs to
the line in the past, but have
not done a "lining" because of
the high cost. We recently
found out that the cost of lin-
ing sewer pipes has been re-
duced by one half. This line
leaks heavily and now a good
candidate for being lined.
Street Report
The Street Crew accomplished
the following tasks this week:
• Sanded some slippery
spots due to melting snow
• Removed some over hang-
ing limbs along trails
• Repaired wing on #308
truck
il i 11 0 0 Ah AM
January 3, 2003
Code Enforcement Report
Paul issued a building permit to
Janie Berg, 711 Woodridge
Drive, this week to begin work
on constructing a retaining wall
along TH13 to repair her slope
failure that occurred on June
13, 2001. Her contractor for
the work is G and S Land Craf-
ters, Inc. They began work this
week. They are removing ±
400 cubic yards of soil and
temporarily storing it at Xcel's
tank farm located a short dis-
tance south on TH13. They will
return the soil to be used as
backfill behind the wall as it is
being constructed.
Paul issued a permit to David
Wayne Construction to com-
plete tenant space finishes at
2365 Waters Drive to be occu-
pied by CSI Crown (32,084 sq.
feet) and 2371 Waters Drive
(7,462 sq. feet) to be occupied
by Burke and Associates.
Year End Engineering De-
partment Paper Work
The Engineering Department is
currently in the process of fill-
ing out a number of surveys
from different agencies. The
Engineering staff has begun
work on the Metropolitan Coun-
cil Environmental Services sur-
vey that comes out in Decem-
ber requiring that metro area
communities compile and up-
date data relative to new sani-
tary sewer connections, water
usage, records of individual
sewage treatment systems, and
calculations of sewage flows for
the past year.
The Engineering Department
has also begun updating and
certifying mileage for streets in
Mendota Heights as of the end
of the current year to comply
with Minnesota Municipal State
Aid Street reporting require-
ments. The Engineering staff
will also begin work shortly on
preparing the National Pollution
Discharge Elimination System
(NPDES) Phase II Permit re-
quired by the Environmental
Protection Agency as mandated
under the Federal Clean Water
Act.
Snow Events
Date: Event: Response:
12/24/02 Dusting Sanded slippery areas