1996-04-09 Parks and Rec Comm Agenda Packet (2)CITY OF MENDOTA HEIGHTS
DAKOTA COUNTY, MINNESOTA
AGENDA
PARKS AND RECREATION COMMISSION
April 9,1996
6:30 p.m. - City Council Chambers
1. Call to Order
2. Roll Call
3. Approval of February 13, 1996 Minutes
4. Mendota Heights Athletic Association T-Ball Update
• Norm Gellerman, Executive Director MHAA
• Sue Hanson, MHAA T-Ball Commissioner
5, Bethel Baptist Church Request for Mendakota Field
• Pastor Don Delich, Bethel Baptist Church
6, Saint Thomas Request for Tennis Courts
7, Dakota County Annual Information Sharing Meeting
8, Fort Snelling State Park Advisory Committee Update
• Chris Esser, Recreation Programmer
9, North Urban Regional Trail
10. Architect for Wentworth Park Shelter
11. Funding Source for Replacement of Five Park Bridges in 1995
12. Updates
• Dakota County Parks and Recreation Council Committee meeting
• Proposal for Partnership - Mississippi River Coordinating Commission
• Parks Report
• Police Report
• Mendakota Lights Task Force
13, Adjourn
Auxiliary aids for disabled persons are available upon request at least 120 hours in advance. If a
notice of less than 120 hours is received, the City of Mendota Heights will make every attempt to
provide the aids. This may not, however, be possible on short notice. Please contact City
Administration at 4524850 with requests.
CITY OF MENDOTA HEIGHTS
551L4uL�
April 5, 1996
T0: Parks and Recreation Commission
FROM: Guy Kullander, Parks Project Manager A/ 0
SUBJECT: Architect for Wentworth Park Shelter
HISTORY
At the March meeting, the Commission requested staff to approach Station
19 Architects to request a proposal to prepare drawings for a park shelter similar
in design to the Kensington Park shelters but longer. The existing shelter is
16' x 16' and the Commission was interested in a shelter in the 16' x 24' range.
I contacted Station 19 and related the Commission's request and asked for
a rough estimate for their architectural services. They responded with a quote of
$2,500 to $3,000 to prepare a set of plans for bidding purposes. This did not
include any conceptual drawings or presentations to the Commission.
Station 19 fees for Kensington Park shelters (2) and the comfort station
were 58,500 for approximately 575,000 construction costs. Each shelter cost
between $11,000 and $11,500 to build.
Fees for the Mendakota Comfort station, kiosk, and picnic shelter building
1991 totaled 59,500 for construction costs of $115,000.
The Commission discussed spending 515,000 for the picnic shelter in this
park. Increasing the size of the shelter from 16' x 16' to 16' x 24' is a one-third
increase in size. An increase of one-third in construction costs would mean that
the 16' x 24' shelter would cost between $15,000 and $16,000 to construct.
Architectural fees of $2,500 to $3,000 would put the final cots in excess of
$18,000.
Discuss the architectural fee amount and determine next step. Options are:
1. Request Council to seek Request for Proposals from several
architectural firms.
2. Recommend to Council to hire Station 19.
3. Consider a "kit" type shelter larger than 16' x 16'.
4. Use existing plans from Kensington Park shelters and obtain a
"release" form Station 19 to use same design drawings and
specifications.
GDK:kkb
CITY OF MENDOTA HEIGHTS
MEMO
April 5, 1996
TO: Parks and Recreation Commission
FROM: Guy Kullander, Parks Project Manager A
SUBJECT: Funding Source for Five Park Bridges in 1995
At the March 19 meeting, Council approved the use of unused contingency
funds from the 1995 City Budget for funding all work completed in 1995 on this
project which totaled $31,678.38.
The remaining work, replacement and restoration of bituminous trails will be
paid out of the Special Park Fund in 1996 following completion of the work. This
is currently estimated to be $4,940.
GDK:kkb
CITY OF MENDOTA HEIGHTS
MEMO
March 14, 1996
TO: Mayor, City Council and Interim Ci A"dmi ator
FROM: Guy Kullander, Parks Project Manager 7/1
SUBJECT: Funding Source for Replacement of Bridges in Valley,
Rogers and Wentworth Parks
In September of 1995, staff requested Council to authorize purchase orders
for the replacement of deteriorated wooden bridges in three parks. Funds were
requested from the Special Park Fund.
Council questioned staff about the appropriateness of using Special Park
Fund monies rather than General Tax Revenue for maintenance work items.
Staff informed Council that the Commission had requested this work be
funded from General Tax revenues. The adopted budges for 1994 and 1995
indicated that the Special Park Fund would finance the bridge replacements.
Council authorized the project to go ahead and directed staff to investigate
the use of excess General Fund monies that may be available to pay for this
project and to report back to Council at a later date for determination of a funding
source for this project.
1. The Special Park Fund has a current balance of $463,000.
2. A review of the 1995 Budget by Treasurer Shaughnessy indicates
that little of the legal and abatement contingency was spent during
the year, and that if the Council wishes they could pay for the bridge
repair from that source. The Council has already appropriated
$25,000 from 1995 for the Equipment Reserve.
Treasurer Shaughnessy recommends that funding for the bridge replacement
work to date ($31,678.38), can be taken from the General Fund Contingency and
the remainder of the work (replacement of bituminous pathways at the five work
sites) required to finish the project should be funded from the Special Park Fund.
If Council concurs with the above recommendation, amotion should be
passed authorizing the funding for the bridge replacement work to be taken from
the General Fund Contingency and to designate approximately $4,940 from the
Special Park Fund to complete the project.
GDK/LES:kkb
Attachments: 1. Project cost estimate and expenditure
2. Funding request memo from September 1, 1993
PARK BRIDGE REPLACEMENT PROJECT
1. Rogers Lake Park Replace wooden bridge with
24" CMP culvert. Restore trail
2. Valley Park Replace wooden bridge with pre-
frabricated steel bridge 4'x35'
3. Wentwork Park- North- Replace wooden bridge with pre-
fabricated steel bridge 8'x30'
South- Replace wooden bridge with
24" CMP culvert. Restore trail.
East- Replace wwoden bridge with
24" CMP culvert. Restore trail
PROJECT BUDGET: $ 35,000
Work Item Estimate Actual
Fabricate bridges $ 14,202.84 $ 14,681.90
Concrete footings 6,000 5,879.50
Crane service 4,500 2,400
Tree Service 0 133.13
Mics. materials 0 138.85
Bridge removal and culverts 71000 81445
$ 31,702.84 $ 31,678.38
Note: All above work items were completed
and paid for in 1995
Work Remaining
Restoration of the eight foot bituminous trail at all five work
sites will be bid and awarded in spring of this year. Estimated
cost is $ 4,940.
Estimate of final project cost is $ 36,500.00
Note: Original estimate of $35,000 did not include work at
Rogers Lake Park. The condition of this bridge made it
necessary to remove it now rather than attempt to repair
and remove in two or three years. This added $3,540 to
the total project cost.
The above information was compiled by Guy Kullander (March, 1995)
TO: Mayor, City Council and City Administrator
FROM: Guy Kullander, Parks Project Manager
0 1 /� :) . . ,
September 1, 1995
MIV�AWOT TO
The Parks and Recreation Commission determined that the bridges should be replaced
with steel bridges and in certain locations with culverts. The total budget to correct four
bridges (one in Valley and three in Wentworth) was $35,000 which would come from the
Special Park Fund.
m ;tentworttt Pa s The budget $35,000 would have to be increased approximately -
$10,500 if three -bridges are purchased. The plan to be described replaces the third bridge
• .•., with . culvert. I
Bids were received in late 1994 to replace only the Valley Pazk Bridge which I had
estimated to cost $10,000. The bids ranged from $25,000 to $37,000. Repairs were made to
the wood bridge by the Parks crew with the intention of rebidding the job in 1995.
This summer the Park I
Recreation Commission and determined that it would be replaced with a culvert when the
• ••• bridge became unrepairable,
' n • :1• a t:�
The Rogers Lake bridge brings the total to five wood bridges that must be replaced. � - -
With a budget of $35,000 this can only be done•if two are replaced with steel bridges and the
other three by culverts. I have received reliable bids and quotes for the various operations
required to do this project. The City will act as General Contractor and bid the work in five
categories.
1. Provide two (2) prefabricated steel bridges $14,202.84
2. Crane service to unload and place bridges 42500400
3. Concrete firm to prepare concrete footings 61000000
4. Excavator to remove three bridges, install culverts, backfill and
prep for trail 71000900
5. Asphalt contractor to restore 8 foot trails 32500000
$35,202.84
City crews will remove and dispose of old bridges and provide and restore each site.
I recommend that City Council approve the bridge replacement plan as outlined above
and accept the bid from Continental Bridge for two steel prefabricated bridges. It will take
eight weeks for fabrication and delivery. During this time firm bids will be accepted for the
remaining portions of the plan. Culverts will be installed at three locations as soon as bids are
approved.
If Council so desires to proceed with the bridge replacement plan as detailed above they
should direct staff to issue a purchase order in the amount of $14,202.84 to Continental Bridge
for the fabrication and delivery of two streel pedestrian and light vehicle bridges and further
direct staff to seek firm bids for the remaining portions of the work.