Pipeline 11 06 2009NEWS
The Pipeline
LETTER
Public Works
Engineering
Code Enforcement November 6, 2009
Public Works
The Parks Crew finished fertilizing the parks. They trimmed the shrubs
around the park signs. The area for the new general skating rink at Ivy Falls Park
was leveled off. The snow plows were brought down from the water tower and
serviced.
Rich mulched leaves at the Veronica lift station. He did a final inspection of
the storm sewers at Bituminous Roadways on Commerce Drive. He helped put out
the Halloween bonfire with John Boland with a fire truck. He did an inventory of
dangerous storm sewer grates for bicyclists on Mendota Heights Road and found
15 bad ones. He replaced a broken manhole cover on Brompton Place and
Highway 13.
The Streets Crew pushed up the Halloween bonfire. They helped the Fire
Department put out the bonfire fire. The ashes were then pushed up to dry out.
BFI was called to obtain four dumpsters to load the bonfire ashes in and then it
was cleaned up. A tree was pushed off the road on Victoria and Marie Avenue. A
dead deer was picked up on Highway 110. John Ambrose welded a new jack stand
on the roller trailer.
Engineering
Visitation Drive & Mendota Heights Road Roundabout - Council accepted
permanent Roadway and Utility Easements as a gift from the Convent of The
Visitation at their meeting on November 3rd. The 16,963 square feet of easement
area was necessary in order to complete the roundabout project. The easements
were given to the City free of charge as part of the cooperative agreement
between the City and The Visitation School. The roundabout is scheduled for
advertisement for bids in December with bid award anticipated to be before
Council in January.
Water Tower Rehabilitation - The consultant hired at the October 6t" Council
Meeting provided a project update to Council at the November 3rd meeting. The
consultant provided photos of the areas within the water tower in need of
renovation as well as the scope of their work and a schedule of events through
Page - 1
project completion. It is anticipated that the water tower rehabilitation will take
place during the summer of 2010, and will last for several months. Part of the
consultant agreement is to conduct meetings with neighboring property owners to
prepare them for the construction project.
2010 Road Reconstruction Project - Council conducted the Public Hearing for the
2010 Road Reconstruction Project at their November 3rd meeting. Streets included
in next year's project are Simard Street, Miriam Street, Valley Lane, View Lane,
Esther Lane, John Street, Spring Street, and Diego Lane. A Neighborhood Meeting
was held on October 28th, and a number of residents attended both it and the
Public Hearing. Questions centered around assessments process and options, as
well as stormwater management questions concerning rain gardens and retaining
ditches in lieu of curb & gutter. The project is anticipated to be bid sometime
during the spring of 2010.
Dakota County Regional Visioning Study (Delaware/494 Interchange) - Staff
has been working with the technical committee for the Dakota County Visioning
Study since February of 2009. A component of the study, which is analyzing
traffic needs between Interstate 35E, US Highway 52, State Highway 110, and
County Road 30 (Diffley Road), is whether an interchange is necessary at, or in
the vicinity of, Delaware and Interstate 494. Another component of the study is
leaning toward the partial or total closure of the I-494 and State Highway 149
(Dodd Road) interchange due to perceived congestion issues with the I -35E exit
ramp as well as its proximity to the potential new interchange at Delaware
Avenue. The next public meeting for the Visioning Study will be November
10th at the Inver Grove Heights Community Center from 4:30pm to
7:OOpm. The consultant will be presenting the final conclusions of the study to
Council sometime over the winter.
Dakota County Soil and Water Conservation District - Staff met with Jim Davidson
of the Dakota County SWCD. The county is in the process of receiving grants from
the state for storm water projects. The city identified two separate stream bank
stabilization projects, replacement of a failed outlet structure in interstate valley
park as well as a potential pond in the Northeast quadrant of Dodd Road and Marie
Avenue. Stream bank project grants will need to be applied for by December 1St
Proposed Lake Drive Closure - Council approved the Traffic Safety Committee
recommendation to send a letter to the Rogers Lake neighborhood asking for
feedback on the concept of closing Lake Drive between Swan Drive and Saint
Thomas Academy. Staff met with both Visitation School and Saint Thomas
Academy this past week to inform them of the concept and will be sending a letter
to the property owners in the Rogers Lake Neighborhood, Visitation, Saint
Thomas, and Patterson Dental next week. An initial Public Hearing will need to be
conducted in January.