The Parks crew fertilized the soccer and ball fields at Mendakota Park,
Kensington Park and Civic Center ball field. The goal mouths at the
Kensington and Mendakota soccer fields were repaired. Dirt was hauled
into the fields, leveled off and seeded. A faucet in the women's restroom
was repaired at Kensington Park South. A sprinkler head was repaired at
City Hall.
Rich cleaned the sanitary sewer lines in the Ivy Keep I & II easements
and Maple Park Drive. He painted hydrants in the Copperfield
neighborhood. New wood mulch was put down around the landscaping at
the Culligan lift station.
The Streets crew blacktopped Mendota Heights Road. Sand was picked
up from Bituminous Roadway and used to cover the new pipe on
Chippewa Avenue which is being repaired by Gartzke Construction.
Engineering
Visitation Roundabout - The City's consultant is completing the
preliminary review package for MnDOT submittal early next week. Once
MnDOT reviews the package and provides comments, the consultant can
proceed with final design documents. The City Council, by process, will
be asked to accept the final plans and authorize the advertisement of the
project and the collection of bids. It is anticipated that this will take
place at either the second Council meeting in October, or the first Council
meeting in November.
Hiring the Civil Engineer I Position - The hiring panel for the Civil
Engineer I position completed interviews this past week. We interviewed
10 candidates and three of the ten stood far above the others. Staff will
be checking references and intends on offering the position to the lead
Page - 1
NEWS
LETTER
Public Works
Engineering
Code Enforcement
The Pipeline
August 7, 2009
candidate on Monday. If the offer is accepted, a hiring authorization will
be before City Council at the August 18th Council meeting.
Sanitary Sewer Analysis - Staff has been analyzing the Sanitary Sewer
Utility Fund for the past several weeks, and has completed a proposal for
the future of the fund that will be included in the upcoming budget
workshop packets sent to Council. At issue is the revenue side of the
Utility Fund and the available cash balance. Staff is proposing a rate
increase to address the issues brought up by the auditor in the Audit
Report presented to Council on Tuesday night.
Traffic Safety Committee - The quarterly meeting of the Traffic Safety
Committee was held on Tuesday afternoon. Five issues brought forth
from area residents were discussed and recommendations will be
forwarded to City Council at the August 18th Council meeting.
Bituminous Roadways - Staff is reviewing the Building Permit plans for
the Bituminous Roadways site development on Commerce Drive. Staff
has also been working on the issue of an easement vacation for the
proposed Bituminous Roadways site. There is an existing easement from
an older plat that is no longer used for utility or roadway. The public
hearing and decision on vacating the easement is scheduled to be before
City Council for the September 1st Council meeting.