Pipeline 01 16 2009NEWS
L E T T E
The Pipe
Public Works
Engineering January 16, 2009
Code Enforcement •
Public Works
The Parks Crew check the warming houses, rinks and Rogers Lake aerator daily. They
continue to flood; broom and snow plow the rinks. They also plowed the cul-de-sacs,
pedways and parking lots.
Rich put up the "thin ice" signs for the Rogers Lake aerator and started the pump for the
winter. He plowed cul-de-sacs and lift station parking lots. He painted the floor at the
Mendota Heights Road main lift station.
The Streets crew mixed more sand and salt. They did maintenance on all plow trucks and
greased the wings and sanders. The bridge decks were cleaned on Mendota Heights Road
and Wagon Wheel Trail.
Snow Events for the Week:
Date: Amount: Response:
1-11-09 1/2"snow Plow all streets and sand
1-12-09 4" snow Plow all streets and sand
1-14-09 1/2"snow Plow all streets and sand
Engineering
Staff is putting the finishing touches on the Feasibility Reports for the 2009 street
construction season. Feasibility studies should be before Council for acceptance and
ordering of Plans & Specification in February.
Staff is continuing to coordinate with Mendota Mall Associates, LLC on their application for
re -development of the Mendota Mall. Application is scheduled for vote at Council on
January 20tH
Staff has finished editing the new City Stormwater Management and Erosion Control
Ordinance. It has been sent back to our consultant for final version production. The
Ordinance is anticipated to be before Council for adoption in February.
John met with the collaborative committee on the NW Inver Grove Heights and NE Eagan
long-range development & traffic study to discuss the scope of work for the 30 year traffic
study being completed by Dakota County. Of interest in this study is the potential of an
interchange at Interstate 494 and Delaware Avenue. The final scope for the study and
advertisement of the RFP is expected sometime in February 2009.
The cold weather took its toll on our watermain system. The city had two separate breaks
this week. The first one on Wednesday was on Delaware Avenue near Sibley High School
and the second was on Downing Street. St. Paul Water Services identified where the
leaks were occurring and made repairs in sub -zero temperatures.