The Pipeline
September 12, 2014
The Parks Crew installed wood chips in the play areas at Rogers Lake and
Friendly Hills Parks. They repaired the trailer, slit seeder, truck #304, and
the fire boat motor. Hockey boards were painted as needed. A large soccer
field was laid out at Kensington Park. All fields were striped and dragged.
The blacktop was painted at the Friendly Hills Park skating rink.
The Utilities Crew checked the lift stations daily. A sanitary sewer inspection
was done at LCS Metal Stamping on old Highway 13 and at the new home
on Oak Street. An inspection was also done on the Dodd Road storm pipe
that runs from homes to the manhole. Pedways were sprayed for weeds on
the north end. Ivy Falls and Wentworth Parks were sprayed for broadleaf
weeds. The sanitary sewer line was cleaned on Mendota Heights Road and
the lift station cleaned. The Lilydale lift station was also cleaned.
The Streets Crew cut weeds on the west end of the city. A tree was down
on Sylvandale Road and pushed off the street. A dead mink was picked up
on Wagon Wheel Trail. Locates were called in for Beebe Avenue and Dodd
Road for sign installation. A new sign head was installed on John Street and
Chippewa Avenue. Heavy duty "No Parking" signs will be installed on
Warrior Drive. They are helping the sweepers that are sweeping up the seal
coat area. Plow damage repairs were made on Winston Court. Black dirt
and grass was put down.
Engineering
City Projects (construction year)
Highway 13 Trail Connection (20141 - Saint Paul Regional Water Service is
working with the contractor to schedule the lowering of a water main line.
The contractor is ready to start immediately after the water main correction.
Completion is expected by the end of September.
Victoria Road Reconstruction & Rolling Green Neighborhood Rehabilitation
(2014/2015 -Water main replacement on Victoria is complete and the
temporary water service has been removed. Caren Road at Victoria is
closed for the duration of the project. Rehabilitation of the Rolling Green
neighborhood is nearly complete, and the Lilydale portion of the project has
been reclaimed and repaved. Storm sewer installation is complete in the
reconstruction area, and curb and gutter installation is scheduled for next
week. Substantial completion date for this phase of the project is
September 27th. An assessment hearing is anticipated during the October
7th City Council Meeting. Public meetings on the second phase of the project
are expected in November/December of this year.
Wentworth Avenue & Pilot Knob Road Trail Rehabilitation Projects (20141 -
The trails on Wentworth (Wachtler to Dodd) and Pilot Knob Road (I-494 to
Highway 13) will be rehabilitated in conjunction with the Victoria and Rolling
Green Neighborhood project. Tree trimming and removal along the trails is
complete, and construction on the trail is anticipated soon. Temporary
parking restrictions should be anticipated during construction.
Marie Avenue/I-35E Erosion Repairs (2014) - Staff has been working with
MnDOT on a project to repair erosion that has taken place in the northeast
quadrant of the Marie Avenue and I -35E intersection. Construction is set to
begin the week of September 15th, and should last 3-4 weeks.
Kensington Neighborhood Rehabilitation (2015 - City Council authorized
staff to produce a Feasibility Report for the project. Once complete, the
Feasibility Report will be presented to City Council (anticipated for the
October 7th meeting), and they will decide whether or not to proceed with
the project design. The project is being developed at the request of the
Kensington Homeowners Association.
County Projects
Lexington Avenue Sealcoating (2014) - Dakota County will be seal coating
(chip seal) Lexington Avenue from Vail Drive to Mendota Heights Road once
the crosswalk and median construction is complete. This is a preventative
maintenance measure to increase the life of the pavement that was put
down in 2012 as part of the mill and overlay project. Actual construction
time frame has not been established, and there is a possibility this work wil
move to 2015.
North Urban Regional Trail Greenway Realignment (2014/2015) - Dakota
County's contractor will be building the entire trail this fall, including the
section along Warrior Drive and Marie Avenue on Henry Sibley High School
property. Parking on the east side of Warrior Drive has been prohibited
during construction (approximately September 2nd through October 31St)
Parking on the west side of Warrior Drive remains prohibited per City Code.
The contractor has removed the old trail segments and has begun grading
for the new trail location. For more information on the NURT construction
project, please contact the Dakota County Project Manager, Chris Hartzel, at
(952-891-7109, Chris. HartzellC@co.dakota.mn.us).
North Urban Regional Trail Greenway Master Plan - Staff attended a
Technical Advisory Committee (TAC) meeting on Thursday to go over the
early stages of the Master Plan development. Dakota County is looking at
improving the current NURT by adding interpretive signage, adding
vegetation and landscaping. A presentation before the City Council will take
place in November to go over the Master Plan and its goals.
State Projects
Highway 149 (Dodd Road) Reconstruction (I-494 to Highway 55 - Eagan) -
This project is underway, and will reconstruct Dodd Road from the I-494
Interchange to Highway 55 in Eagan. Construction is expected to be
substantially complete by the end of November. Contact the City of Eagan
for more information.
I -35E Guardrail Installation (2014) - MnDOT will be installing new guardrails
along I -35E between Highway 13 and the Marie Avenue bridge. The work is
part of a metro -wide project, and the Highway 13 portion could happen
anytime between August and September of next year. Notice will be given
to the City prior to work beginning. Lane closures and traffic delays should
be expected during off-peak travel times. Installation work is expected to
last less than 2 weeks.
Other Activities
Lower Mississippi River Watershed Management Organization (LMRWMO) -
Staff attended the monthly meeting of the LMRWMO on Wednesday. A
project to repair erosion west of Cherokee Park in Saint Paul was discussed,
as was the ongoing study of Rogers and Augusta Lakes. The next meeting
is scheduled for October 8t" at West Saint Paul City Hall.
Future Cities Competition - Staff is again volunteering at Friendly Hills
Middle School assisting Middle School students with the annual competition.
This year's theme is, 'Feeding a Future City," and will focus on urban and
suburban agricultural services for city population. In addition to the
normally required land use planning, and infrastructure development,
students will have to incorporate the growth and production of one protein
and one vegetable in such a quantity to feed their city population. Between
now and the finals State competition in January, students will model a city
using SimCity software, write an essay and narrative brief about their city,
build a scale model, and make an oral presentation about their city.