August 5, 2014
ling
The Parks Crew dragged the fields, cut grass and striped the soccer fields.
They worked on outfitting the new truck.
The Utilities Crew checked the lift stations daily. The generator was
exercised at the main lift station. A wallet was retrieved from the storm
sewer on Marie Avenue with assistance from the Parks Crew. The right of
way guardrails were sprayed for weeds. Hagstrom King Park and Marie Park
were sprayed for broadleaf weeds. A sanitary sewer service was capped on
Willow Lane.
The Streets Crews trimmed trees on both sides of Delaware Avenue at
Abbey way. They helped the mechanic with the rear tires on dump truck
304. Light bulbs were replaced in the signals at Mendota Heights Road and
Dodd Road. "No U Turn" signs were picked up and installed on Warrior
Drive. "No Parking" signs were reinstalled after they were taken down along
Warrior Drive. A street sign was replaced at Dodd Road and Cheri Lane.
Engineering
City Projects (construction year)
Highway 13 Trail Connection (20141 - Saint Paul Regional Water Service is
scheduled to relocate the water main next week. The contractor is ready to
start immediately after the water main correction. Completion is expected
by the end of September.
Victoria Road Reconstruction & Rolling Green Neighborhood Rehabilitation
(2014/2015 -Water main replacement on Victoria is complete and the
temporary water service has been removed. Caren Road at Victoria is
closed for the duration of the project. Rehabilitation of the Rolling Green
neighborhood is underway, and the Lilydale portion of the project has been
reclaimed and repaved. Storm sewer installation is ongoing in the
reconstruction area, and curb and catch basin repair is underway in the
rehabilitation area. Substantial completion date for this phase of the project
is September 27th. An assessment hearing is anticipated during the October
7th City Council Meeting. Public meetings on the second phase of the project
are expected in November/December of this year.
Wentworth Avenue & Pilot Knob Road Trail Rehabilitation Projects (20141 -
The trails on Wentworth (Wachtler to Dodd) and Pilot Knob Road (I-494 to
Highway 13) will be rehabilitated in conjunction with the Victoria and Rolling
Green Neighborhood project. Tree trimming and removal along the trails is
complete, and construction on the trail is anticipated soon. Temporary
parking restrictions should be anticipated during construction.
Marie Avenue/I-35E Erosion Repairs (2014) - Staff has been working with
MnDOT on a project to repair erosion that has taken place in the northeast
quadrant of the Marie Avenue and I -35E intersection. Staff attended a pre -
construction meeting on Wednesday. Construction is set to begin the week
of September 15th, and should last 3-4 weeks.
Kensington Neighborhood Rehabilitation (2015) - City Council authorized
staff to produce a Feasibility Report for the project. Once complete, the
Feasibility Report will be presented to City Council (anticipated for the
September 16th meeting), and they will decide whether or not to proceed
with the project design. The project is being developed at the request of
the Kensington Homeowners Association.
County Projects
Lexington Avenue Sealcoating (2014) - Dakota County will be seal coating
(chip seal) Lexington Avenue from Vail Drive to Mendota Heights Road once
the crosswalk and median construction is complete. This is a preventative
maintenance measure to increase the life of the pavement that was put
down in 2012 as part of the mill and overlay project. Actual construction
time frame has not been established, and there is a possibility this work will
move to 2015.
North Urban Regional Trail Greenway Realignment (2014/2015) - There has
been a significant schedule change from previous reports on this project.
Dakota County's contractor will be building the entire trail this fall, including
the section along Warrior Drive and Marie Avenue on Henry Sibley High
School property. Parking on the east side of Warrior Drive has been
prohibited during construction (approximately September 2nd through
October 31St). Parking on the west side of Warrior Drive remains prohibited
per City Code. Staff attended an all school assembly on Friday to address
concerns about the project and resident traffic safety concerns around the
school. For more information on the NURT construction project, please
contact the Dakota County Project Manager, Chris Hartzel, at (952-891-
7109, Chris. Hartzell@co.dakota.mn.us).
State Projects
Highway 149 (Dodd Road) Reconstruction (I-494 to Highway 55 - Eagan) -
This project is underway, and will reconstruct Dodd Road from the I-494
Interchange to Highway 55 in Eagan. Construction is expected to be
substantially complete by the end of November. Contact the City of Eagan
for more information.
I -35E Guardrail Installation (2014) - MnDOT will be installing new guardrails
along I -35E between Highway 13 and the Marie Avenue bridge. The work is
part of a metro -wide project, and the Highway 13 portion could happen
anytime between August and September of next year. Notice will be given
to the City prior to work beginning. Lane closures and traffic delays should
be expected during off-peak travel times. Installation work is expected to
last less than 2 weeks.