Mertensotto, Friendly Hills, and Hagstrom King ball fields were graded and
leveled out by the Parks Crew. Grass was cut. The soccer fields were
striped. Accessories were installed on the new truck. All the ball fields were
dragged and groomed.
The lift stations were checked daily by the Utilities Crew. Weeds were
pulled at the Veronica, Centre Pointe, Lilydale and storm lift stations. A
sanitary sewer line inspection was done at 825 Bluebill. The trailer mounted
generator was exercised. Broken hydrant flags were changed out on fire
hydrants though out the city. A broken manhole cover was changed out on
Mears Avenue.
The Streets Crew cut down a tree that was hit by the street sweepers on
Mayfield Heights Road. They helped the mechanic with the parks vehicle.
Storm grates were cleaned. Barricades were dropped off on Stone Road for
a block party. They helped the Parks Crew with stump grinding.
Engineering
City Projects (construction year)
Highway 13 Trail Connection (20141 - Saint Paul Regional Water Service is
scheduled to relocate the water main on September 8th. The contractor is
ready to start immediately after the water main correction. Completion is
expected by the end of September.
Victoria Road Reconstruction & Rolling Green Neighborhood Rehabilitation
(2014/20151 -Water main replacement on Victoria is complete and the
temporary water service has been removed. Construction on the
southbound lane has begun and the intersection of Victoria and Caren Road
is closed for the duration of the project. Rehabilitation of the Rolling Green
neighborhood has begun. The Marie Park skating rink paving was approved
by City Council at their August 19th meeting, and will be completed at the
end of the project. Substantial completion date for this phase of the project
is September 27th. Public meetings on the second phase of the project are
expected in November/December of this year.
Wentworth Avenue & Pilot Knob Road Trail Rehabilitation Projects (2014) --
The trails on Wentworth (Wachtler to Dodd) and Pilot Knob Road (I-494 to
Highway 13) will be rehabilitated in conjunction with the Victoria and Rolling
Green Neighborhood project. Tree trimming and removal along the trails is
complete, and construction on the trail is anticipated later in August.
Temporary parking restrictions should be anticipated during construction.
Marie Avenue/I-35E Erosion Repairs (2014) - Staff has been working with
MnDOT on a project to repair erosion that has taken place in the northeast
quadrant of the Marie Avenue and I -35E intersection. The contract was
awarded at the August 19th City Council Meeting and a pre -construction
meeting is anticipated for early September. Construction should be
complete by October.
Kensington Neighborhood Rehabilitation (2015 - City Council authorized
staff to produce a Feasibility Report for the project. Once complete, the
Feasibility Report will be presented to City Council (anticipated for the
September 16th meeting), and they will decide whether or not to proceed
with the project design. The project is being developed at the request of
the Kensington Homeowners Association.
County Projects
Lexington Crosswalk at Victoria (20141 - This project is complete.
Lexington Avenue Sealcoating (2014) - Dakota County will be seal coating
(chip seal) Lexington Avenue from Vail Drive to Mendota Heights Road once
the crosswalk and median construction is complete. This is a preventative
maintenance measure to increase the life of the pavement that was put
down in 2012 as part of the mill and overlay project. Actual construction
time frame has not been established.
North Urban Regional Trail Greenway Realignment (2014/2015) - There has
been a significant schedule change from previous reports on this project.
Dakota County's contractor will be building the entire trail this fall. Staff
attended a pre -construction meeting on Wednesday where the schedule was
discussed. The new trail along the east side of Warrior Drive and the south
side of Marie Avenue will be constructed in September and
October. Temporary parking restriction along both Warrior and Marie are
anticipated during construction. Staff will be discussing this matter with the
contractor and the school district next week. For more information, please
contact the Dakota County Project Manager, Chris Hartzel, at (952-891-
7109, Chris. Hartzell@co.dakota.mn.us) .
State Projects
Highway 149 (Dodd Road) Reconstruction (I-494 to Highway 55 - Eagan) -
This project is underway, and will reconstruct Dodd Road from the I-494
Interchange to Highway 55 in Eagan. Construction is expected to be
substantially complete by the end of November. Contact the City of Eagan
for more information.
I -35E Guardrail Installation (2014) - MnDOT will be installing new guardrails
along I -35E between Highway 13 and the Marie Avenue bridge. The work is
part of a metro -wide project, and the Highway 13 portion could happen
anytime between August and September of next year. Notice will be given
to the City prior to work beginning. Lane closures and traffic delays should
be expected during off-peak travel times. Installation work is expected to
last less than 2 weeks.