Pipeline 03 28 2014NEWS
LETTER
Public Works =
Engineering
Code Enforcement
Public Works
The Pipeline
March 28, 2014
The Parks Crew did daily trash pickup and daily check of the aerator at
Rogers Lake. They transported the reel and rotary mower from Par 3 to
public works for servicing. The trucks were washed. Truck 501 was taken
in for some repairs. The snow plow was repaired on truck 503.
The Streets Crew filled potholes. Mailboxes repair work is starting. Salt
was pushed up in the storage bin.
Engineering
City Projects (construction year)
Hunter Lane/Orchard Place Neighborhood Improvements (20131 -The
project is considered substantially complete and the final lift of wear course
asphalt will be placed in the spring.
Highway 13 Trail Connection (2014)-- Construction will not begin until the
spring. A utility conflict with Saint Paul Regional Water Service needs to be
resolved prior to construction. Staff will hold a coordination meeting with
Saint Paul Regional Water Service and the contractor in the coming weeks.
Victoria Road Reconstruction & Rolling Green Neighborhood Rehabilitation
(2014/2015 - The consultant is working on the design plans and
specifications for the first phase of construction. The first phase will
reconstruct Victoria from Lilydale to Marie Avenue and rehabilitate the
Stratford/Walsh/ Rolling Green neighborhood. The remainder of Victoria was
put off to a future date, but it is anticipated for construction in 2015. The
Lilydale portion of Victoria from Caren Road to Highway 13 is included. Staff
is reviewing an 80% complete plan set and will provide comments and
revisions to the consultant. A neighborhood meeting will be held in early
April to go over specific issues and concerns with individual property
owners. A notice letter will go out 1-2 weeks ahead of the meeting.
Wentworth Avenue & Pilot Knob Road Trail Rehabilitation Projects (20141 -
The trails on Wentworth (Wachtler to Dodd) and Pilot Knob Road (Mendota
Heights Road to Highway 13) are scheduled for rehabilitation in the coming
year. Projects will reclaim the existing pavement and install ADA compliant
ramps along each trail. Construction is anticipated in June/July.
County Projects
Delaware Avenue Resurfacing (20141 - Dakota County is planning on
resurfacing Delaware Avenue from Highway 110 south to I-494. This
project will not alter the lane alignment of Delaware, but will provide a new
asphalt driving surface and new striping. Construction is anticipated to
begin in late June.
Lexington Crosswalk at Victoria (20141 - The median and crosswalk are
scheduled for installation this summer. This project will install a center
median in Lexington on the north side of the Victoria intersection and
provide for a crosswalk to connect the trails on the east and west of
Lexington. The left turn lane from southbound Lexington to eastbound
Victoria will be removed as part of this project. A JPA with Dakota County
for the project will be presented to City Council at their April 1St meeting.
State Proiects
Highway 110 & Lexington Avenue Signal Replacement (2014) - The existing
signal will be replaced this summer with a new LED signal with flashing
yellow arrow for the left turn lanes on Lexington.
I 35E & Marie Avenue Drainage and Erosion Control Improvements (20141 -
Storm Water Runoff at the northeast corner of I -35E and Marie Avenue has
caused erosion that has exposed utility pipes and conduits. Since a portion
of the runoff comes from the Interstate right-of-way, MnDOT has taken the
lead in designing a solution. MnDOT has asked that the City administer the
construction contract for the improvement, and a Cooperative Construction
Agreement will be presented to City Council for approval at their April 1St
meeting. The City and MnDOT completed a similar project in 1994, and the
terms of the agreement are proposed to mimic the original agreement.
Highway 13 Reconstruction (2015) - The section of Highway 13 that was
not rehabilitated in 2012 is scheduled for reconstruction in 2015. This
section is from I -35E south and west to 2nd Street in Mendota. This section
will receive a widened shoulder, curb, gutter, and storm sewer to help
alleviate drainage and erosion problems in Lilydale.
Highway 149 (Dodd Road) Resurfacing (20171 - Dodd Road is scheduled to
be resurfaced from Highway 55 in Eagan to Annapolis Street in 2017. At
this time, there are no plans to widen the State Highway, but some
alterations for drainage and public safety are possible. Originally scheduled
for 2015, the project was delayed to coincide with the Highway 110
rehabilitation project. Due to the project delay, Dodd Road will receive
another sealcoat (chip seal) in 2014.
Highway 110 Resurfacing (2017) - Preliminary project scoping has begun.
This project will not reconstruct or alter the alignment of the state highway,
but modifications to access points, traffic signals, shoulders, drainage, and
pedestrian facilities are likely.