March 14, 2014
The Parks Crew did their daily trash pickup. The warming houses were
cleaned out and the gas shut off. Broken shovels were repaired as needed.
The hockey goals were taken off the rinks and put in storage. The flooding
hoses and hydrant fittings were also removed and stored. Truck 503 was
serviced. They assisted the Fire Department in returning hoses to the fire
hall after the house fire on the Highway 110 Frontage Road.
The Utilities Crew checked the lift stations daily. Both generators were
exercised. After a resident's concern, the storm sewer was looked at on
Fieldstone Drive and it was flowing fine. There was a possible sewer backup
on Highway 13 and a problem was found in the homeowner's service. Root
killer was added to the Marie Avenue sanitary sewer line.
The Streets Crew opened catch basins throughout the city. Blacktop
material was picked up and potholes were filled. A crime watch sign was
installed in the Evergreen Knoll neighborhood. They helped a resident with
removing snow and mud from the front yard that was left there from
cleaning a catch basin.
Engineering
City Projects (construction year)
Hunter Lane/Orchard Place Neighborhood Improvements (2013 -The
project is considered substantially complete and the final lift of wear course
asphalt will be placed in the spring.
Highway 13 Trail Connection (2014)_- Construction will not begin until the
spring. A utility conflict with Saint Paul Regional Water Service needs to be
resolved prior to construction.
Victoria Road Reconstruction & Rolling Green Neighborhood Rehabilitation
(2014/20151 - The consultant is working on the design plans and
specifications for the first phase of construction, and the City anticipates
bidding the project in the April/May timeframe. The first phase will
reconstruct Victoria from Lilydale to Marie Avenue and rehabilitate the
Stratford/Walsh/ Rolling Green neighborhood. The remainder of Victoria was
put off to a future date, but it is anticipated for construction in 2015. The
Lilydale portion of Victoria from Caren Road to Highway 13 will be included.
Wentworth Avenue & Pilot Knob Road Trail Rehabilitation Projects (20141 -
The trails on Wentworth (Wachtler to Dodd) and Pilot Knob Road (Mendota
Heights Road to Highway 13) are scheduled for rehabilitation in the coming
year. Projects will reclaim the existing pavement and install ADA compliant
ramps along each trail. Construction is anticipated in June/July. A Joint
Powers Agreement with Dakota County will be on the March 18th City
Council Agenda.
County Projects
Delaware Avenue Resurfacing (20141 - Dakota County is planning on
resurfacing Delaware Avenue from Highway 110 south to I-494. This
project will not widen or otherwise alter the lane alignment of Delaware, but
will provide a new asphalt driving surface and new striping. Construction is
anticipated to begin in late June.
Lexington Crosswalk at Victoria (20141 - The median and crosswalk are
scheduled for installation this summer. This project will install a center
median in Lexington on the north side of the Victoria intersection and
provide for a crosswalk to connect the trails on the east and west of
Lexington. The left turn lane from southbound Lexington to eastbound
Victoria will be removed as part of this project.
State Proiects
Highway 110 & Lexington Avenue Signal Replacement (2014) - The existing
signal will be replaced this summer with a new LED signal with flashing
yellow arrow for the left turn lanes on Lexington.
Highway 13 Reconstruction (2015) - The section of Highway 13 that was
not rehabilitated in 2012 is scheduled for reconstruction in 2015. This
section is from I -35E south and west to 2nd Street in Mendota. This section
will receive a widened shoulder, curb, gutter, and storm sewer to help
alleviate drainage and erosion problems in Lilydale.
Highway 149 (Dodd Road) Resurfacing (20171 - Dodd Road is scheduled to
be resurfaced from Highway 55 in Eagan to Annapolis Street in 2017. At
this time, there are no plans to widen the State Highway, but some
alterations for drainage and public safety are possible. Originally scheduled
for 2015, the project was delayed to coincide with the Highway 110
rehabilitation project. Due to the project delay, Dodd Road will receive
another sealcoat (chip seal) in 2014.
Highway 110 Resurfacing (2017) - Preliminary project scoping has begun.
This project will not reconstruct or alter the alignment of the state highway,
but modifications to access points, traffic signals, shoulders, drainage, and
pedestrian facilities are likely.
Other Activities
Lower Mississippi River Watershed Management Organization (LMRWMO) -
Staff attended the monthly meeting of the LMRWMO board. The LMRWMO is
making progress in updating the Watershed Management Plan and
developing a new Joint Powers Agreement for the member Cities to
incorporate the portion of Mendota Heights that used to be part of the now
dissolved Gun Club Lake Watershed Management Organization. The
LMRWMO is also working on an erosion control repair in Cherokee Park (City
of Saint Paul) that involves storm water drainage from Mendota Heights and
West Saint Paul.
MN2050 - Staff attended a meeting of the MN2050 organization on Friday.
The organization is working with Twin Cities Public Television on producing a
series of documentaries on the state of Minnesota's infrastructure. A 2
minute trailer for the upcoming Road and Bridge documentary, as well as an
abridged version of the water and wastewater documentary can be seen on
the MN2050 website at www.mn205O.ora.