The Pipeline
February 7, 2014
The Parks Crew continue to snow blow the trails throughout the City. Truck
503 was taken to Mauer Chevrolet for a recall. They continue flooding the
ice rinks as needed. Truck 501 was taken to Kremer Spring for a problem
with the steering. The trucks were cleaned.
The Utilities Crew checked the lift stations. The check valves were rebuilt at
the Mendota Heights Road lift station. Pump one check valve had a large
rag stuck in it. Pump two check valve's gasket was torn apart. The utilities
trucks were washed.
The Streets Crew helped repair the hydraulic ram on truck 304. Bridge
decks on Wagon Wheel Trail, Mendota Heights Road, and Acacia Boulevard
were cleared of snow. Salt and sand were mixed with the cat loader. Fire
hydrants were cleaned of snow in the business park. Snow piles on the
boulevards were pushed back. Wear shoes were fabricated for the snow
blower on the bobcat and a new cutting edge was installed.
Engineering
City Projects (construction year)
Hunter Lane/Orchard Place Neighborhood Improvements (20131 -The
project is considered substantially complete and the final lift of wear course
asphalt will be placed in the spring.
Crown Point & Overlook Neighborhood Rehabilitations (2013) - The
contractor will need to finish the final punch -list items in the spring.
Highway 13 Trail Connection (2014) --Construction will not begin until the
spring. A utility conflict with Saint Paul Regional Water Service needs to be
resolved prior to construction.
Victoria Road Reconstruction & Rolling Green Neighborhood Rehabilitation
(2014/2015 - The consultant is working on the design plans and
specifications, and the City anticipates bidding the project in the April/May
timeframe. The project will be constructed in phases. The first phase,
scheduled for 2014, will reconstruct Victoria from Lilydale to Marie Avenue
and rehabilitate the Stratford/Walsh/ Rolling Green neighborhood. The
remainder of Victoria was put off to a future date, but it is anticipated for
construction in 2015. The City of Lilydale has asked that the portion of
Victoria from Caren Road to Highway 13 be included at Lilydale's expense.
Wentworth Avenue & Pilot Knob Road Trail Rehabilitation Projects (20141 -
The trails on Wentworth (Wachtler to Dodd) and Pilot Knob Road (Mendota
Heights Road to Highway 13) are scheduled for rehabilitation in the coming
year. Projects will reclaim the existing pavement and install ADA compliant
ramps along each trail. Construction is anticipated in June/July.
County Projects
Delaware Avenue Resurfacing (20141 - Dakota County is planning on
resurfacing Delaware Avenue from Highway 110 south to I-494. This
project will not widen or otherwise alter the lane alignment of Delaware, but
will provide a new asphalt driving surface and new striping. Construction is
anticipated to begin in late June.
Lexington Crosswalk at Victoria (20141 - The median and crosswalk are
scheduled for installation this summer. Construction will likely take place in
conjunction with the Delaware Avenue Resurfacing project. This project will
install a center median in Lexington on the north side of the Victoria
intersection and provide for a crosswalk to connect the trails on the east and
west of Lexington. The left turn lane from southbound Lexington to
eastbound Victoria will be removed as part of this project.
State Proiects
Highway 110 & Lexington Avenue Signal Replacement (2014) - The existing
signal will be replaced this summer with a new LED signal with flashing
yellow arrow for the left turn lanes on Lexington.
Highway 13 Reconstruction (2015) - The section of Highway 13 that was
not rehabilitated in 2012 is scheduled for reconstruction in 2015. This
section is from I -35E south and west to 2nd Street in Mendota. This section
will receive a widened shoulder, curb, gutter, and storm sewer to help
alleviate drainage and erosion problems in Lilydale.
Highway 149 (Dodd Road) Resurfacing (20171 - Dodd Road is scheduled to
be resurfaced from Highway 55 in Eagan to Annapolis Street in 2015. At
this time, there are no plans to widen the State Highway, but some
alterations for drainage and public safety are possible. The project may be
delayed until 2017 to be constructed in conjunction with the Highway 110
resurfacing project. Due to the project delay, Dodd Road will receive
another sealcoat (chip seal) in 2014.
Highway 110 Resurfacing (2017) - Preliminary project scoping has begun.
This project will not reconstruct or alter the alignment of the state highway,
but modifications to access points, traffic signals, shoulders, drainage, and
pedestrian facilities are likely.