Pipeline 11 15 2013NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
November 15, 2013
The Parks Crew mulched leaves in the parks as needed. Mendakota Park,
the fire hall, city hall and all neighborhood ball fields were fertilized. Trucks
501 & 503 were serviced and prepared for the winter plowing season. A
new tool box was installed on truck 501.
The Utilities Crew mulched and mowed the grass and leaves at the Veronica
lift station. The sanitary sewer lines were flushed along Lexington Avenue
and Tom Thumb Boulevard to Wagon Wheel Trail. The standby generator
was exercised at the Mendota Heights Road lift station and the trailer mount
generator was also exercised.
The Streets Crew trimmed trees along the sidewalks in the Pondhaven and
Copperfield neighborhoods. The blacktopping equipment was winterized.
Engineering
City Projects (construction year)
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013) -
The contractor is working on the punch -list items, and signal completion will
take place upon delivery of parts from MnDOT. New luminaires have been
installed at the NE corner.
Hunter Lane/Orchard Place Neighborhood Improvements (20131 -The
project is considered substantially complete and the final lift of wear course
asphalt will be placed in the spring. Assessment amounts not paid off by
November 1St have been certified to the County and payable through annual
property tax statements.
Crown Point & Overlook Neighborhood Rehabilitations (2013) - The
contractor is finishing the final punch -list items. Assessed property owners
can pay their assessment off partially or in -full at City Hall up until
November 18th. After that the remaining assessed amount will be certified
to the County and payable through annual property tax statements.
Sanitary Sewer Cleaning and Televising (2013 - This project is
substantially complete. Staff will review the data when the report is received
from the contractor.
Sanitary Sewer Lining (2013 -This project will install a liner in place on
sections of sanitary sewer main that have been identified as having multiple
root penetrations. All lining activities this year will be on the north end of
the City. Minor traffic impacts should be anticipated while the contractor
accesses manholes. Lining is expected to add up to 25 years to the life of
the sanitary sewer main.
Mendota Heights Road Sanitary Sewer Force Main Replacement (2013) -
The main directional drilling is complete. The contractor is in the process of
jacking a pipe under Highway 55 next week and begin manhole
construction. Project should be substantially complete in a week.
Highway 13 Trail Connection (20131 - The contractor is ready to mobilize
for construction. As soon as MnDOT State Aid office gives the City
permission, a notice -to -proceed will be given to the contractor. A utility
conflict with Saint Paul Regional Water Service needs to be resolved in
conjunction with the construction. Anticipated completion of the trail will be
later this fall. Pavement of the trail may be delayed until the spring
depending on the contractor's schedule.
Rolling Green Neighborhood Rehabilitation & Victoria Road Reconstruction
2014? - An informal neighborhood meeting was held on October 23rd at
City Hall. Over 40 area residents attended the meeting and offered
comments, suggestions, and asked questions about the project. A public
hearing was held at the November 5th City Council Meeting. The public
hearing was held over until the November 19th Council meeting.