Pipeline 11 08 2013NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
November 8, 2013
The Parks Crew are mulching leaves in the parks. Trash barrels were
brought to the Halloween bonfire site and picked up the next day. Portable
satellites were also moved to the Halloween bonfire site. The other
satellites were picked up from the parks. The soccer fields at Kensington
Park South and field one at Mendakota Park were top dressed. Truck 501
was serviced; new tires were installed and it was prepared for the winter
season.
The Utilities Crew checked the lift stations daily. The impellers and brass
wear rings were changed on the pumps at the Northland lift station. New
fire hydrant flags were installed in the Hunter and Orchard area. The
manholes were inspected where Lametti installed new pipes in the sewer
relining area. Marking flags were installed at city hall and at the Veronica
lift station for plowing. The alarm went off at the main lift station on
Monday at 6:00 pm for high water.
The Streets Crew hauled away the ashes from the bonfire site to SKB
Landfill and then cleaned up the site. The plow wings and sanders were
installed on all plow trucks and checked over. A couch was picked up from
the street on First Avenue and Medora Road. A keep back 75' sign was
made for the city of South Saint Paul. The hot box was taken off truck 303.
Engineering
City Projects (construction year)
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013) -
The contractor is working on the punch -list items, and signal completion will
take place upon delivery of parts from MnDOT. New luminaires have been
installed at the NE corner.
Hunter Lane/Orchard Place Neighborhood Improvements (20131 -The
project is considered substantially complete and the final lift of wear course
asphalt will be placed in the spring. Assessment amounts not paid off by
November 1St will be certified to the County and payable through annual
property tax statements.
Crown Point & Overlook Neighborhood Rehabilitations (2013) - The
contractor is finishing the final punch -list items. Assessed property owners
can pay their assessment off partially or in -full at City Hall up until
November 15th. After that the remaining assessed amount will be certified
to the County and payable through annual property tax statements.
Sanitary Sewer Cleaning and Televising (20131 - This project is
substantially complete. Staff will review the data when the report is received
from the contractor.
Sanitary Sewer Lining (2013 -This project will install a liner in place on
sections of sanitary sewer main that have been identified as having multiple
root penetrations. All lining activities this year will be on the north end of
the City. Minor traffic impacts should be anticipated while the contractor
accesses manholes. Lining is expected to add up to 25 years to the life of
the sanitary sewer main.
Mendota Heights Road Sanitary Sewer Force Main Replacement (2013) -
The main directional drilling is complete. The contractor is in the process of
jacking a pipe under Highway 55 next week and begin manhole
construction. Project should be substantially complete in a couple weeks.
Highway 13 Trail Connection (20131 - The contractor is ready to mobilize
for construction. As soon as MnDOT State Aid office gives the City
permission, a notice -to -proceed will be given to the contractor. A utility
conflict with Saint Paul Regional Water Service needs to be resolved in
conjunction with the construction. Anticipated completion of the trail will be
later this fall. Pavement of the trail may be delayed until the spring
depending on the contractor's schedule.
Rolling Green Neighborhood Rehabilitation & Victoria Road Reconstruction
2014? - An informal neighborhood meeting was held on October 23rd at
City Hall. Over 40 area residents attended the meeting and offered
comments, suggestions, and asked questions about the project. A public
hearing was held at the November 5th City Council Meeting. The public
hearing was held over until the November 19th Council meeting.