The Pipeline
November 1, 2013
The Parks Crew replaced the aerator tines on the pull behind aerator. Truck 301
was taken to Kremer Spring for repairs. The fertilizer spreader was installed on
the tractor. The soccer fields at Kensington Park South were fertilized and
prepared for top dressing next week.
The Utilities Crew checked the lift station daily. A rock and rag were stuck in the
pump impellor at the St. Thomas lift station. The pump was pulled out of the wet
well and cleaned up. Trees were trimmed at the Northland lift station. Sanitary
sewer lines were cleaned along Celia Street. Big pieces of minerals were cut out of
this area due to ground water infiltration. A catch basin on Arcadia Drive was
cleaned out of rocks and mud.
The Streets Crew pushed up the bonfire materials every day. Storm basins in
need of repair were fixed on Huber Drive, Hampshire Drive and Medallion Drive.
Where storm basin repairs were made on Maple Park Drive they patched, graded
and blacked topped the area. They also filled in the area behind the curb with dirt
and grass seed. Tree stumps were grinded and the area filled with black dirt in
the Valley Curve area, Walsh Lane and Kirchner Avenue. In the alley way by
Hiawatha Avenue and Freemont Avenue class 5 was put down in low spots, leveled
off with the bobcat and compacted with the roller.
Engineering
City Projects (construction year)
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013 - The
contractor is working on the punch -list items, and signal and lighting completion
will take place upon delivery of parts from MnDOT.
Hunter Lane/Orchard Place Neighborhood Improvements (2013) -The project is
considered substantially complete, and the final lift of wear course asphalt will be
placed in the spring. Assessed property owners can pay their assessment off
partially or in -full at City Hall up until November 1st. After that the remaining
assessed amount will be certified to the County and payable through annual
property tax statements.
Crown Point & Overlook Neighborhood Rehabilitations (2013) - The contractor is
finishing the final punch -list items. Assessed property owners can pay their
assessment off partially or in -full at City Hall up until November 15th. After that
the remaining assessed amount will be certified to the County and payable
through annual property tax statements.
Sanitary Sewer Cleaning and Televising (2013) - This project is substantially
complete. Staff will review the data when the report is received from the
contractor.
Sanitary Sewer Lining (2013) -This project will install a liner in place on sections
of sanitary sewer main that have been identified as having multiple root
penetrations. All lining activities this year will be on the north end of the City.
Minor traffic impacts should be anticipated while the contractor accesses
manholes. Lining is expected to add up to 25 years to the life of the sanitary
sewer main.
Mendota Heights Road Sanitary Sewer Force Main Replacement (2013) - The main
directional drilling is complete. The contractor will be jacking a pipe under
Highway 55 next week and begin manhole construction. Project should be
substantially complete in a couple weeks.
Highway 13 Trail Connection (2013) - The contractor is ready to mobilize for
construction. As soon as MnDOT State Aid office gives the City permission, a
notice -to -proceed will be given to the contractor. A utility conflict with Saint Paul
Regional Water Service needs to be resolved in conjunction with the construction.
Anticipated completion of the trail will be later this fall. Pavement of the trail may
be delayed until the spring depending on the contractor's schedule
Rolling Green Neighborhood Rehabilitation & Victoria Road Reconstruction (2014?)
- An informal neighborhood meeting was held on October 23rd at City Hall. Over
40 area residents attended the meeting and offered comments, suggestions, and
asked questions about the project. The public hearing before City Council is
scheduled for November 5th (note: Council meeting will begin at 8:OOpm due to
School District elections). Issues, concerns, and questions brought up in the
neighborhood meeting will be forwarded to Council for the public hearing. Due to
the size of the project Council may direct construction over multiple years. This
tn
will be discussed at the Public Hearing on November 5