Pipeline 09 13 2013N E W S The Pipeline
LETTER
Public Works
u
Engineering September 13, 2013
Code Enforcement
Public Works
The Parks Crew made repairs to the sprinkler system at Mendakota Park.
The water fountain at Kensington South Park was installed. Hanging tree
limbs at Friendly Hills Park along the pedway were trimmed. Fallen tree
limbs were picked up at Ivy Hills Park.
The Utilities Crew had a pre -meeting with the sewer televising contractor.
He also attended a pre -construction meeting with Northdale construction for
the Veronica lift station rehabilitation. He finished spraying total weed killer
along the fence lines as needed in all parks.
The Streets Crew finished up blacktop patching on Decorah Lane, Pagel
Road and Havenview Court. The beaver dam in the storm outlet off Pond
Circle was dug out. The storm pipe was jetted out because of heavy mud.
The storm outlet that goes under the pedway was cleaned out at Hagstrom
King Park. Three cottonwood trees were cut down that were growing next
the storm outlet. Trees were cleaned up along the pond that were dead.
The debris was taken to S & S Tree in South Saint Paul. Fabricating and
welding was done for the police department's new sergeant's car.
Engineering
City Projects (construction year)
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013) -
Construction is underway. Concrete work is nearly complete. The base of
the trail is in place and paving should be completed this week. Traffic
impacts are greater than anticipated, but detours are available to the north
along Marie Avenue, or to the south along Mendota Heights Road. Police
are monitoring detour routes for speed compliance. Substantial completion
of the project is expected early next week.
Hunter Lane/Orchard Place Neighborhood Improvements (20131 - Utility
installation is substantially complete. Base course of pavement has been
placed on Orchard, Culligan, and Glenhill. Curb and gutter installation along
Hunter is expected in the next week, followed by road base grading.
Pavement of Hunter can be expected in approximately one to two weeks.
The contractor has replaced the culvert under Lexington Avenue and paved
the patch site. Substantial completion is expected by the end of September
with the assessment hearing scheduled for the October 2nd City Council
Meeting. For more information, please see the project page on the city web
page: www.mendota-heights.com. Project information is updated weekly.
Crown Point & Overlook Neighborhood Rehabilitations (2013) - This project
is substantially complete. Staff has prepared the project punch -list, and the
contractor will be repairing the punch list items during the remaining
construction season. An assessment hearing is scheduled for the October
15th City Council meeting.
Lexington Avenue Pedestrian Trail, Hwy 110 to Douglas Road (2013) - New
sod was placed on the northern portion of the trail to repair damage done
during construction. The trail is open for use.
Sanitary Sewer Cleaning and Televising (2013 - This project is underway.
The contractor is working in the area of the city west of I -35E and north of
Highway 110. Center Pointe Business Park is also included in the project.
Minor traffic impacts should be anticipated.
Mendota Heights Road Sanitary Sewer Force Main Replacement (2013) -
Design of the replacement force main is complete and the authorization to
bid the project is scheduled for the September 17th City Council meeting.
The force main has broken 5 times in the past 6 years and is in need of
replacement. Construction could begin as early as this fall.
Highway 13 Trail Connection (20131 - City Council awarded the project to
Urban Companies of Vadnais Heights at their September 3rd meeting. City
Staff is working with adjacent property owners on acquiring the necessary
easements for the project. Easement acceptance is scheduled for the
September 17th City Council Meeting. Notice to proceed with construction is
anticipated in mid-September and the project should be completed within a
few weeks from the start date. Construction is expected to begin in late
September/early October.
County Projects (Construction Year)
Delaware Avenue Guardrails (2013) - Installation of guardrails on Delaware
Avenue in selected locations between Highway 110 and I-494 will begin
later this month. Plans have been completed and are under inter -agency
review. Construction is expected within the coming weeks.
North Urban Regional Trail (NURT) Realignment/Greenway Corridor -
County staff is progressing on the design of the trail realignment through
the Henry Sibley property. The County Project Manager will be giving an
update to the Parks and Recreation Commission on October 81h and to the
City Council on October 15th. The City of West Saint Paul is planning on
reconstructing Marie Avenue from Delaware to Charlton in conjunction with
the NURT realignment construction in 2014.
Other Activities
Lower Mississippi River Watershed Management District (LMRWMO� - Staff
attended the monthly WMO Board meeting on Wednesday in South Saint
Paul. The WMO provided an update on the Watershed Restoration and
Protection (WRAP) plan being developed for Rogers Lake and Lake Augusta
in Mendota Heights, along with Pickerel Lake in Lilydale, Thompson Lake in
West Saint Paul, and for Sunfish Lake. These lakes and surrounding
watersheds are being studied to provide the City and area residents with
practices that can improve the overall water quality in the water bodies.
The final report is expected to be published over the winter. For more
information contact City Engineering staff.