Pipeline 08 02 2013N E W S The Pipeline
LETT E R iiii�
Public Works ■t�'
Engineering -- August 2, 2013
Code Enforcement
Public Works
The Parks Crew aerated the soccer fields at Kensington Park South and all
neighborhood baseball fields. Grass seed was put down on the soccer fields
at Kensington Park South along with the Mendakota Park soccer field, and
Hagstrom King baseball fields. Dead shrubs were replaced around park
signs. Bases were moved back to their normal lengths after the weekend
tournament. Rec rock was put down and leveled around fields one and two
at Mendakota Park. Black dirt was put down and is being prepared for grass
seed around the water tower.
The Utilities Crew cleaned sanitary sewer lines along Vicki Lane, Overlook
Road, Douglas Road, and Lilac Lane. A piece of jewelry was found in the
line and is being held at City Hall. Call 651-452-1850 to claim. Weeds were
sprayed with weed killer that are growing in the cracks on all pedways.
The Streets Crew helped rebuild the wear bar on the field dragger. They
helped install the strobe light on the engineering truck. Three brush piles
were cleaned up on Keokuk Lane and Pagel Road. A low spot along Kendon
Lane was filled in and erosion control was installed and the bank seeded.
Seal coating chips were hauled to the staging area after being swept up.
Engineering
City Projects (construction year)
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013) -
Construction is scheduled to begin Monday, and is scheduled for completion
by September 3rd. A portion of Interstate Valley Creek Trail northwest of
the intersection will be relocated as part of the contract.
Hunter Lane/Orchard Place Neighborhood Improvements (20131 - Curbing
has been installed on Orchard Place through the curve to Hunter Lane, and
the base material has been placed and compacted. Utility construction on
Hunter has begun. Paving activity is expected to begin on Orchard in the
coming weeks. A stockpile of material has been placed on Glenhill Road at
Victoria, so residents accustomed to using this access are asked to use
Culligan Lane off Hunter temporarily. Rehabilitation work on Veronica,
Orchard Circle, Culligan, and Glenhill is expected in the coming weeks.
Substantial completion is expected by the end of September with the
assessment hearing in October.
Crown Point & Overlook Neighborhood Rehabilitations (2013) - This project
is substantially complete. Staff has been preparing the project punch -list,
and the contractor will be repairing the punch list items in August. An
assessment hearing is scheduled for October.
Lexington Avenue Pedestrian Trail, Hwy 110 to Douglas Road (20131 - The
trail has been re -paved, and pedestrian ramps installed. Punch -list items
remain along with some minor landscape restoration. The trail has been re-
opened.
Sanitary Sewer Cleaning and Televising (20131 - This project is underway.
The contractor will be working in the area of the city west of I -35E and
north of Highway 110. Center Pointe Business Park is also included in the
project. Minor traffic impacts should be anticipated. During this week's
cleaning, an item of jewelry was found in the sanitary sewer and is being
saved at City Hall. Call the Engineering Department at 651-452-1850 if you
are missing an item and can describe what was found.
Mendota Heights Road Sanitary Sewer Force Main Replacement (2013) -
The design contract was awarded at the City Council's July 16th meeting.
Design is anticipated to be complete and ready for bid by October/
November. This force main has broken 5 times in the past 6 years and is in
need of replacement. Construction of the replacement could begin as early
as this fall.
Highway 13 Trail Connection (20131 - The City did not receive the DNR
grant money we had applied for, but the City will be moving forward with
this trail construction this summer anyway. The trail will connect Riverside
Lane to Lilydale Road along the south side of Highway 13. Authorization to
bid the project is scheduled for the August 6th City Council Meeting.
Construction is expected in October.
County Projects (construction year)
Lexington Avenue Crosswalk (2013) - The crosswalk and island at the
Victoria/ Lexington intersection is scheduled for installation in August.
Surveyors have marked the area and utilities have been located. Specific
schedules will be posted as they are planned.
Delaware Avenue Guardrails (2013) - Guardrails along both sides of
Delaware Avenue, between Highway 110 and Interstate 494 will be installed
this summer. Design of the guardrails has been completed. County
maintenance crews will be doing the installation and they are scheduled for
installation in August.
Other Activities
Lower Mississippi River Watershed Management Organization
(LMRWMO) - Staff attended the monthly meeting on Thursday. The 2014
budget was approved, and a consultant contract was approved for studying
PAH contamination in Thompson Lake in West Saint Paul. The LMRWMO
board also discussed Mendota Heights' request to remove themselves from
the Gun Club Lake WMO and join completely with the LMRWMO.