Public Works
The Parks Crew cut up a tree on the pedway in Valley Park and trimmed
overhanging limbs along the trail. Sprinkler lines were repaired at
Mendakota Park and Kensington Park. They cleaned up Mendakota Park
after the weekend tournament. Dirt was put down around the new cement
pad at Friendly Hills Park and for the donated bench at Huber Drive and
Cheyenne Lane.
The Utilities Crew cleaned sanitary sewer lines along Stratford Road,
Coventry Court, Walsh Lane, Oxford Court, Rolling Green Curve and the
Burow Pond easement. He fixed an irrigation pipe at Mendakota Park. The
Victoria Road fire hydrants were painted.
The Streets Crew did blacktop patching on Rolling Green Curve, Windwood
Court, Oxford Court and Walsh Lane. The trimmed trees because of sight
distance problems at Mendota Heights Road and Delaware Avenue, Huber
Drive and Delaware Avenue, and at Marie Avenue and Victoria Road. The
storm outlet was dug out on Victoria Curve, debris and mud was cleaned
out. The sinkhole was cut out on Ridgewood Drive and Marie Avenue, fixed
and blacktopped.
Engineering
City Projects (construction year)
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013 -
Construction is anticipated to begin on or about August ist, and is scheduled for
completion by September 3rd. A portion of Interstate Valley Creek Trail northwest
of the intersection will be relocated as part of the contract.
Hunter Lane/Orchard Place Neighborhood Improvements (2013) -The contractor
reclaimed the bituminous on the remaining streets in the project. Storm sewer
and water main for phase one has been completed. The contractor is placing
gravel in anticipation for the curb installation on Tuesday July 22nd. On Monday
July 21st the contractor will begin installing water main in the phase 2 portion of
the project. Substantial completion is expected by the end of September with the
assessment hearing in October.
In
Crown Point & Overlook Neighborhood Rehabilitations (20131 - This project is
substantially complete. Staff will develop a punch list in the coming weeks, and
the contractor will be repairing the punch list items in August. An assessment
hearing is scheduled for October.
Lexington Avenue Pedestrian Trail, Hwy 110 to Douglas Road (2013) - The trail
has been re -paved, and pedestrian ramps installed. Punch -list items remain along
with some minor landscape restoration. The trail has been re -opened.
Sanitary Sewer Cleaning and Televising (2013) -Work is anticipated to begin next
week. The contractor will be working in the area of the city west of I -35E and
north of Highway 110. Center Pointe Business Park is also included in the
project. Minor traffic impacts should be anticipated.
Mendota Heights Road Sanitary Sewer Force Main Replacement (2013 - City
Council awarded the the project to Bolton & Menk, Inc. at their July 16th
meeting. This force main has broken 5 times in the past 6 years and is in need of
replacement. Construction of the replacement could begin as early as this fall.
Highway 13 Trail Connection (2013) - The City did not receive the DNR grant
money we had applied for, but the City will be moving forward with this trail
construction this summer anyway. The trail will connect Riverside Lane to Lilydale
Road along the south side of Highway 13. Construction is expected in September.
County Projects (construction year)
Lexington Avenue Crosswalk (2013) - The crosswalk and island at the Victoria/
Lexington intersection is scheduled for installation in August. Surveyors have
marked the area and utilities have been located. Specific schedules will be posted
as they are planned.
Delaware Avenue Guardrails (2013) - Guardrails along both sides of Delaware
Avenue, between Highway 110 and Interstate 494 will be installed this
summer. County maintenance crews will be doing the installation and they are
scheduled for installation in July/August.
Dakota County Greenways Initiative - Dakota County is working on a County -wide
greenway initiative to provide trail routes throughout the County that are
separated from roadways. Details about the Initiative can be found
at: http://www.hkgi.com/projects/dakota/