Pipeline 06 21 2013N E W S The Pipeline ,,,
LETTER
Public Works June 21, 2013 sw"W�
Engineering
Code Enforcement
Public Works
The Parks Crew repaired the baseball benches at Ivy Hills and Friendly Hills Parks.
They attended a chain saw safety meeting. They hauled out the appliances from
the house on Lemay Lake Road. Broken sprinkler lines were worked on at
Kensington Park South.
The Utilities Crew sprayed Friendly Hills Tot Lot, right-of-ways, guard rails, Glen
Hill easements and Public Works with broadleaf weed killer. Selected areas of
Valley Park were treated with total week killer. They also attended the chainsaw
safety class.
The Streets Crew dug out and cleaned the storm pipe on Summit Avenue. Black
dirt and grass seed were put down. Old sod was picked up from First Avenue,
Laura Street, and Summit Lane. Black dirt and grass seed were put down on
Lakeview Avenue. New stickers were made up for the parks trash barrels. New
back brakes were installed on truck 304. A bent push bumper was straightened
on a squad car. Blacktop patching continues. They also attended the chainsaw
safety class.
Engineering
City Projects (construction year)
Dodd Road/Hiahwav 110 Intersection Pedestrian Improvements (2013) - Council
awarded the bid at their June 18th meeting. Staff and the City's consultant will
hold a preconstruction meeting in the coming weeks. Construction will begin
shortly after the preconstruction meeting, and is scheduled for completion by
September 3rd.
Hunter Lane/Orchard Place Neiahborhood Improvements (2013) - Construction is
underway. Utility installations along Orchard Place are underway. The contractor
is working on Orchard Place first, then Hunter Lane. Rehabilitation work on
Veronica, Orchard Circle, Culligan, and Glenhill is expected in late July/early
August. Substantial completion is expected by the end of September with the
assessment hearing in October.
Crown Point & Overlook Neighborhood Rehabilitations (20131 - Base course
pavement has been placed in both the Crown Point and Overlook neighborhoods.
Utility manhole casting adjustments have been made and landscaping is complete.
Wear course placement will take place next week, weather permitting. Substantial
completion is expected in July. An assessment hearing is scheduled for October.
Lexington Avenue Pedestrian Trail, Hwy 110 to Douglas Road (2013) - The trail
has been re -paved, and pedestrian ramps installed. Landscape restoration is
underway. The trail remains closed during construction.
Sanitary Sewer Cleaning and Televising (2013) - Council awarded the contract at
their June 18th meeting. The contractor will be working in the area of the city west
of I -35E and north of Highway 110. Center Pointe Business Park is also included
in the project. Work should begin in the coming weeks.
Interstate Valley Creek Trail Paving - The trail is now paved! Xcel Energy's
contractor is working on closing out the final punch list items, and the trail will
reopen on Monday. Thank you to everyone for their patience.
County Projects (construction year)
Lexington Avenue Crosswalk (2013) - The crosswalk and island at the Victoria/
Lexington intersection is scheduled for installation in August. Specific schedules
will be posted as they are planned.
Delaware Avenue Guardrails (2013) - Guardrails along both sides of Delaware
Avenue, between Highway 110 and Interstate 494 will be installed this summer.
County maintenance crews will be doing the installation and they are scheduled for
installation in July/August.
North Urban Regional Trail (NURT) Realignment (2014) - Design is underway for
the new alignment of the NURT through the Henry Sibley High School property.
Utilities have been located and surveyors have been on site most of the week.
Design should be completed over the winter with construction anticipated in 2014.
For more information, contact the County Project Manager, Chris Hartzel, at 952-
891-7106.
Other Activities
Gun Club Lake Watershed Management Organization (GCLWMO) - Staff attended
the quarterly meeting of the GCLWMO on Wednesday. The GCLWMO is in the
process of updating their Watershed Management Plan. Mendota Heights has
asked about the possibility of departing the GCLWMO and placing that portion of
the City in the Lower Mississippi River Watershed Management Organization
(LMRWMO). This move would consolidate storm water rules across the City, and
reduce the amount of staff time spent on WMO activities. The process, if approved
by both WMOs should take about 6 months.