The Parks Crew turned off the aerator at Rogers Lake, rolled up the hoses
and brought them back to public works for storage. Maintenance was done
on the snow blower for next winter and new chains were installed on the
tires. Plows were taken off the trucks and stored in the water tower. All
summer equipment was taken out of the water tower and brought to the
shop. They started sweeping the trails.
The Utilities Crew finished painting the break room/kitchen. Part was of the
hallway was painted. The new generator was taken to total construction to
get new wiring. New parts were ordered for the Mendota Heights Road
force main due to the recent break.
The Streets Crew continues to fill pot holes throughout the city with UPM
mix. New hydraulic hoses were installed on the bucket of the John Deere
Tractor. The new truck was picked up from Inver Grove Ford. The sign
room was organized.
Engineering
City Projects (construction year)
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013 - The
completed plans and specifications are being routed through MnDOT for final
approval. The project will be advertised for bid soon. We are anticipating a bid
opening in May, with a contract award scheduled for the June 4th City Council
Meeting. Construction will begin shortly after contract award.
Hunter Lane/Orchard Place Neighborhood Improvements (2013) - Final plans have
been approved and the project is authorized for bidding. Bid opening is scheduled
for May 1St at 10:00am. Contract award is scheduled for the May 7th City Council
Meeting with construction beginning in June.
Crown Point & Overlook Neighborhood Rehabilitations (20131 - Staff conducted
the bid opening on Wednesday. Asphalt Surfaces Technology Corporation is the
apparent low bidder. Staff is currently verifying their bid documents. Contract
award is scheduled for the April 16th City Council meeting. Construction start is
anticipated in late May. Additionally, the project includes the Lexington Avenue
trail rehabilitation (see the next project) and preventative maintenance (chip seal)
in the Evergreen Knoll, Hidden Creek Trail, and the Bachelor/Stanwich
neighborhoods.
Lexington Avenue Pedestrian Trail, Hwy 110 to Douglas Road (2013) - Project was
bid with the Crown Point & Overlook Neighborhood Rehabilitation Project. Dakota
County is assisting with project construction costs. Project includes pavement
replacement, minor realignment, and pedestrian ramp replacement and/or new
installation. Construction is anticipated in late May/early June.
Highway 13 Trail Connection (2013) -The City has applied for a grant from the
Department of Natural Resources for construction funding. If not funded through
a grant, the City intends to construct the connection in 2013 with City funds.
Project will connect existing trails between Riverside Lane and Lilydale Road
County Projects (construction year)
North Urban Regional Trail (NURT) Realignment/Greenway Study (2014) - Dakota
County staff will be presenting the alignment alternatives to the District 197
School Board on April 15 to gather their opinions, and will present to the Dakota
County Board of Commissioners on April 16t". Staff is recommending the Dodge
Nature Center Alignment as the best fit for the Greenways Grant they received,
and the Henry Sibley alignment as a reasonable alternative. The Board of
Commissioners is expected to select an alignment alternative at that meeting. For
more information, please contact the Dakota County Project Manager, Chris
Hartzel, at 952-891-7106.
Lexington Avenue Crosswalk (2013) - Construction of the center median and
crosswalk on Lexington Avenue at Victoria will take place this summer.
Construction is anticipated in July/August.
Other Activities
Lower Mississippi River Watershed Management Organization (LMRWMO) - Staff
attended the monthly meeting of the LMRWMO on Thursday with both the City's
primary and alternate citizen representatives. Mary Jeanne Schneeman was
elected the Board's Treasurer. Updates were provided on the lake monitoring
efforts, and upcoming projects.