Pipeline 10 15 2010NEWS
LETTER
The Pipeline
Public Works�,� d
Engineering �'
Code Enforcement October 15, 2010
Public Works
The Parks Crew blew out the sprinkler systems at Mendakota Park,
Kensington Park, City Hall and the Fire Hall. The grass around the out
buildings at Kensington South and Mendakota were fertilized. A broken
water line was repaired at the Fire Hall.
Rich checked bad spots in the sanitary sewer lines to make sure they were
flowing free and there were no blockages.
Public Works crew is making plans for site preparation to facilitate the
Halloween bonfire at Mendota Plaza. Drop off of brush (no grass or leaves)
will be allowed beginning on Monday, October 25th
Engineering
Highway 55/Mendota Heights Road Intersection - The construction project is
underway. Existing pavement is being cut and removed, and improvement
areas have been marked and staked. Project is designed to extend existing
turn lanes, establish right -turn lanes, and reconfigure the signal to provide
better traffic flow through the intersection. Residents should be aware
of traffic revisions at this intersection due to construction through
the end of December.
2010 Reconstruction/Rehabilitation Project - Work for the 2010 portion of
the project is substantially complete. Remaining portions of wear course
asphalt on Spring Street, John Street, and Simard Street will be completed
in the spring of 2011. Assessment Hearing for the completed project will be
held at Council at the October 19th meeting.
Water Tower Rehabilitation - The external renovations are substantially
complete. The process of re -charging the water tower is under way. St.
Paul Regional Water Services will be installing telemetry for the tower on
Monday (10/18). The tower is then scheduled for disinfection on Tuesday
(10/19). The tank will then be filled and allowed to rest for 72 hours when
it will then be tested for leaks, bacteria, chlorine residual, and flavor. If all
tests pass it will then be brought back online to feed the water supply
system by the end of October. Restoration work to the grounds around the
tower and general site cleanup items are still being completed.
2011 Street Reconstruction Project (Wagon Wheel Trail) - Staff is preparing
for the Public Hearing scheduled for the November 16th Council
meeting. Notices will be sent to the affected property owners informing
them of the Public Hearing. Project is proposed to reconstruct Wagon Wheel
Trail from Lexington Avenue to Dodd Road, install storm sewer with curb &
gutter, and provide for a pedestrian trail along the length of the project.
Also proposed are the rehabilitation (mill & overlay) of Alice Lane, Rodgers
Court, and Swan Court.