Pipeline 10 01 2010NEWS
LETTER
The Pipeline
Public Works
Engineering(::
Code Enforcement October 1, 2010
Public Works
The Parks Crew attached the mulching kit to the #500 xmack mower for the
fall mulching of leaves. They repaired the hydraulic line on the #5900
groundmaster mower.
The Streets Crew cut back trees that were on the shoulder and hanging over
the road on Coleshire Lane. They started trimming trees on Emerson
Avenue and Dodd Road. Tree limbs were also trimmed at Copperfield and
Delaware Avenue. Storm sewer
grates were cleaned. They filled
in a well holding tank with sand
on a city lot on the west end of
the city. The repair of storm
sewer pipes was started on
Annapolis Street at Chippewa
Avenue and Medallion Drive at
Lexington Avenue. Cones and
barricades were dropped off at
the Police Department.
Engineering
Picture of well discovered at 1181 Bourn Lane.
Photo by Terry Blum
Highway 55/Mendota Heights Road Intersection - The construction project
has begun. Temporary traffic signals at the intersection have been
installed, safety markings and signs are in place, and the project is being
surveyed and marked for upcoming demolition. Residents should be
aware of traffic revisions at this intersection through the end of
December.
2010 Reconstruction/Rehabilitation Project - Work for the 2010 portion of
the project is substantially complete with small, punch -list items remaining.
Remaining portions of wear course asphalt on Butler and Ivy Falls Park,
Spring Street, and Simard Street will be completed in the spring of 2011.
Assessment hearing for the completed project will be held at the October
19th City Council meeting. The final mailboxes were re -installed by the
contractor this past week.
Water Tower Rehabilitation - The painting of the tower body is substantially
complete. Weather (rain and wind) prevented the contractor from meeting
their previously stated September 30th completion date, but with the
cooperation of the weather, the tower project should be substantially
complete by the end of this coming week.
2011 Street Reconstruction Project (Wagon Wheel Traill - Staff has
completed the Feasibility Report for the 2011 Street Reconstruction Project
and it is scheduled to be presented to Council at the October 5th meeting.
The project will reconstruct Wagon Wheel Trail from Lexington to Dodd Road
and will include the installation of storm sewer, curb & gutter, and an eight
foot bituminous trail along the length of the project.
Sewer Lining Contract - Each year the City contracts out services to clean,
video inspect/record, and line portions of our sanitary sewer system. The
cleaning and video recording contract was awarded earlier this year, and the
sewer lining work is scheduled to be before Council at their October 5th
meeting. These projects allow the City to reduce the amount of
groundwater and storm water that finds its way into our sanitary sewer
system increasing the total volume the City contributes to the Metropolitan
Council sewage treatment facilities. This in turn increases the amount we
have to pay to Met Council as a City.
Summit Development - Staff met with representatives form Opus
Corporation on Thursday (Sep 29) to discuss the development of the final
two twin -homes (4 units) a The Summit development at Wachtler and
Highway 13. It is the intention of the parties involved to start construction
in the spring.
Lilydale Racquet Club Site - Staff was contacted last week by developers
currently working on a proposed development plan through the City of
Lilydale. The plan includes utility connections from the City of Mendota
Heights. Once past accounts on the site have been settled, staff can
continue work on connecting this area to City utilities.