Pipeline 08 27 2010NEWS
LETTER
Public Works
Engineering
Public Works
The Pipeline
August 27, 2010
The Parks Crew continued to paint the hockey boards and warming houses.
They repaired the sprinkler valves at Mendakota Park on the soccer field.
All mowers were serviced. They trimmed the overhanging tree limbs in
Mendakota Park along the pedway.
Rich cleaned the sanitary sewer lines on Hidden Creek Trail and the Sunset
easement. He sprayed broadleaf weeds at Kensington, Hagrstrom King and
Friendly Hills Parks. He replaced hydrant flags that were broken. There was
a power outage at 5:00 PM on Saturday at the Mendota Heights Road lift
station. George responded because Rich was unable to come in and power
was restored at 8:15 PM.
Engineering
Visitation Drive/Mendota Heights Road Roundabout - The roundabout is
open and substantially complete. Permanent street lights still need to be
installed (estimated by September 15th). The temporary access to Visitation
from Lake Drive is removed; curb has been placed to completely close off
access to the school from Lake Drive. Landscaping along Lake Drive and
replacement of the Visitation fence is expected by September 15th.
Highway 55/Mendota Heights Road Intersection - Bids were opened on
Monday, August 23rd. Staff is compiling the Bid Tabulation and award of the
contract will be before Council at their September 7th meeting. The project
should begin construction by September 15th. Residents should be
aware of traffic revisions at this intersection beginning on
September 1St" and lasting for approximately 3 months. The project
is scheduled for completion by mid-December.
2010 Reconstruction/Rehabilitation Project - The contractor milled the wear
course off the remaining streets. Curb and concrete work should be
completed by early next week. Next week, the contractor will begin raising
manholes, paving bituminous trails, placing sod, project site clean-up, and
various other tasks. Final paving should be approximately two weeks away.
Street Improvement Plan - Staff presented the 2011-2015 Street
Improvement Plan (SIP) to City Council at the 2011 Budget work session on
August 17th. The SIP is a projection of the next 5 years for street
reconstruction, street rehabilitation, and utilization of the City's Municipal
State Aid financial account. A final version will be brought before Council for
public comment and formal adoption in the coming weeks.
2011 Reconstruction/Rehabilitation Projects - Staff is continuing the
preliminary work on the 2011 Street Projects. Wagon Wheel Trail is
scheduled for reconstruction next year, and the Knollwood Neighborhood
roads (Knollwood Court, Knollwood Lane, Medora Court, Medora Lane, Ivy
Lane, Lower Colonial Drive, Upper Colonial Drive, Cherry Hill Road east of
Wachtler, and Farmdale Road east of Wachtler) are scheduled for
rehabilitation, commonly referred to as a mill -and -overlay. Preliminary
Plans and Feasibility Reports will be brought before Council in the coming
months.
Dodd Road Utility and Storm Drainage Work (MnDOT Project) - The
contractor has projected this work to be completed by September 10th
Weather delays and utility coordination with outside businesses has caused
the completion to slip from its original August 25th completion date.