Public Works
Engineering 7
Code Enforcement August 6, 2010r ''►
Public Works
The Parks Crew is still working on the hockey boards at the hockey rinks.
They repaired the sprinkler heads at the Kensington soccer fields. All
sprinkler heads were marked at Mendakota and Kensington fields and the
fields were aerated. The ball fields at Mendakota Park and soccer fields at
Kensington Park were fertilized.
Rich cleaned the floats at the Veronica lift station. The manhole cover was
changed on Wachtler Avenue. The sanitary sewer lines were cleaned on
Copperfield Drive, Stone Road, Watersedge Terrace, Fieldstone Drive, Pond
View Drive and Grieve Glen Road. Fire hydrants were painted on Highway
13.
The Streets Crew helped the Parks Crew cleaned up trees on the pedway
that runs through Kensington Park. A new street sign was made up for
Lakeview Avenue and LeMay Lake Road that was taken. A sign head was
fixed on South Plaza Drive. Barricades were dropped off for National Night
Out on Wilshire Court, Mears Avenue, Bluebill Drive, Bluff Circle, Downing
Street and London Road. Buckthorn was picked up from Pagel Road. Tim
helped Cliff work on the John Deere backhoe.
Engineering
Visitation Drive/Mendota Heights Roundabout - The contractor stabilized
area soil with sod, seed, and erosion control blanket on Friday (8/6) and
should be placing the final lift of bituminous (asphalt) on Monday (8/9),
striping is scheduled to be completed by Wednesday (8/11), and the
roundabout should be open by August 20th once interim lighting is installed.
Final lighting installation should be complete by Labor Day.
Highway 55/Mendota Heights Road Intersection - The project is out for bid.
Bid opening is scheduled for August 23rd, and the project should begin
construction by September 15th. Residents should be aware of traffic
revisions at this intersection beginning on September 1St". The
project is scheduled for completion by mid-December.
2010 Reconstruction/Rehabilitation Project - The contractor paved the first
lift of pavement on Monday (8/2) and Tuesday (8/3) installed driveways on
Friday (8/6). The contractor will be completing the cul-de-sac at the end of
Spring Street next week and then will moving on to the mill and overlay
portion of the project. Manholes still need to be exposed as well as
boulevard work.
Street Improvement Plan - Staff will be presenting the 2011-2015 Street
Improvement Plan (SIP) to City Council after the 2011 Budget work session
on August 17th. The SIP is a projection of the next 5 years for street
reconstruction, street rehabilitation, and utilization of the City's Municipal
State Aid account. Once comments are received from Council during the
work session, a final version will be brought before Council for public
comment and formal adoption.
Public Works Director/City Engineer Returns - John Mazzitello has returned
from his deployment to Afghanistan with the Minnesota Air National Guard.
He started back with the City on Monday (8/2), and is getting back up to
speed on the status of projects and overall state of the Department. John
would like to thank the City (Council, Staff, and Residents) for making the
transitions both to and from deployment incredibly easy for both him and
his family, and also for all the support provided during his absence.