Pipeline 04 23 2010NEWS
LETTER
The Pipeline
Public Works
Engineering �•
Code Enforcement April 23, 2010 40 ,s ;
Public Works
The Parks Crew striped the soccer, softball and lacrosse fields. They cleaned out
the water tower for the painters. Crab grass preventative was put down as
needed. The mulching kit was taken off the Xmark for the summer.
Rich mowed the grass at the Veronica lift station. He did his annual inspection of
Lilydale's storm sewer into the Mississippi and there were no illicit discharges. He
inspected Mendota Plaza's sanitary sewer pipe, Veit Companies did the work. He
helped clean out the water tower.
The Streets Crew picked up car parts and trash that was dumped on Valencour
Court. The street sweepings were hauled to Dakota County. Tom Olund and the
Street Crew attended the spring equipment expo in St. Cloud.
Engineering
Intern - Engineering received approval to hire an Engineering Intern for the
summer.
Data Collector - City Council approved the purchase of a data collector to
upgrade its current equipment used for surveying.
2010 Street Project- GMH Asphalt was awarded the bid for the 2010 Street
Reconstruction & Rehabilitation Project with their bid of $1,021,688.11. There
were 11 bidders on this project. The engineer's estimate for the project was
$1,263,716.30. A preconstruction meeting has been scheduled for Tuesday, April
27th