Loading...
Pipeline 04 02 2010NEWS T LETTER Public Works Engineering Code Enforcement he Pipeline 40.d April 2, 2010 Public Works The Parks Crew put more trash barrels in the park as needed. The tennis nets were put up and leaves cleaned out of the tennis courts. The pedways were swept. The bases were installed at Hagstrom King and Mendakota Park. The bathrooms were opened at Mendakota and Kensington Park. Rich repaired two water boxes on Centre Pointe. He cleaned the "the bad spots" in the sanitary sewer lines on Victoria, William Court, Keokuk, Pontiac Place, Decorah, Ocala, Apache, Hazel Court, North Freeway Road, Knob Road, Wagon Wheel and Mendota Heights Road near Friendly Hills Middle School. He did a sanitary sewer inspection at 651 South Freeway Road. The Streets Crew started taking the sanders, plows, and wings off all plow trucks to get ready for street sweeping which is scheduled to start on Monday. A dead deer was picked up from the bank along 35E by the Marie Avenue bridge. They are working on mail box repairs. Code Enforcement Code Enforcement has issued the first of two permits to Benson -Orth Associates for the Mendota Plaza, 750 Highway 110, for a partial building demolition and exterior fagade work valued at $1,502,069.00. The second permit was issued to the same contractor for 790 Highway 110 for the new Walgreens Pharmacy for $1,475,961.00. The Walgreens will contain 14,820 square feet of space. Engineering Water Tower Rehabilitation - A Preconstruction meeting is scheduled on Monday April 5. The contractor will begin mobilizing equipment to prepare for the upcoming project. Highway 55/Mendota Heights Road - Staff continues to work with property owners on securing easements for the proposed intersection improvement project. Mendota Heights Road Roundabout - Proposals have been scored for the selection of a consultant for construction oversight on the project. Staff will be recommending Bolton & Menk, Inc. at the upcoming Council meeting. 2010 Reconstruction project - Bid opening is scheduled for April 14th. Approximately 15 sets of plans have been distributed to contractors. Dakota County Traffic Visioning Study - The consultant for the study has distributed its preliminary recommendations. Alternatives with the addition of an interchange at Delaware Avenue and 494 are not being recommended. Ryan attended the Minnesota Storm Water Coalition meeting on Wednesday. The City will be required to renew its permit next year and the coalition reviews the permit guidelines and makes recommendations on the City's behalf.