Loading...
Pipeline 03 09 2012N E W S M. 0 Pipeli11 ne 1 V e L E T T E R Publlh6 Works Engineering March 9, 2012 Code Enforcement Public Works The Parks Crew picked up downed tree limbs from last week's heavy snowfall. They attended the spring workshop for the Minnesota Parks and Sports Turf Managers Association at Northwestern College. The parks trailer had its brakes repaired along with its wheel bearings. Units 505 & 506 were prepared for summer storage. Repairs were made on truck 501 to fix a broken hose and the cracked. push ram was fixed. The Utilities Crew cleaned grease off the floats at the Veronica lift station. Root killer was applied on Summit Lane. Staff attended the Mendota Heights safety training and regional safety meeting in South Saint Paul. The Streets Crew cleaned off snow on the bridge deck on Mendota Heights Road, Wagon Wheel Trail, and Acacia Blvd. On Saturday the streets were salted. Maintenance was done on truck 303 to repair the front plow, which had a broken spring from hitting a water box. The John Deere tractor was washed, steam cleaned and greased. Engineering Lemay Lake Road Reconstruction - Staff is currently working on the road section design. We are looking at the possibility of making the cul-de-sacs. 24 -feet wide to address some resident concerns. A second informational meeting for area residents and property owners is anticipated in April. Final plans are anticipated in May. Marie Avenue Rehabilitation - Staff is waiting to receive comments from MnDOT on the preliminary design. Final plans are anticipated by late March. The striping plan will be mailed to Marie Avenue residents once completed. Diane Road N eighborhood/Mendota Heights Road Rehabilitation - Staff is waiting for MnDOT comments on the preliminary design. MnDOT review is only required for the Mendota Heights Road portion of the project. Final plans are anticipated by late March. Dodd Road Trail Extension to Eagan -Eagan has a grant from Met Council to widen Dodd Road south of 1-494 to be constructed in 2014. Part of the project is to add lane capacity to the entrance/exit ramp to/from 1-494 on the north side of the Interstate (in Mendota Heights). Eagan would like to include a trail extension on the west side of Dodd Road from the 1-494 Bridge to Mendota Heights Road. The City of Mendota Heights would need to participate in the project for this to happen, but Eagan is offering to include the design and construction of the extension under their contract. Staff is working with Eagan on gathering cost estimate information on what Mendota Heights' participation level would likely be. More to come... White Pine Senior Living PUD Amendment Application - Staff has revived the latest version of the PUD Amendment plans from the developer. Once reviewed, staff will provide comments back to the developer. If deemed acceptable, a letter will be sent to the developer granting approval of the PUD Amendment plans. Dodd Road/Highway 110 Intersection Pedestrian Improvements - Staff has been answering questions from consulting firms interested in proposing on the design work for the intersection project. Proposals are due on March 21st, and a staff recommendation for the selected consultant is anticipated to be on the April 3rd Council agenda. MnQ0T & Dakota County Projects The following projects are under the direction of MnDOT and Dakota County. They are presented as information only. For more information on MnDOT projects contact J.P. Gillach (651-234-7503, -james.gillachostate.mn.us). Highway 13 Resurfacing (MnDOT) - The Resurfacing of Highway 13, along with drainage improvements and ADA upgrades between I -35W and Annapolis Street (Burnsville to West St. Paul) is scheduled for the summer of 2012. Segmented construction should be anticipated between May and October of 2012. MnDOT will contact impacted Mendota Heights' residents with construction schedule news and road closure information. Detours around the construction areas will be provided. The portion of Highway 13 from Mendota to I -35E will be exempted from this project and reconstructed in 2015 under a separate MnDOT project. Highway 110 Resurfacing (MnDOT) - A small portion of Highway 110 from Lexington Avenue east to the I -35E Bridge,, along with spot repairs between Lexington and Highway 13 will be resurfaced during the summer of 2012. MnDOT is working with Dakota County to minimize conflicts with their Lexington Avenue project (see below), also scheduled for 2012. Turnback of Old Sibley Memorial Highway (MnDOT) - MnDOT intends to vacate the Right -of -Way for the Old Sibley Memorial Highway. Concept plans are being developed for the land use once it is vacated. The next meeting is scheduled for April 20th at Camp Sacagawea in Apple Valley. MnDOT will be contacting the two Mendota Heights businesses impacted by the proposal prior to the April meeting. Lexington Avenue Resurfacing (County) - Dakota County will be resurfacing Lexington Avenue from Highway 110 south to Mendota Heights Road in 2012. NO expansion of Lexington Avenue is anticipated. Dakota County is working with MnDOT to minimize conflicts with their Highway 110 project, also scheduled for the summer of 2012. For more information contact the Dakota County Transportation Department at 952-891-7100.