The Parks crews collected trash from the parks. A ditch was dug at Ivy Falls Park
to drain water from the skating rink. Trail sweeping was started. Water meters
were installed at Mendakota Park and Kensington Park for the public restrooms
and utility rooms were stocked with supplies for the summer. Summer equipment
was serviced and is ready for use.
The street crew started making signs to replace those that were damaged during
winter (Valencoor Cir, Arcadia Drive, Sylvandale Court, Sylvandale Road,
Brompton PI). Astorm grate was cleared on Cherry Hill Road near the Excel tank
farm. The outlet has consistently been a maintenance issue for the city. Mailbox
repair was ongotng. A dead cat was picked up from Bluebill Drive. Pot holes were
filled in the city With temporary patching material.
Rich checked sanitary sewer lift stations daily. A dented wet well cover was
repaired at the Mendota Heights Road lift station near St. Thomas Academy.
Stand-by generators were serviced and tested (one at main lift station and trailer
mounted unit). New batteries were installed in the jet truck. Rich met with the
city engineering department to plan 2011 and future sewer projects.
Enciiinggrinng
Wagon Wheel Trail Reconstruction - Final plans for the reconstruction
project have been submitted to MnDOT for review. Once MnDOT approval is
received, the project will be advertised for bid. We are anticipating a
scheduled bid opening date in early May. Construction is anticipated to
begin mid-June with substantial completion by the end of September.
Delaware Avenue Reconstruction - Dakota County held the bid opening on
April 5t". Danner Construction was the apparent low bidder. Danner
Construction built the Mendota Heights Road/Visitation Drive Roundabout.
With this bid opening, the project remains on schedule for construction start
in early June and d substantial completion by Labor Day weekend. Project
information can be found at: us/EnvironmentRoads/RoadConstruction/Current/63-22.htm
.http://www.co.dakota.mn.us/EnvironmentRo
for Rogers Lake and its surrounding drainage area. Representative Hansen
and Mr. Jaschke requested the meeting to get an update on the weed
control operations at the lake, and the efforts of the Lower Mississippi River
Watershed Man'agement Organization (LMRWMO) to get a drainage and
water quality study completed for the lake. Earlier this year the LMRWMO
requested the Minnesota Pollution Control Agency include Rogers Lake in an
area -wide study of stormwater runoff and water quality. Staff provided
these updates and pledged to continue keeping Representative Hansen's