Pipeline 08 26 2011N E W S The Pipeline
LETTER
Public Works
Engineering August 26, 2011
Code Enforcement aAi
Public Works
The Parks Crew striped the soccer fields. They also striped parking lot lines
at the fire hall, Mendakota Park, Hagstrom King Park, and city hall. French
drains were dug at Kensington Park play areas. The grills were replaced at
Wentworth Park.
The Utility Crew sprayed the right of ways with round up total kill. Sanitary
Sewer lines were cleaned on First Avenue, Kay Avenue, Walsh Lane, Oxford
Court, William Court, and Glen Hill Road and in the easements on Eagle
Ridge Road, Victoria townhomes, and Caren Court. The thermostat was
changed on truck 404.
The Streets Crew put together new signs and installed them for the Avenues
and Brookside Lane. Blacktop patching was done at the old fire hall, public
works garage, Stratford Road, Walsh Lane, and Marie Avenue from Dodd
Road to Delaware Avenue. John fabricated a box and bracket for the parks
grass seeder.
Engineering
Wagon Wheel Trail Reconstruction - Xcel is finishing their utility relocation
work. The city contractor has removed pavement for the storm sewer work
which is scheduled to begin Friday August 26t". Milling of the remainder of
the street is scheduled for September 8t"
Delaware Avenue Reconstruction - The first course of pavement has been
installed. The remaining layers of asphalt for the street and trail will be
installed by Friday September 2nd. Project information can be found at the
project web
site: http://www.co.dakota.mn.us/EnvironmentRoads/RoadConstruction/Current/63-
22. htm
Knollwood Neighborhood Street Rehabilitation - The contractor removed the
pavement and is finishing stabilizing the subsurface soils. The streets are
t"
scheduled to be paved with the base course by Friday, August 26
MnDOT Projects
The following projects are under the management and supervision of
MnDOT and are presented as information only. Contacts for each individual
project are listed after the project update.
Dodd Road Resurfacing - MnDOT completed placing an asphalt overlay on
Dodd Road between Lake Drive and Hilltop Road and sealcoating the
remainder of Dodd Road to the North. For more information, go to the
MnDOT project web page
at: http://www.dot.state.mn.us/metro/news/11/08/1Ohwy149.htmI
I -35E Resurfacing - MnDOT began resurfacing I -35E on August 18th. The
project is anticipated to last until November 1st. In addition to the
pavement resurfacing, MnDOT will be installing new guardrails, improving
drainage, and upgrading exit and entrance ramp signals. The project will be
accomplished mainly at night and during off-peak (non -rush hour) traffic
times. Lane closures are expected during off-peak traffic times.
Information on the project can be found at the MnDOT project web
page: http://www.dot.state.mn.us/metro/projects/i35eeagan/index.htmI
I -35E & Highway 13 Traffic Signal Installation - Traffic signals at the exit
and entrance ramps to I -35E from Highway 13 will begin on approximately
September 15th. Information about the project on Highway 13
reconstruction projects can be found on the MnDOT project web
page: http://www.dot.state.mn.us/metro/projects/hwy13mendota/
Mendota Bridge Resurfacing - MnDOT began resurfacing the Mendota Bridge
to extend the life of the bridge deck beginning on August 15th. The project
is expected to add 20 years to the life of the bridge deck. For more
information on the project contact the MnDOT project manager, Kent
Barnard, at 651-234-7504.
Stormwater Pond Condition Assessment - The consultant has completed
their condition survey and sampling of the three designated ponds
(Copperfield, Burrows, and Park Place), and is compiling the data for their
draft report and recommendations. By terms of the contract, the consultant
should have a draft report before City Council in October.