Pipeline 07 22 2011N E W S The Pipeline
LETTER \'4)
Public Works
Engineering
Code Enforcement July 22, 2011
Public Works
The Parks Crew cleaned up downed tree limbs on the trail in Valley Park, repaired
the infields at Mendakota Park after the weekend rain storms, and prepared the
fields at Mendakota Park for this weekend's tournament.
The Utility Crew cleaned the sanitary sewer lines in Junction Lane, John Street,
Esther Street, Spring Street, View Street, and Butler Avenue. The storm pipe on
Lower Colonial Drive was cleaned, and fire hydrants on Eagle Ridge Drive were
painted.
The Street Crew cleaned storm grates throughout the city. Tree limbs were picked
up from boulevards. Blacktop patching was completed on London Road and Mager
Court. The trail at Marie Avenue and Dodd Road was blacked topped and crack -
sealed. Sod damage from snow plow activity was repaired after the rain washed
away the black dirt and grass seed that was put down earlier. The trucks were
washed, waxed and steam cleaned.
All Public Works and Engineering staff attended mandatory safety training on
Tuesday. Identification and treatment for heat stress, heat exhaustion, and heat
stroke were discussed along with lock-out/tag-out procedures and electrical safety.
Engineering
Wagon Wheel Trail Reconstruction - Tree removal and vegetation clearing is
complete. Utility companies (Xcel, Comcast, Qwest, etc.) are completing the
relocation of underground utilities and utility poles. Due to scheduling conflicts
with Xcel Energy, pavement removal and road reconstruction are now anticipated
to begin on Monday (7/25). This delay in construction start will move the
substantial completion date back by 3 weeks, from the original date of October 7th
to the new completion date of October 28tH
Delaware Avenue Reconstruction - The contractor is continuing to work on
widening the road bed and completing the utility installations. Upcoming activities
include completing utility installation, preparing the widened road base for the
sub -surface gravel layers, and preparing the roadway for paving. Substantial
completion of the project is anticipated by Labor Day. Delaware Avenue is
closed to through traffic and a detour is posted. Project information can be
found at the Dakota County web site:
http://www.co.dakota.mn.us/EnvironmentRoads/RoadConstruction/Current/63-
7 7 htm
Knollwood Neighborhood Street Rehabilitation - Council awarded the construction
project to McNamara Construction at the July 19th meeting. Construction is
expected to begin on or about August 1St with substantial completion of the project
by October 7th. Crack sealing and sealcoating the southern portion of the project
area has already been completed.
Lilydale Racquet Club Senior Housing and Apartment Development - Staff
continues to work with the developer on establishing municipal water service to
the development site in Lilydale. The developer and the City entered into an
agreement last month and plans for the water main extension have been provided.
Saint Paul Regional Water Service (SPRWS) has provided design comments to the
developer and will work directly with the developer on remaining issues, and
construction will not begin until all parties have come to agreement. The City of
Lilydale is predicating their approvals of the project on a water service agreement
being in place.
Lower Mississippi River Watershed Management Organization (LMRWMO) -The
LMRWMO met Thursday at Mendota Heights City Hall to go over agency comments
received on the Draft 3rd Generation Watershed Management Plan. Responses to
the agency comments were discussed and will be incorporated into the plan. A
public Hearing on the Draft Plan has been scheduled for 9:OOam on Thursday,
August 18th at West Saint Paul City Hall. Once public and agency comments are
incorporated into the plan, it will be presented to the Councils of the member cities
and Councils will be asked to pass a Resolution of support. Staff is anticipating a
support Resolution being presented to Council in September or October. The Joint
Powers Agreement for the WMO will also need to be updated once the Plan is
approved. The Draft Plan is available for public review at the LMRWMO web page:
http://www.dakotacountyswcd.org/watersheds/lowermisswmo.
2012 Street Projects - Staff continues to compile data for the 2012 street
reconstruction and rehabilitation project Feasibility Reports. Proposed for
reconstruction are LeMay Lake Road, Lakeview Avenue, Kendon Lane, Furlong
Avenue, and Victory Avenue. Proposed for Rehabilitation are Diane Road, Celia
Drive, Rae Court, Adeline Court, Nina Court, Barbara Court, Douglas Road (east of
Victoria), Marie Avenue and Mendota Heights Road (both from Delaware Avenue to
Dodd Road). Completion of the Feasibility Reports is anticipated this fall, when
they will be presented to Council.
Infrastructure Improvement and Maintenance Plans - Staff is updating the Street
Improvement Plan (SIP) and in anticipating presenting the 2012-2016 SIP to
Council this fall. The 2012 reconstruction and rehabilitation schedule has already
been given the approval for Feasibility Report production. Staff is also completing
the draft Sanitary Sewer Improvement Plan, which will also be introduced for
approval this fall. The Sanitary Sewer Plan will outline the sewer cleaning,
televising, and lining plan for the next 5 years with cost estimates and funding
sources.