Pipeline 07 01 2011N E W S The Pipeline
LETTER
Public Works
Engineering IIIJuly 1, 2011
Code Enforcement
Public Works
The Parks Crew repaired the Victoria Highlands Park ball field infield from
vandalism. A car had driven over the infield and rutted the field. Sprinkler
valves were repaired at Mendakota Park.
The Utility Crew continues to paint fire hydrants, and preparing for the
annual sanitary sewer cleaning and televising project.
The Street Crew cut trees along Victoria Road from Douglas Road to Diane
Road. Temporary seal coat signs were picked up from the project area and
brought back to the shop. A mail box was replaced on Victoria Road that
was hit by a fallen tree.
Engineering
Wagon Wheel Trail Reconstruction -Tree removal and vegetation clearing
has begun. Saint Paul Regional Water Service has finished replacing the fire
hydrants. Construction limits have been staked at the site. Xcel Energy is
moving underground lines and relocating utility poles. Due to scheduling
conflicts with Xcel Energy, pavement removal and road reconstruction will
start later than anticipated. Mid -July is now expected for existing pavement
removal. Physical construction/demolition of the road is expected to begin
July 5t" with substantial completion by October 7t".
Delaware Avenue Reconstruction - Construction activity is in full swing.
Pavement has been removed, and the sub -base is being widened. Water
main and storm sewer are being installed. The contractor will be working
early on July 6t" to replace the water main and service stub to Henry Sibley
High School. Project substantial completion is anticipated by Labor Day.
Delaware Avenue is closed to through traffic and a detour is posted.
Project information can be found at the Dakota County web site:
http://www.co.dakota.mn.us/EnvironmentRoads/RoadConstruction/Current/63-22.htm
Lower Mississippi River Watershed Management Organization (LMRWMO) -
The LMRWMO Draft 3rd Generation Watershed Management Plan agency
comment period has closed. The Draft Plan is available for view at
http://www.dakotacountyswcd.org/watersheds/lowermisswmo. The next
meeting of the LMRWMO is scheduled for July 21st, at Mendota Heights City
Hall where a public hearing date will be set after agency comments have
been discussed. Once public and agency comments are incorporated into
the plan, it will be presented to the Councils of the member cities and
Councils will be asked to pass a Resolution of support.
Knollwood Neighborhood Street Rehabilitation - The Knollwood
Neighborhood Rehabilitation project is currently out for bid. Bid opening is
scheduled for July 13th with Council award of the contract at the July 19th
meeting. Construction is expected to begin about August 1St with
substantial completion of the project by October 7th. Crack sealing and
sealcoating the southern portion of the project area has already been
completed.
American Public Works Association (APWA) Conference Committee - The
Public Works Director attended a meeting of the Minnesota Chapter of the
APWA to assist in planning the Fall 2011 Chapter Conference. Guest
speaker and presentation schedules are being worked out for the conference
that will be held in Brooklyn Center in mid-November.
2012 Street Projects - Staff is working on the Feasibility Reports for the
2012 street reconstruction and rehabilitation projects. Proposed for 2012
reconstruction are LeMay Lake Road, Lakeview Avenue, Kendon Lane,
Furlong Avenue, and Victory Avenue. Proposed for 2012 Rehabilitation are
Diane Road, Celia Drive, Rae Court, Adeline Court, Nina Court, Barbara
Court, Douglas Road (east of Victoria), Marie Avenue and Mendota Heights
Road (both from Delaware Avenue to Dodd Road).