Pipeline 06 03 and 10 2011NEWS The Pipeline
L E T T E R_-_
Public Works June 3, 2011 and
Engineering June 10, 2011
Code Enforcement
Public Works
The parks crew finished spraying for weeds in the parks. The Crew
prepared Mendakota Park, set up equipment and took down the equipment
for the parks celebration. The sprinkler systems were tested at Kensington
Park (a valve was replaced), Mendakota Park, City Hall, and at the fire hall.
They removed a vandalized spray painting from the pavilion at Mendakota
Park. John and Cliff cut back a lilac shrub for the street crew in the center
median on Lilac Lane.
The street crew spent most of the week blacktopping on Chippewa Avenue
and Knollwood Lane getting ready for the seal coating and chip seal
projects. Storm grates are being cleaned. Downed trees were cut up that
were on trails and in the streets. Potholes were filled and overlays done in
the Diane Road area, Hunter and Orchard area and on Mendota Heights
Road.
The utility crew fixed a water box on Nina Court. An area that had settled
around a fire hydrant was filled with dirt and grass seed on Laura Court.
The sanitary sewer lines were cleaned on Wagon Wheel Trail from 35E to
Lexington Avenue (the lines were filled with roots), in the Summit Lane
easement and Mendota Heights Road near Friendly Hills Middle School.
They sprayed for weeds in road right-of-ways, at guard rails and fence lines
for the street crew. Total weed kill was applied at the Lilydale lift station
parking area. Dandelions were sprayed again at Kensington Park. Fire
hydrants were washed and prepped for painting on Dodd Road and the Ivy
Falls area.
Engineering
Wagon Wheel Trail Reconstruction - Staff has scheduled a preconstruction
meeting with the contractor on June 16th. Tree removal has been marked
at the construction site, and Saint Paul Regional Water Service has begun
replacing the fire hydrants. Construction limits have also been staked at the
site. Construction is expected to begin in late June/early July with
t"
substantial completion by October 7
Delaware Avenue Reconstruction - The contractor has started flagging
utility locations along Delaware. Preliminary portions of the project are
underway. Traffic disruption is expected to begin next week, and
substantial completion of the project is anticipated by Labor Day weekend.
Delaware Avenue will be closed to through traffic during construction.
A detour will be provided. Project status and contact information can be
found on the project page and the Dakota County web site:
http://www.co.dakota.mn.us/EnvironmentRoads/RoadConstruction/Current/63-22.htm
Highway 13 at I-494 MnDOT Construction Project - The project is scheduled
to be complete by June 12th. Pavement repair, guardrail installation,
drainage/grading improvements, and landscape repair are ongoing. The
contractor will be working from 6:30am to 5:30pm Monday through Friday.
MnDOT contact is Charles Graf at 651-406-4725.
Lower Mississippi River Watershed Management Organization (LMRWMOJ -
The Draft LMRWMO 3rd Generation Watershed Management Plan is available
for agency comments. Comments are due back to the consultant by June
28th, and Engineering Staff has a copy available for review. The Draft
Watershed Management Plan is also available at the LMRWMO web page:
http://www.dakotacountyswcd.org/watersheds/lowermisswmo. The next meeting of
the LMRWMO is scheduled for June 16, at Mendota Heights City Hall where
agency comments received to date will be discussed.
Dakota County Capital Improvement Plan (CIP) Updates - Dakota County is
requesting input on their 2012-2016 CIP. Projects in the CIP are divided
into three categories: Transportation, Parks, and Buildings. Projects can be
requested through City staff by June 24th. A Final Draft will be published in
September. The 2011-2015 CIP can be found at the Dakota County web
site: httn://www.co.dakota.mn.us/CountvGovernment/BudoetFinance/20llBudoet.htm.
Highway 55 & Mendota Heights Road Reconstruction - The contractor has
been working on final pavement and striping items this week this week, and
has also been finishing up landscaping details. Completion of the side slope
erosion stabilization is scheduled for next week. Staff will schedule a
punch -list walk-through inspection once construction is completed.
County Road 45 (Lilydale Road) Turnback -The City of Saint Paul has
already agreed to take responsibility for Lilydale road from the southwestern
end of Lilydale Regional Park (by Pool & Yacht Club) into Saint Paul. If the
turnback takes place, Mendota Heights would be responsible for the 'loop"
from Highway 13 to just past the Highway 13 bridge. The City of Lilydale
would be responsible for the road from the Highway 13 bridge to Lilydale
Regional Park. The City of Lilydale has no road maintenance function
within their government and has asked for Mendota Heights for a quote on
how much it will cost for us to maintain the —1100 feet of road for them.
The turnback of Lilydale Road will eventually require Council approval.