The Parks Crew planted donated trees in the parks as needed. Rec rock was
hauled in to Hagstrom-King Park, Mendakota Park, and the Civic Center ball
fields to level low areas. Brush was picked at Marie Park and hauled away.
Rich did a sanitary sewer inspection at 1937 Dodd Road. A five foot repair
had been done because of roots blocking the service. He sprayed for
broadleaf weeds at the Fire Hall, North and South Kensington Park,
Mendakota Park and Curley's Park. He helped Parks Crew plant trees.
The Streets Crew continues working on the sod repair list. They are also
working on repairing mailboxes. Trees were trimmed at the Trail Road and
Marie Avenue corner because of sight distance problems. Pot holes were
patched on Wagon Wheel Trail, Mendota Heights Road, Mendakota Drive
and Concord Way. John A. and Tim helped Cliff work on a fire truck.
Engineering
Wagon Wheel Trail Reconstruction - Bids were opened on Wednesday
morning, and an apparent low bidder was selected. Bid prices will be
checked against the engineer's estimate and a recommendation for award of
the contract is expected to be before Council at the May 17th meeting.
Construction is anticipated to begin in early June with substantial completion
by October 7th
Delaware Avenue Reconstruction - Staff attended the preconstruction
meeting with the contractor on Wednesday. Small, preliminary portions of
the project are underway. Traffic disruption is expected to begin during the
first half of June (after school is out), and substantial completion of the
project is anticipated by Labor Day weekend. Delaware Avenue will be
closed to through traffic during construction, and a detour around the
project will be provided and signed. Project status and contact information
can be found on the project page and the Dakota County web site:
http://www.co.dakota.mn.us/EnvironmentRoads/RoadConstruction/Current/63-22.htm
Highway 13 at I-494 MnDOT Construction Project - Construction started on
Wednesday. The project consists of pavement repair, guardrail installation,
drainage/grading improvements, and landscape repair. The contractor will
be working from 6:30am to 5:30pm Monday through Friday, and access to
adjacent properties will be maintained throughout the project. Residents
should expect periodic traffic reductions to one lane in either direction
throughout the project, which is scheduled for completion by June 12th.
MnDOT project contact for this project is Charles Graf at 651-406-4725.
Lower Mississippi River Watershed Management Organization (LMRWMO) -
The Draft LMRWMO 3rd Generation Watershed Management Plan has been
distributed for agency comments. Agency comments are due back to the
consultant by June 28th, and Engineering Staff has a copy available for
review. The Draft Watershed Management Plan is also available at the
LMRWMO web page: http://www.dakotacountyswcd.org/watersheds/lowermisswmo.
After the agency comment period, there will be a public comment period
when the LMRWMO will ask for a Resolution of support from each member
City's Councils. The next meeting of the LMRWMO is scheduled for June 16,
at Mendota Heights City Hall where agency comments received to date will
be discussed.
2012 City Street Projects - Staff is preparing to gather background
information on the 2012 street reconstruction and rehabilitation projects.
This is beginning a little earlier than normal as staff hopes to get our
seasonal intern involved in the site surveys and preliminary designs.
Authorization requests for feasibility reports to be produced are scheduled
to be presented to Council at the May 17th meeting. The 2012 program, as
identified in the Street improvement Plan (SIP) are:
Reconstruction: Lemay Lake Road, Lakeview Avenue, Kendon Lane,
Furlong Avenue, and Victory Avenue
Rehabilitation: Diane Road, Celia Drive, Rae Court, Adeline Court,
Nina Court, Barbara Court, Douglas Road (east of Victoria), Marie Avenue
(between Dodd Road and Delaware Avenue), and Mendota Heights Road
(between Dodd Road and Delaware Avenue).
Municipal State Aid (MSA) Street Designation - Staff has been working with
MnDOT on revising our MSA street designations. This is done periodically to
allow MSA funds to be expended on specified streets. There is a specific list
of criteria a street must meet in order to qualify as an MSA designated
street, so options of altering our designations are limited. The
recommended, revised MSA street map is scheduled to be before Council for
approval at the May 17th meeting.