Pipeline 04 22 2011NEWS
LETTER
Public Works
Engineering
Code Enforcement
Public Works
The Pipeline
lat April 22, 2011
The Parks Crew dragged the ball fields. Downed tree limbs were picked up
in the park. The volleyball net at Rogers Lake Park was replaced. The
Rogers Lake aerator and thin ice signs were removed and placed in storage
for the summer. A cedar fence was repaired on Wachtler Avenue that was
damaged from a snow plow. Repaired the tennis court net at Marie Park.
Rich marked manholes on the northeast interceptor line. He helped the
Parks crew plant trees and shrubs at Kensington Park. A hydrant flag was
replaced on a fire hydrant on Concord Way. The pump 2 meter was broken
at the Veronica lift station and Rich replaced it. Mendakota Golf Course had
a contractor clean the sanitary sewer line on Wagon Wheel Trail. Rich
inspected the sewer line downstream from the Somerset Golf Course after
they had their sewer line cleaned.
The hot box was installed on the dump truck, the asphalt tray was installed,
and the LP tank hooked up. Mailboxes were replaced on Emerson Avenue,
Sylvandale Court and others are being worked on. A broken storm grate
was replaced on Hiawatha Avenue. A stop sign was replaced that was taken
at High Ridge and Warrior. A bent sign post was fixed at Warrior Drive and
the Frontage Road.
Engineering
Wagon Wheel Trail Reconstruction - The project is advertised and
contractors are welcome to call for bid sets. An Ordinance codifying the no
parking areas of the post -construction project was approved by Council at
their April 19th meeting. The Ordinance was a requirement of MnDOT in
order to utilize Municipal State Aid (MSA) funds for the project. Staff has
scheduled the bid opening for Wednesday May 11th at 10:OOam, with
contractor award anticipated for the May 17th City Council meeting.
Construction is anticipated to begin mid-June with substantial completion by
the end of September.
Delaware Avenue Reconstruction - Dakota County has awarded the project
and the contractor is making preparations to begin construction. The
project remains on schedule for construction start in early June and
substantial completion by Labor Day weekend. There may be some
construction activity beginning by late May, but the existing roadway will
not be disturbed until after Henry Sibley High School is off for summer
vacation. Dakota County intends to have the reconstruction of the road
area substantially complete before school resumes in September. Project
information can be found on the County web page:
http://www.co.dakota.mn.us/EnvironmentRoads/RoadConstruction/Current/63-22.htm
Knollwood Neighborhood Rehabilitation - Public Hearing for this project was
held at the April 19th City Council Meeting. No public testimony was offered,
the project was ordered, and plan and specification production was directed.
Construction is anticipated to begin late June or early July, with substantial
completion by the end of September.
2011 MnDOT Construction Projects - The Minnesota Department of
Transportation (MnDOT) has published its list of 2011 construction projects.
Staff presented these projects at the April 19th City Council Meeting.
Projects scheduled for construction in the Mendota Heights area include:
TH 13 & I -35E Exit/Entrance Ramps - Traffic Signal Installation (July).
TH 13 from I-494 to Pilot Knob Road - Pavement Resurface, Guardrail
Installation, & Drainage Improvements (May/June).
I -35E from Lone Oak Road to West 7th Street - Pavement Overlay,
Repair, & Replacement (July/August). After Hwy13 signals are complete.
TH 149 (Dodd Road) from Mendota Heights Road to Smith Avenue -
Pavement Repair and Sealcoat Treatment (October/November).
At the request of Council, staff has arranged for the MnDOT project
manager for the Highway 13/I -35E traffic signal project to provide
background information and answer questions about the project at the May
17th City Council Meeting.
Dakota County Capital Improvement Plan (CIP) Updates - Dakota County is
asking for input from local communities on their 2012-2016 CIP. Projects
are divided into three categories within the CIP: Transportation, Parks, and
Buildings. Projects can be requested by local communities, through City
staff by June 24th, for inclusion in the plan. A Final Draft will be published in
September, and Cities will be asked for a Council approved Resolution of
support for the CIP at that time. The 2011-2015 approved CIP can be found
at the Dakota County web site:
http://www.co.dakota.mn.us/CountyGovernment/BudgetFinance/2011 Budget.htm.
Lower Mississippi River Watershed Management Organization (LMRWMOj -
Mendota Heights hosted the monthly LMRWMO meeting at City Hall
Thursday morning. The revisions for the 3rd Generation Watershed
Management Plan were approved and the LMRWMO Board approved sending
the plan out for agency review. Once agency comments are received, the
Plan will be updated to reflect those comments, and the Plan will be
published for public review. A Public Hearing on the Watershed
Management Plan is scheduled for the July 21St LMRWMO meeting. More
details about the Plan review and approval process will follow as the Public
Hearing date gets closer.
The deadline for registering for the LMRWMO interactive stormwater
management workshop is April 27th. The workshop is scheduled for the
morning of Saturday, April 30th from 9:30 to noon at the Science Museum of
Minnesota. The workshop is free, but registration will be required. RSVP
information can be found in the invitation e-mail. The workshop is focused
on stormwater management issues, is intended to be educational and
interactive, and is geared towards community and civic leaders. Anyone
interested in attending can contact Engineering Staff and we can provide the
RSVP information.
Stormwater Pond Assessment Request for Professional Services - Council
authorized Staff to seek professional services for assessing the water quality
treatment performance of three City stormwater ponds at their April 19th
meeting. Staff will be issuing a Request for Proposals (RFP) for consulting
firms to respond to. Staff will be asking consultants to assess the existing
performance of the three ponds for removing sediment and chemical
nutrients from the stormwater runoff, recommend actions to improve the
performance of the ponds, and provide cost estimates for the recommended
actions. The three ponds scheduled to be evaluated are Copperfield,
Burrows, and Park Place. Assessment of these ponds is anticipated during
the summer.
Rogers Lake Weed Control - Staff submitted the permit application to the
Department of Natural Resources (DNR). Staff anticipates hearing back
from the DNR by the first week in May. Midwest AquaCare is ready to apply
the herbicide treatment to the lake in early to mid-June pending the receipt
of the DNR permit.