Sep
The Parks Crew top dressed the outfields at Hagstrom King Park. Black dirt
was hauled in, leveled and grass seed put down. The bathrooms at
Kensington Park and Mendakota Park were washed down and cleaned. They
attended the safety meeting at city hall.
The Utility Crew did a fall inspection at the liftstations that included all
electrical, pulling the pumps, and checking the piping systems. Spraying of
weeds on all the pedways was finished. Broadleaf weeds were sprayed at
Kensingotn Parks and at the fire hall.
The Streets Crew marked the south side of Highway 110 Frontage Road for
no parking signs and called in locates. Class 5 gravel was brought in for the
Highway 110 Frontage Road for filling in the shoulder where it had washed
out. Blacktop patching was done on the pedway behind Parkview Plaza
around the water boxes. Potholes were filled on Decorah Lane at Apache
Street, Pagel Road, Havenview Road, and around the storm grate on
Medallion Drive.
Engineering
City Projects (construction year)
Lemay Lake Road Reconstruction (2012 - Storm sewer installation is
complete. Victory Lane, Kendon Lane and Furlong Avenue received the first
lift of asphalt. Substantial project completion is expected in October, and
an assessment hearing for the project is scheduled for the October 16th City
Council meeting.
Marie Avenue Rehabilitation (2012) -Sod is scheduled for installation next
week. The second lift of asphalt (wear course) is expected in late
September to early October. An assessment hearing for the project is
scheduled at the October 2nd City Council meeting.
Diane Road Neighborhood & Mendota Heights Road Rehabilitations (20121 -
These projects were completed earlier this summer. An Assessment
Hearing for the projects is scheduled at the October 2nd City Council
Meeting.
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013) -
The consultant is continuing work on design plans for the project and
coordination with MnDOT for project requirements. Staff has submitted a
scope change request for the Met Council to include the relocation of a small
portion of Interstate Valley Creek Trail, which is adjacent to the intersection.
A stakeholder letter is scheduled to be sent out this fall to get input into the
project design from interested parties. The consultant is scheduled to
present an update to City Council at their September 18th meeting.
Hunter Lane/Orchard Place Neighborhood Improvements (20131 - The
Feasibility Report for the project was approved at the August 21St City
Council Meeting, and a public hearing on the project was ordered for
October 2nd. There will be an informal neighborhood meeting on September
17th at City Hall. The formal public hearing on October 2nd will be part of the
regularly scheduled Council Meeting.
Crown Point & Overlook Neighborhood Rehabilitations (2013) - An
informational meeting was held on August 27th at City Hall. Residents that
attended were presented with the anticipated project schedule, scope of
work, and proposed assessments. A formal public hearing for the project is
scheduled before City Council at their September 18th meeting.
Verizon to Work On Fiber Optic Line at Historic Pilot Knob - Representatives
from Verizon will be working on the Historic Pilot Knob site next week to
adjust the elevation of their underground fiber optic lines. The work is
estimated to take approximately five days, and the disturbed areas will be
fully restored when the project is completed.
Old Sibley Memorial Highway - MnDOT has informed other affected
agencies, including the City of Mendota Heights, of their intention to vacate
the right-of-way for Old Sibley Memorial Highway from Highway 13 at
Mendota Heights Road to Highway 13 near Saint Peter's Church. MnDOT
has decided that before any open houses or other forms of public meetings
take place, they should meet with the Dakota County Board of
Commissioners and Mendota Heights City Council to discuss potential
alternatives. These meetings will likely be held over the winter.