Pipeline 09 28 2012N E W S The Pipeline
LETTER
Public Works
Engineering
Code Enforcement September 28, 2012
Public Works
The Parks crew painted hockey boards at Marie Park, Wentworth Park and
Friendly Hills Park. Broken sprinkler heads were repaired at city hall along
the driveway by the police garage. Updates were installed on the grounds
master mower. Tree limbs were trimmed along the pedway in Wentworth
Pa rk.
The Utilities Crew assisted with blacktop patching. Broadleaf weeds were
sprayed at Marie Avenue, Victoria Highlands Park, Valley Park, Wentworth
Park, and Ivy Park.
The Streets Crew finished up blacktop patching on Acacia Blvd., Acacia
Drive, and started on Center Pointe Curve. Crosswalk signs were put in
place on Huber Drive at Hampshire Drive. Trees and shrubs were trimmed
on Caren Road at Victoria looking south. A large willow tree was trimmed
on Mohican that was hanging into the street. They helped officer Larrive
and the Dakota County Drug Task Force destroy marijuana plants.
Engineering
City Projects (construction year)
Lemay Lake Road Reconstruction (2012) - Curb & Gutter installations are
virtually complete. Paving of the first lift has been completed. Contractor
will be restoring boulevards next week. Substantial project completion is
expected in early October, and an assessment hearing for the project is
scheduled for the October 16th City Council meeting. Wear course will be
installed later this fall.
Marie Avenue Rehabilitation (2012) - The project is nearing completion.
The final lift of Bituminous was installed Thursday and striping scheduled for
Friday. An assessment hearing for the project is scheduled at the October
2nd City Council meeting.
Diane Road Neighborhood & Mendota Heights Road Rehabilitations (20121 -
The contractor removed dead sod and seeded areas in the project. An
Assessment Hearing for the projects is scheduled at the October 2nd City
Council Meeting.
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013) -
The consultant is continuing work on design plans for the project and
coordination with MnDOT for project requirements, and has provided staff
with 60% design drawings for review. The consultant provided an update at
the September 18th City Council meeting. Not much detail was provided in
the presentation because MnDOT has not yet approved proposed details of
the improvements. Final plans are anticipated in late fall/early winter with
bidding and construction in 2013.
Hunter Lane/Orchard Place Neighborhood Improvements (20131 - The
public hearing for the project is scheduled for October 2nd. Staff anticipates
a large neighborhood turn out for the hearing.
Crown Point & Overlook Neighborhood Rehabilitations (2013) -Final plans
will be prepared and bids are anticipated in the spring for the 2013
construction season.