Pipeline 11 16 2012N E W S The Pipeline
LETTER
Public Works 1�
Engineering November 16, 2012
Code Enforcement fig
Public Works
The Parks Crew cleaned up downed trees and limbs in the parks and
pedways as needed after a rare November tornado ripped through part of
the city. Shrubs were trimmed around the park signs. Black dirt was put
down in Ivy Falls Park to fill in where trees had been uprooted and to fill
sink holes.
The Utility Crew assisted the Streets and Parks Crew with storm damage
clean up. The sanitary sewer and storm sewers were inspected at the St.
Thomas that Opus installed. Manholes makers were installed at Eagle Ridge
townhomes.
The Streets Crew was called in by the Fire Chief on Saturday night at 11:20
p.m. to help clean up downed trees on the north end of the city that were
blocking streets. George, John B, Rich and Cliff came in and worked until
late Sunday afternoon. They then spent the rest of the week picking up
trees and limbs on the north end and in Ivy Falls Park where four big spruce
trees blew over. Trees on Willow Lane weren't cleaned up until Tuesday
because of wires being tangled in them.
Engineering
City Projects (construction year)
Lemay Lake Road Reconstruction (2012I - Striping is scheduled early next
week. Minor punch list items will be completed in the spring.
Dodd Road/Highway 110 Intersection Pedestrian Improvements (2013) -An
update for City Council from the consultant is anticipated in December.
Final plans are anticipated in late fall/early winter with bidding and
construction in 2013.
Hunter Lane/Orchard Place Neiahborhood Improvements (2013) - Staff is
working on the final design and putting together the final plan set. A
second informational meeting is anticipated over the winter to go over
specific property design issues with affected residents. Final plan
completion is expected in March with construction starting in June 2013.
Crown Point & Overlook Neighborhood Rehabilitations (2013) -Staff is
working on the final design plans. If necessary, a neighborhood open house
will be held over the winter to work out specific design issues with property
owners. Final plans will be prepared anticipating spring 2013 construction.
Lexington Avenue Pedestrian Trail, Hwy 110 to Douglas Avenue (2013) -
Staff is preparing design plans for an overlay project for this trail to be
completed during the summer of 2013. Dakota County has included this
project in their Capital Improvement Plan (CIP) to augment project cost.
The City is responsible for 55% of the construction cost and design services,
and the County will provide 45% of the construction cost.
Storm Sewer Improvements - Gartzke Construction extended a culvert on
Wagon Wheel Trail and installed a culvert at Par 3. PAC construction
repaired a broken storm sewer in Valley Park. Kirchner Construction
repaired a storm sewer outlet at Wentworth Park and will be repairing some
catch basins around town next week.
Other Activities
Lower Mississippi River Watershed Management Organization (LMRWMO) -
Earlier this year, the LMRWMO began a study of the water quality and
possible pollution sources in several lakes including Rogers and Augusta
Lakes in Mendota Heights. They are beginning the second part of the study
which aims to understand the thoughts and visions of community members
and involve them in the plans for improving these lakes. A Community
Conversation Meeting is scheduled for November 15th at the Dakota Lodge
at Thompson County Park in West Saint Paul. The meeting is from 6:30-
8:00pm. For more information about this meeting go to the LMRWMO web
page at www.dakotaswcd.org/watersheds/lowermisswmo/wrapp.html.
Gun Club Lake Watershed Management Organization (GCLWMO� - The
Public Works Directors from the three member cities of the GCLWMO
(Mendota Heights, Inver Grove Heights, and Eagan) have been discussing
the future governance options for the GCLWMO. The GCLWMO's Watershed
Management Plan is in need of renewal, and the Board is discussing options
to make the organization more efficient and effective for its member Cities.
Five -Year Infrastructure Plans - Staff is working on updates for the Street
Improvement Plan (SIP) and the Sanitary Sewer Improvement and
Maintenance Plan (SSIMP). Projects within the plans are being prioritized
based on infrastructure need and available resources. The 2013-2017 plans
will be presented to City Council at the December 4th meeting. Once
acknowledged, the plans will be posted on the City's web -page.