The Parks Crew picked up downed limbs in Wentworth Park and at the
Public Works Garage. The storage box was brought in from Mendakota Park
that was used by Parks and Recreation. They continue to spray weeds in
the parks and pedways, where needed. Replacement boards were installed
in the hockey rinks, where needed.
The Utilities Crew cleaned sanitary sewer lines on North and South Freeway Road,
South Lane, Oak Street, and the easement near Mendota Plaza. Roots were cut
in the sanitary sewer line on Hingham Court, Chippewa Avenue, and Annapolis
Street. A sanitary sewer and storm sewer inspection was completed at Whispering
Pines at Mendota Plaza.
The Streets Crew made up elections signs, and picked up tree limbs on
Kirchner Avenue and along Hunter Lane. A new sign post was installed on
Medallion Drive and at Mayfield Heights Road at Highway 13. A bent sign
post was replaced at Mendakota Drive at Dodd Road. The bent gate at the
Pilot Knob site was fixed. The ditch line was cleaned out south on Lexington
Avenue because of a sight distance complaint.
Engineering
(2012) Lemay Lake Road Reconstruction - Stormwater pond construction is
complete, and storm sewer installation is under way. Pavement reclaiming
is also under way. Substantial project completion is expected in October,
and an assessment hearing for the project is scheduled for the October 16th
City Council meeting.
(2012) Marie Avenue Rehabilitation - The contractor has replaced worn or
damaged sections of curb, and is now making soil corrections in preparation
for placing pavement. Marie Avenue remains closed to through traffic. A
signed detour is provided. Construction is anticipated to last into
September. An assessment hearing for the project is scheduled at the
October 2nd City Council meeting.
(2013) Dodd Road/Highway 110 Intersection Pedestrian Improvements -
Staff and the consultant met with MnDOT representatives on site last week
to go over design details for the project. The detailed information received
will be incorporated into the plans for construction. Staff is preparing a
scope change request for the Met Council to include the relocation of a small
portion Interstate Valley Creek Trail, which is adjacent to the intersection.
A stakeholder letter is scheduled to be sent out this fall to get input into the
project design from interested parties. The consultant is scheduled to
present an update to City Council at their September 18th meeting.
(2013) Hunter Lane/Orchard Place Neighborhood Improvements - A resident
survey letter has been sent out to get preliminary issues identified for
preliminary project design. The Feasibility Report for the project is
scheduled for the August 21St City Council Meeting. If the Feasibility Report
is accepted by Council, a neighborhood meeting is scheduled for September
17th followed by a formal public hearing before City Council on October 2nd.
(2013) Crown Point & Overlook Neighborhood Rehabilitations - The
Feasibility Report for these projects was approved at the August 7th City
Council Meeting. A neighborhood meeting is scheduled for August 27th, and
a formal public hearing is scheduled before City Council at their September
18th meeting.
(2013) Highway 13 and Dodd Road Trail Construction - Staff is contacting
the consultant used originally for the design of trail gap connection projects
along Highway 13 and Dodd Road. These projects are programmed for
2013 construction. A grant application is necessary for funding to complete
the Dodd Road trail from Market Street to Marie Avenue. Application for a
DNR (Legacy funding) grant will be made early next year.
Engineering Intern Goes Back to School - This week, the Engineering
Ar
Department bid farewell to Kevin Shay, our
summer intern. Kevin is returning to
Purdue University, where he will be starting
his junior year in their Civil Engineering
program. Kevin provide much needed
assistance with our construction projects
this summer, and was extremely valuable in
helping get the data in our GIS system up-
to-date. Engineering staff took Kevin to
lunch, and he got to have his "exit
interview" in a very unique location (see
photo).
Interstate Valley Creek Trail (IVCT) Repairs - The following statement was
provided by Xcel Energy on the status of re -paving IVCT: "Xcel Energy's
gas department is undergoing a major system integrity project beginning
the week of August 13th. K S Energy Services is the company's contractor
that will be working in the area thru mid-October. Xcel Energy and K S
Energy Services will be utilizing the Valley Park trail to transport equipment
for the project work. Once their construction work is completed, the trail
will be restored and blacktopped. They are anticipating that the trail will be
completely restored by the late October/early November timeframe. Xcel
Energy extends its apologies for any inconvenience its project has created
for the Mendota Heights residents who utilize the Valley Park trail system."
Staff continues to work with Xcel and regular updates on their gas main
project, which will culminate with the re -paving of IVCT.
MnDOT Projects
The following projects are under the direction of MnDOT and Dakota County.
They are presented as information only. For more information on MnDOT
projects contact J.P. Gillach (651-234-7503, james.gillach@state.mn.us).
Old Sibley Memorial Highway - MnDOT has informed other affected
agencies, including the City of Mendota Heights, of their intention to give up
the right-of-way for Old Sibley Memorial Highway from Highway 13 at
Mendota Heights Road to Highway 13 near Saint Peter's Church. MnDOT
has decided that before any open houses or other forms of public meetings
take place, they should meet with the Dakota County Board of
Commissioners and Mendota Heights City Council to discuss potential
alternatives. These meetings will likely be held over the winter.